Project Management: The Managerial Process (Mcgraw-hill Series Operations and Decision Sciences)
7th Edition
ISBN: 9781259666094
Author: Erik W. Larson, Clifford F. Gray
Publisher: McGraw-Hill Education
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 6, Problem 14E
You are managing a product upgrade project for Bangkokagogo. Given the project network that follows, complete the forward and backward pass, compute activity slack, and identify the critical path. Use this information to create a Gantt chart for the project. Be sure to show slack for noncritical activities.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
Prepare a plan for a small project of moderate complexity (at least 12 activities, with some interdependencies between activities).
Your plan should identify the activity by their beginning and ending nodes and by short, descriptive titles. Estimate the times to
complete the activities. Prepare a PERT/CPM network. Determine critical path and the expected time for completing the project
(Activity Analysis and Event Analysis). Choose a project of some personal interest and knowledge (e.g. building a house, selling a
house, political campaign etc.) Your project will be judged by how completely it identifies all activities, the reasonableness of your
time estimates and the correctness of your analysis.
UPLOAD YOUR ANSWER HERE AS IMAGE/PDF.
From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path.How many days will the project take?
Construct the DATA SHEETS with ES, EF, LS, LF, TF, FF, AND INDF.
What is the duration of the project?
Identify the critical path.
How many days can ACTIVITY C be delayed without extending the duration of the whole project?
Chapter 6 Solutions
Project Management: The Managerial Process (Mcgraw-hill Series Operations and Decision Sciences)
Ch. 6 - How does the WBS differ from the project network?Ch. 6 - How are WBS and project networks linked?Ch. 6 - Why bother creating a WBS? Why not go straight to...Ch. 6 - Why is slack important to the project manager?Ch. 6 - What is the difference between free slack and...Ch. 6 - Why are lags used in developing project networks?Ch. 6 - What is a hammock activity, and when is it used?Ch. 6 - Here is a partial work breakdown structure for a...Ch. 6 - Draw a project network from the following...Ch. 6 - Draw a project network from the following...
Ch. 6 - Draw a project network from the following...Ch. 6 - Draw a project network from the following...Ch. 6 - From the following information, develop an AON...Ch. 6 - The project information for the custom order...Ch. 6 - You have signed a contract to build a garage for...Ch. 6 - You are creating a customer database for the...Ch. 6 - K. Nelson, project manager of Print Software....Ch. 6 - A large Southeast city is requesting federal...Ch. 6 - You are creating a customer database for the...Ch. 6 - You are completing a group term paper. Given the...Ch. 6 - You are managing a product upgrade project for...Ch. 6 - You are creating a database for the Oklahoma City...Ch. 6 - The planning department of an electronics firm has...Ch. 6 - Using Microsoft Project, set up the network and...Ch. 6 - The optical disk project team has started...Ch. 6 - From the following information, compute the early,...Ch. 6 - Given the following information, compute the...Ch. 6 - Given the information in the following lag...Ch. 6 - Given the network below, compute the early, late,...Ch. 6 - The CyClon project team has started gathering...Ch. 6 - Advantage Energy Technology Data Center...Ch. 6 - Advantage Energy Technology Data Center...Ch. 6 - Advantage Energy Technology Data Center...Ch. 6 - The GE Company is preparing a bid to build the new...Ch. 6 - The GE Company is preparing a bid to build the new...Ch. 6 - The G&E Company is preparing a bid to build the...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.Similar questions
- Programme evaluation and review technique (PERT) is a project management technique that employs three time estimates for each activity while Critical path method (CPM) uses only one-time factor per activity. However, both techniques deploy the same six basic steps. Describe and differentiate these steps. Need little long answer for this homework.thanks for your helparrow_forwardUse the Program Evaluation and Review Technique to represent the project in an activity network. In conjunction with the Critical Path Method, use the activity network to find the shortest time possible to complete the project, to identify the critical jobs in the project, and to determine the earliest and latest that each activity can start and finish without making the project completion longer.a=1, b=1, c=6, d=5, e=2, f=5; andab=1x1=1, bc=1x6=6, cd=6x5=30, de=5x2=10, ef=2x5=10, af=1x5=5.arrow_forwardThe following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Duration (weeks) Precedes B, C E F F Activity A (start) What is the total slack for the non critical path(s) in the project? BOE C F (end) 1 2. 2182 This exercise contains only parts b, c, and d. b) The activities on the critical path are c) The total project completion time for Rafay Ishfaq's software firm is weeks. (Enter your response as a whole number.) d) Determine the slack time for each of the activities. (Enter your responses as whole numbers.) ABC EF 11 Activity Slack Time (weeks) week(s) (Enter your response as a whole number.)arrow_forward
- A project's activities must be completed in the sequence indicated below. Activity Immediately Preceding Activity Duration in Weeks A - 3 B - 20 C - 15 D - 10 E - 5 F A 4 G D 3 H D, E 10 I F 3 J B 10 K G, H 7 L B, I 5 The project ends with the intersection of activities: C, J, K and L 1- Use CPM to construct (Draw) the project Network and find the critical path. 2- How long is the project expected to takearrow_forwardYou are the project manager of the software installation project in the table below. You would like to find the minımum-cost schedule for your project. There is a $500-per-week penalty for each week the project is delayed beyond week 25. In addition, your project team determined that indirect project costs are $2,000 per week. Normal Cost Crash Time Crash Cost ($) 3,000 3,000 10,000 Normal Time (weeks) Immediate Activity Predecessor(s) (weeks) (S) A 1 3,000 6,000 C A 9. 8. 12,000 8 2. А, В 10 3,000 9.000 4,000 5,000 2,000 3.000 5,000 9,000 7,000 12 6. E, F 2 1 G 5.000 C, F 8 2,000 8.000 a. What would be your target completion week? The target completion week is week (Enter your response as an integer.)arrow_forwardThe following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Duration (weeks) This exercise contains only parts b, c, and d. b) The activities on the critical path are A-B-F Activity A (start) BU C E F (end) 1 2362 10 Precedes B, C F E F c) The total project completion time for Rafay Ishfaq's software firm is 13 weeks. (Enter your response as a whole number.) d) Determine the slack time for each of the activities. (Enter your responses as whole numbers.) Activity Slack Time (weeks)arrow_forward
- Given the following network, What is the critical path? How long will it take to complete this project? The duration, in days, follows the letter of each activity. Can activity B be delayed without delaying the completion of the project? If so, how many days?arrow_forwardFrom the following information, develop an AON project network. Complete theforward and backward pass, compute activity slack, and identify the critical path.How many days will the project take?arrow_forwardDraw the network diagram based on the information given below. Calculate the ES, EF, LS, LF and slack for each activity and identify the critical path. Can the project be completed in 40 weeks? Activity Preceding Activity Time (Weeks) ES EF LS LF Slack A 10 B 8 C A, B 6 D A 8 E B 9 F C, D 7 G D, E 12 H F, G 10 b) Assume that activity A actually finished at the 9th week, activity B actually finished at the 10th Recalculate the expected project completion time. Which activities would you focus on in order to get the project back on schedule?arrow_forward
- Consider the project described in the table below: Activity Duration A B C D E F G H 9 4 8 8 5 7 4 6 OEST-9 and LCT = 15 OEST=9 and LCT = 13 Immediate Predecessor What is the earliest start time (EST) and latest completion time (LCT) of activity B? OEST=9 and LCT = 20 OEST-9 and LCT-17 - A A A B B,C C,D E,F,Garrow_forwardThe fo llowing is a table of activities associated with a project at Rafay lshfaq's software firm in Chicago, their durations, and what activities each must precede: a) Draw an AOA diagram of the project, including activity durations.b) Define the critical path, listing all critical activities in chronological order.c) What is the project completion time (in weeks)?d) What is the slack (in weeks) associated with any and all noncritical paths through the project?arrow_forwardA project schedule has the following characteristics: explain all the step to construct the network and find critical patharrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Understanding BusinessManagementISBN:9781259929434Author:William NickelsPublisher:McGraw-Hill EducationManagement (14th Edition)ManagementISBN:9780134527604Author:Stephen P. Robbins, Mary A. CoulterPublisher:PEARSONSpreadsheet Modeling & Decision Analysis: A Pract...ManagementISBN:9781305947412Author:Cliff RagsdalePublisher:Cengage Learning
- Management Information Systems: Managing The Digi...ManagementISBN:9780135191798Author:Kenneth C. Laudon, Jane P. LaudonPublisher:PEARSONBusiness Essentials (12th Edition) (What's New in...ManagementISBN:9780134728391Author:Ronald J. Ebert, Ricky W. GriffinPublisher:PEARSONFundamentals of Management (10th Edition)ManagementISBN:9780134237473Author:Stephen P. Robbins, Mary A. Coulter, David A. De CenzoPublisher:PEARSON
Understanding Business
Management
ISBN:9781259929434
Author:William Nickels
Publisher:McGraw-Hill Education
Management (14th Edition)
Management
ISBN:9780134527604
Author:Stephen P. Robbins, Mary A. Coulter
Publisher:PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract...
Management
ISBN:9781305947412
Author:Cliff Ragsdale
Publisher:Cengage Learning
Management Information Systems: Managing The Digi...
Management
ISBN:9780135191798
Author:Kenneth C. Laudon, Jane P. Laudon
Publisher:PEARSON
Business Essentials (12th Edition) (What's New in...
Management
ISBN:9780134728391
Author:Ronald J. Ebert, Ricky W. Griffin
Publisher:PEARSON
Fundamentals of Management (10th Edition)
Management
ISBN:9780134237473
Author:Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:PEARSON
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY