Calculate fixed
Boxer Manufacturing produces luxury dog houses. Each dog house requires 4.0 hours of machine time for its elaborate trim and finishing. For the current year, Boxer calculated its predetermined fixed manufacturing overhead (MOH) rate to be $26 per machine hour. The company budgets its fixed MOH to be $202,000 per month. Last month. Boxer produced 2,000 dog houses and incurred $198,400 (actual) of fixed MOH.
Requirements
- 1. Calculate the fixed overhead
budget variance . - 2. Calculate the fixed overhead volume variance.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Your company has received an order for 20 units of aproduct. Th e labor cost to produce the item is $9.50 per hour. Th esetup cost for the item is $60 and material costs are $25 per unit. Th e item is sold for $92. Th e learning rate is 80 percent. Overheadis assessed at a rate of 55 percent of unit labor cost.(a) Determine the average unit cost for the 20 units if the fi rstunit takes four hours.(b) Determine the minimum number of units that need to bemade before the selling price meets or exceeds the averageunit cost.
Boxer Manufacturing produces luxury dog houses. Each dog house requires 4.0 hours of machine time for its elaborate trim and finishing. For the current year, Boxer calculated its predetermined
fixed manufacturing overhead (MOH) rate to be $20 per machine hour. The company budgets its fixed MOH to be $202,000 per month. Last month, Boxer produced 2,000 dog houses and incurred
$196,400 (actual) of fixed MOH.
Read the requirements.
Requirement 1. Calculate the fixed overhead budget variance
Begin by determining the formula for the fixed overhead budget variance, then compute the variance. (Enter the variance as a positive number. Label the variance as favorable (F) or unfavorable (U)
in the input field after the amount you enter.)
Fixed MOH
budget variance
Learning CurveBordner Company manufactures HVAC (heating, ventilation, and air conditioning) systems for commercial buildings. For each new design, Bordner faces a 90 percent learning rate. On aver-age, the first unit of a new design takes 600 hours. Direct labor is paid $25 per hour.
Required:1. Set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours, and cumulative total time in hours. Show results by row for total pro-duction of one unit, two units, four units, eight units, and sixteen units. (Round hour answers to two significant digits.)
2. What is the total labor cost if Bordner makes the following number of units: one, four, sixteen? What is the average cost per system for the following number of systems: one, four, or sixteen? (Round your answers to the nearest dollar.)
3. Using the logarithmic function, set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours,…
Chapter 11 Solutions
Managerial Accounting (5th Edition)
Ch. 11 - (Learning Objective 1) Which of the following is...Ch. 11 - (Learning Objective 2) The direct material price...Ch. 11 - Prob. 3QCCh. 11 - Prob. 4QCCh. 11 - Prob. 5QCCh. 11 - (Learning Objective 4) Which of the following is...Ch. 11 - Prob. 7QCCh. 11 - (Learning Objective 6) Which of the following is...Ch. 11 - Prob. 9QCCh. 11 - (Learning Objective 7Appendix) Which of the...
Ch. 11 - Compute the standard cost of direct materials...Ch. 11 - Compute the standard cost of direct labor...Ch. 11 - Explain a direct material variance (Learning...Ch. 11 - Prob. 11.4SECh. 11 - Calculate direct material variances when the...Ch. 11 - Calculate direct labor variances (Learning...Ch. 11 - Prob. 11.7SECh. 11 - Prob. 11.8SECh. 11 - Calculate fixed overhead variances (Learning...Ch. 11 - Calculate and interpret fixed overhead variances...Ch. 11 - Prob. 11.11SECh. 11 - Calculate and interpret overhead variances...Ch. 11 - Record costing transactions (Learning Objective 7)...Ch. 11 - Record standard costing transactions (Learning...Ch. 11 - Identify ethical standards violated (Learning...Ch. 11 - Vocabulary (Learning Objectives 1, 2, 3, 4, 5, 6)...Ch. 11 - Calculate standard cost and gross profit per unit...Ch. 11 - Calculate standard cost per unit (Learning...Ch. 11 - Calculate and explain direct material variances...Ch. 11 - Calculate missing direct material variables...Ch. 11 - Calculate and explain direct labor variances...Ch. 11 - Calculate and interpret direct material and direct...Ch. 11 - Calculate the material and labor variances...Ch. 11 - Record materials and labor transactions (Learning...Ch. 11 - Calculate the standard cost of a product before...Ch. 11 - Recognize advantages and disadvantages of standard...Ch. 11 - Compute and interpret overhead variances (Learning...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Make journal entries in a standard costing system...Ch. 11 - Prepare a standard cost income statement (Learning...Ch. 11 - Calculate standard cost and gross profit per unit...Ch. 11 - Calculate the standard cost per unit (Learning...Ch. 11 - Calculate and explain direct material variances...Ch. 11 - Calculate missing direct material variables...Ch. 11 - Calculate and explain direct labor variances...Ch. 11 - Prob. 11.38BECh. 11 - Prob. 11.39BECh. 11 - Prob. 11.40BECh. 11 - Prob. 11.41BECh. 11 - Recognize advantages and disadvantages of standard...Ch. 11 - Calculate and interpret overhead variances...Ch. 11 - Prob. 11.44BECh. 11 - Prob. 11.45BECh. 11 - Prob. 11.46BECh. 11 - Prob. 11.47BECh. 11 - Prob. 11.48BECh. 11 - Prob. 11.49APCh. 11 - Comprehensive standards and variances problem...Ch. 11 - Comprehensive standards and variances problem...Ch. 11 - Prob. 11.52APCh. 11 - Prob. 11.53APCh. 11 - Prob. 11.54BPCh. 11 - Comprehensive standards and variances problem...Ch. 11 - Comprehensive standards and variances problem...Ch. 11 - Work backward through labor variances (Learning...Ch. 11 - Determine all variances and make journal entries...Ch. 11 - Calculate labor variances in a hotel (Learning...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Bordner Company manufactures HVAC (heating, ventilation, and air conditioning) systems for commercial buildings. For each new design, Bordner faces a 90 percent learning rate. On average, the first unit of a new design takes 600 hours. Direct labor is paid 25 per hour. Required: 1. Set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours, and cumulative total time in hours. Show results by row for total production of one unit, two units, four units, eight units, and sixteen units. (Round hour answers to two significant digits.) 2. What is the total labor cost if Bordner makes the following number of units: one, four, sixteen? What is the average cost per system for the following number of systems: one, four, or sixteen? (Round your answers to the nearest dollar.) 3. Using the logarithmic function, set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours, cumulative total time in hours, and the time for the last unit. Show results by row for each of units one through eight. (Round answers to two significant digits.)arrow_forwardYour firm designs training materials for computer training classes, and you have just received a request to bid on a contract to produce a complete set of training manuals for an 8-session class. From previous experience, you know that your firm follows a 90% learning rate. For this contract, it appears that the effort will be substantial, running 400 hours for the first session. Your firm has an average cost of labor of $60/hour and the overhead is expected to run a fixed $1000 per session. The customer will pay you a flat fixed rate per session (Per Session Price.) If your profit markup is 12%, what will be the Total Price, the Per Session Price, and at what session will you break even? Answer the following four questions: What is the Total Price? This is what you would charge the customer so that you can have your profit markup of 10% over all of your costs. To calculate this, first figure out your cost per each session, add them up, and then add your profit. What is the Per…arrow_forwardA University produces two courses for its Management students this year. MATA32 and MATA33. Each student taking MATA32 requires 6 hours of teaching, 2 hours of adminis- tration, with a revenue of $1300. Each student taking MATA33 requires 7 hours of teaching, 1 hour of administration with a revenue of $1700. Due to the University's resources, there is a maximum of 2010 teaching hours and 150 administration hours. The University must also admit at least 30 MATA32 and at least 30 MATA33 students due to government regulation. What is the maximum revenue? (A) 90000 (B) 129000 (C) 188000 (D) 192500 (E) None of the abovearrow_forward
- The following scenario relates to 5 questions. Bear Co has developed a new model of television. The estimated labour time for the first unit is 12 hours but a learning curve of 75% is expected to apply for the first eight units produced Note: The learning index for a 75% learning curve is -0.415. Overhead production costs must be estimated based on a previous model, the Leonardo, that was made by Bear Co. Production quantities and total overhead costs for the last four months of production of the Leonardo were as follows: Month Output Total overhead cost (units) $ September 1,800 278,200 October 2,000 310,000 November 1,700 252,900 December 200,000 1,000 You have been asked to estimate the variable overhead cost per unit of the new television by assuming that it will be the same as for the Leonardo, using the information provided for the last four months of its manufacture, and applying a 6% inflation rate. What is the variable cost per unit using the high-low method (to two decimal…arrow_forwardThe following scenario relates to 5 questions. Bear Co has developed a new model of television. The estimated labour time for the first unit is 12 hours but a learning curve of 75% is expected to apply for the first eight units produced Note: The learning index for a 75% learning curve is-0-415. Overhead production costs must be estimated based on a previous model, the Leonardo, that was made by Bear Co. Production quantities and total overhead costs for the last four months of production of the Leonardo were as follows: Month Output Total overhead cost (units) $ September 1,800 278,200 October 2,000 310,000 November 1,700 252,900 December 1,000 200,000 The first phase of production has now been completed for the new television. The first unit actually took 12-5 hours to make and the total time for the first eight units was 34-3 hours, at which point the learning effect came to an end. What is the actual learning rate, and did the labour force learn more quickly or less quickly than…arrow_forwardThe cutting department of Legacy Production Company started 40,000 units of specialized chairs during the month of March. The department incurred $15,000 in direct material costs; 2,500 direct labor hours paid at $10 per hour; and manufacturing overhead applied at 150% of direct labor cost. Legacy Production Company uses process costing to accumulate costs. NOTE: There was no beginning inventory in March. Required (Excel Template downloadProvided): (Module Learning Outcomes LO5.1 through LO5.5 AND Course Learning Outcome #1 & #2) Calculate the conversion costs incurred during the month of March (show your calculations). Assume, that only 30,000 units were completed and transferred out. The remaining units left in ending inventroy are only 70% complete with respect to conversion costs. Direct materials are added at the beginning of the process. Prepare a Cutting Department cost production report for the month of March Refer to the cost production report in part b. What are…arrow_forward
- The Beacon Hills High School entered into a contract with Beacon Printing Services which stipulates that the latter shall produce 10,000 sets of modules to be distributed to learners during the 1st quarter of the school year. The contract further states that Beacon Printing Services shall charge Beacon Hills High School at 20% above cost. Overhead costs are applied at the rate of P 10.00 per hour. After the job was completed, it was found out that 2,000 sets were determined to be spoiled due to significant errors. Fortunately, the 2,000 spoiled sets can be sold to a scrap buyer for P 3.00 per set. Direct costs charged to the job are: Materials – P 300,000 and Direct Labor (P15.00 per hour) – P 60,000. Only 8,000 sets were delivered to Beacon Hills High School. FIND: How much should be charged to Work In Process to record production cost? How much should be charged to Spoiled Good Inventory? What is the total cost of the finished goods inventory assuming that spoilage is to be…arrow_forwardThe manufacturing process of a new product is very labor intensive. The learning curve percentage (LC) for the process is 90%. It took 30 hours with 15 workers together to produce the first product. The average labor cost including overhead expenses is about $20 per hour. (a) Estimate the labor cost (including overhead expenses) to produce the tenth product? (Hint: 2 steps. How long is T_10? How much is the cost?) (b) A new training program is intended to lower the learning-curve percentage by 10% (minus 10%). If the program is successful, what cost savings will be realized for the tenth unit? (Hint: How long is the new T_10? How much is the new cost? How much is the cost saving?)arrow_forwardShaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows. Overhead Cost Pools Amount Purchasing $75,000 Handling materials 82,000 Production (cutting, milling, finishing) 210,000 Setting up machines 100,000 Inspecting 96,000 Inventory control (raw materials and finished goods) 126,000 Utilities 450,000 Total budgeted overhead costs $1,139,000 For the last 4 years, Shaker Stairs Co. has been charging overhead to products on the basis of machine hours. For the year 2020, 100,000 machine hours are budgeted.Jeremy Nolan, owner-manager of Shaker Stairs Co., recently directed his accountant, Bill Seagren, to implement the activity-based costing system that he has…arrow_forward
- Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows. Overhead Cost Pools Amount Purchasing $75,000 Handling materials 82,000 Production (cutting, milling, finishing) 210,000 Setting up machines 100,000 Inspecting 120,000 Inventory control (raw materials and finished goods) 126,000 Utilities 450,000 Total budgeted overhead costs $1,163,000 For the last 4 years, Shaker Stairs Co. has been charging overhead to products on the basis of machine hours. For the year 2020, 100,000 machine hours are budgeted.Jeremy Nolan, owner-manager of Shaker Stairs Co., recently directed his accountant, Bill Seagren, to implement the activity-based costing system that he has…arrow_forwardNUBD manufactures specialty components for the electronics industry in a highly labor intensive environment. ABC Electronics has asked Lake to bid on a component that NUBD made for ABC last month. The previous order was for 80 units and required 160 hours of direct labor to manufacture. ABC would now like 560 additional components. NUBD experiences an 80% learning curve on all of its jobs. The number of direct labor hours needed for NUBD to complete the 560 additional components is?arrow_forwardThe following information is provided to you: Time taken to produce first 8 shock pads 640 hours Time taken to produce first 16 shock pads 1200 hours Calculate the learning curve The following information is provided to you: Direct labour needed to make first machine. 1000 hoursLearning curve. 80%Direct labour cost. R300 per hourDirect materials cost. R180000 per machine Fixed cost for machines at each cumulative production R800000 Calculate the total direct hours required to manufacture four (4) machines. ( Indicate both average time per unit as well as cumulative time per unit for all theunits) Calculate the total costs to manufacture 4 machinesarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
What is variance analysis?; Author: Corporate finance institute;https://www.youtube.com/watch?v=SMTa1lZu7Qw;License: Standard YouTube License, CC-BY