Textbook Question
Chapter 11, Problem 11.6SE
Calculate direct labor variances (Learning Objective 3)
Edelman Oil performs oil changes. The standard wage rate for oil change technicians is $17 per hour. By analyzing its past records of time spent on oil changes, the company has developed a standard of 18 minutes (or 0.30 hours) per oil change.
In July, 1,600 oil changes were performed at Edelman Oil. Oil change technicians worked a total of 310 direct labor hours at an average rate of $24 per hour.
Requirements
- 1. Calculate the direct labor rate variance.
- 2. Calculate the direct labor efficiency variance.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
to complete the first setup on a new machine took an employee 250 minutes. using 72%
cumulative average - time learning curve indicated that the second setup on the new
machine is expected to take. answer choices: a.) 110 minutes b.) 90 minutes c.) 180
minutes d.) 215 minutes
The cutting department of Legacy Production Company started 40,000 units of specialized chairs during the month of March. The department incurred $15,000 in direct material costs; 2,500 direct labor hours paid at $10 per hour; and manufacturing overhead applied at 150% of direct labor cost. Legacy Production Company uses process costing to accumulate costs. NOTE: There was no beginning inventory in March.
Required (Excel Template downloadProvided): (Module Learning Outcomes LO5.1 through LO5.5 AND Course Learning Outcome #1 & #2)
Calculate the conversion costs incurred during the month of March (show your calculations).
Assume, that only 30,000 units were completed and transferred out. The remaining units left in ending inventroy are only 70% complete with respect to conversion costs. Direct materials are added at the beginning of the process. Prepare a Cutting Department cost production report for the month of March
Refer to the cost production report in part b. What are…
Foto-Fast Copy Shop provides a variety of photocopying and printing services. On June 5, the owner invested in some computer-aided photography equipment that enables customers to reproduce a picture or illustration, input it digitally into the computer, enter text into the computer, and then print out a four-color professional quality brochure. Prior to the purchase of this equipment, Foto-Fast Copy Shop’s overhead averaged $37,500 per year. After the installation of the new equipment, the total overhead increased to $90,000 per year. Foto-Fast Copy Shop has always costed jobs on the basis of actual materials and labor plus overhead assigned using apredetermined overhead rate based on direct labor hours. Budgeted direct labor hours for theyear are 7,500, and the wage rate is $8 per hour.Required:1. What was the predetermined overhead rate prior to the purchase of the new equipment?2. What was the predetermined overhead rate after the new equipment was purchased?3. Suppose Rick Anselm…
Chapter 11 Solutions
Managerial Accounting (5th Edition)
Ch. 11 - (Learning Objective 1) Which of the following is...Ch. 11 - (Learning Objective 2) The direct material price...Ch. 11 - Prob. 3QCCh. 11 - Prob. 4QCCh. 11 - Prob. 5QCCh. 11 - (Learning Objective 4) Which of the following is...Ch. 11 - Prob. 7QCCh. 11 - (Learning Objective 6) Which of the following is...Ch. 11 - Prob. 9QCCh. 11 - (Learning Objective 7Appendix) Which of the...
Ch. 11 - Compute the standard cost of direct materials...Ch. 11 - Compute the standard cost of direct labor...Ch. 11 - Explain a direct material variance (Learning...Ch. 11 - Prob. 11.4SECh. 11 - Calculate direct material variances when the...Ch. 11 - Calculate direct labor variances (Learning...Ch. 11 - Prob. 11.7SECh. 11 - Prob. 11.8SECh. 11 - Calculate fixed overhead variances (Learning...Ch. 11 - Calculate and interpret fixed overhead variances...Ch. 11 - Prob. 11.11SECh. 11 - Calculate and interpret overhead variances...Ch. 11 - Record costing transactions (Learning Objective 7)...Ch. 11 - Record standard costing transactions (Learning...Ch. 11 - Identify ethical standards violated (Learning...Ch. 11 - Vocabulary (Learning Objectives 1, 2, 3, 4, 5, 6)...Ch. 11 - Calculate standard cost and gross profit per unit...Ch. 11 - Calculate standard cost per unit (Learning...Ch. 11 - Calculate and explain direct material variances...Ch. 11 - Calculate missing direct material variables...Ch. 11 - Calculate and explain direct labor variances...Ch. 11 - Calculate and interpret direct material and direct...Ch. 11 - Calculate the material and labor variances...Ch. 11 - Record materials and labor transactions (Learning...Ch. 11 - Calculate the standard cost of a product before...Ch. 11 - Recognize advantages and disadvantages of standard...Ch. 11 - Compute and interpret overhead variances (Learning...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Make journal entries in a standard costing system...Ch. 11 - Prepare a standard cost income statement (Learning...Ch. 11 - Calculate standard cost and gross profit per unit...Ch. 11 - Calculate the standard cost per unit (Learning...Ch. 11 - Calculate and explain direct material variances...Ch. 11 - Calculate missing direct material variables...Ch. 11 - Calculate and explain direct labor variances...Ch. 11 - Prob. 11.38BECh. 11 - Prob. 11.39BECh. 11 - Prob. 11.40BECh. 11 - Prob. 11.41BECh. 11 - Recognize advantages and disadvantages of standard...Ch. 11 - Calculate and interpret overhead variances...Ch. 11 - Prob. 11.44BECh. 11 - Prob. 11.45BECh. 11 - Prob. 11.46BECh. 11 - Prob. 11.47BECh. 11 - Prob. 11.48BECh. 11 - Prob. 11.49APCh. 11 - Comprehensive standards and variances problem...Ch. 11 - Comprehensive standards and variances problem...Ch. 11 - Prob. 11.52APCh. 11 - Prob. 11.53APCh. 11 - Prob. 11.54BPCh. 11 - Comprehensive standards and variances problem...Ch. 11 - Comprehensive standards and variances problem...Ch. 11 - Work backward through labor variances (Learning...Ch. 11 - Determine all variances and make journal entries...Ch. 11 - Calculate labor variances in a hotel (Learning...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Bordner Company manufactures HVAC (heating, ventilation, and air conditioning) systems for commercial buildings. For each new design, Bordner faces a 90 percent learning rate. On average, the first unit of a new design takes 600 hours. Direct labor is paid 25 per hour. Required: 1. Set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours, and cumulative total time in hours. Show results by row for total production of one unit, two units, four units, eight units, and sixteen units. (Round hour answers to two significant digits.) 2. What is the total labor cost if Bordner makes the following number of units: one, four, sixteen? What is the average cost per system for the following number of systems: one, four, or sixteen? (Round your answers to the nearest dollar.) 3. Using the logarithmic function, set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours, cumulative total time in hours, and the time for the last unit. Show results by row for each of units one through eight. (Round answers to two significant digits.)arrow_forwardThe following scenario relates to 5 questions. Bear Co has developed a new model of television. The estimated labour time for the first unit is 12 hours but a learning curve of 75% is expected to apply for the first eight units produced Note: The learning index for a 75% learning curve is-0-415. Overhead production costs must be estimated based on a previous model, the Leonardo, that was made by Bear Co. Production quantities and total overhead costs for the last four months of production of the Leonardo were as follows: Month Output Total overhead cost (units) $ September 1,800 278,200 October 2,000 310,000 November 1,700 252,900 December 1,000 200,000 The first phase of production has now been completed for the new television. The first unit actually took 12-5 hours to make and the total time for the first eight units was 34-3 hours, at which point the learning effect came to an end. What is the actual learning rate, and did the labour force learn more quickly or less quickly than…arrow_forwardThe manager of a crew that installs wood floors has tracked the crew’s output over the past several weeks. Each worker works 40 hours per week, and earns $21 per hour. The wholesale cost of lumber to the company is $6 per square foot, and the company charges its customers $15 per square foot of flooring installed. The firm’s overhead rate is 150%. Week Crew Size Lumber Used (sq. ft) Flooring Installed (sq ft) 1 4 480 420 2 2 250 238 a. Calculate labor productivity for each of the weeks shown. Use the best measure of output and labor available. b. Now calculate multifactor productivity for each of the weeks shown. Explain your results imply in terms of dollars of outputarrow_forward
- The Beacon Hills High School entered into a contract with Beacon Printing Services which stipulates that the latter shall produce 10,000 sets of modules to be distributed to learners during the 1st quarter of the school year. The contract further states that Beacon Printing Services shall charge Beacon Hills High School at 20% above cost. Overhead costs are applied at the rate of P 10.00 per hour. After the job was completed, it was found out that 2,000 sets were determined to be spoiled due to significant errors. Fortunately, the 2,000 spoiled sets can be sold to a scrap buyer for P 3.00 per set. Direct costs charged to the job are: Materials – P 300,000 and Direct Labor (P15.00 per hour) – P 60,000. Only 8,000 sets were delivered to Beacon Hills High School. FIND: How much should be charged to Work In Process to record production cost? How much should be charged to Spoiled Good Inventory? What is the total cost of the finished goods inventory assuming that spoilage is to be…arrow_forwardThe following scenario relates to 5 questions. Bear Co has developed a new model of television. The estimated labour time for the first unit is 12 hours but a learning curve of 75% is expected to apply for the first eight units produced Note: The learning index for a 75% learning curve is -0.415. Overhead production costs must be estimated based on a previous model, the Leonardo, that was made by Bear Co. Production quantities and total overhead costs for the last four months of production of the Leonardo were as follows: Month Output Total overhead cost (units) $ September 1,800 278,200 October 2,000 310,000 November 1,700 252,900 December 200,000 1,000 You have been asked to estimate the variable overhead cost per unit of the new television by assuming that it will be the same as for the Leonardo, using the information provided for the last four months of its manufacture, and applying a 6% inflation rate. What is the variable cost per unit using the high-low method (to two decimal…arrow_forwardGuillermo's Oil and Lube Company is a service company that offers oil changes and lubrication for automobiles and light trucks. On average, Guillermo has found that a typical oil change takes 30 minutes and 6.2 quarts of oil are used. In June, Guillermo's Oil and Lube had 960 oil changes. Guillermo's Oil and Lube Company provided the following information for the production of oil changes during the month of June:Actual number of oil changes performed: 960Actual number of direct labor hours worked: 472 hoursActual rate paid per direct labor hour: $14.50Standard rate per direct labor hour: $14.00 Required: If required, round your answers to the nearest cent. 1. Calculate the direct labor rate variance (LRV) and the direct labor efficiency variance (LEV) for June using the formula approach. Direct labor rate variance (LRV) $______ Fvaorable or Unfavorable Direct labor efficiency variance (LEV) $_______ Favorable or Unfavorable 2. Calculate the total direct labor variance for…arrow_forward
- wage ige per hour. By analyzing its past records of time spent on oil changes, the company has developed a standard of 21 minutes (or 0.35 hours) per oil change. In July, 1,000 oil changes were performed at Fiber Oil. Oil change technicians worked a total of 290 direct labor hours at an average rate of $25 per hour. Read the requirements. enter. Abbreviations used: DL = Direct labor.) Actual hours x ( *($ 290 x ( Standard rate X 16.00 $ Actual rate 25.00 = DL rate variance U Requirement 2. Calculate the direct labor efficiency variance. Determine the formula for the efficiency variance, then compute the efficiency variance for the direct labor. (Enter the variance as a positive number. Enter currency amounts in the formula to the nearest cent and then round the final variance amount to the nearest whole dollar. Label the variance as favorable (F) or unfavorable (U) in the input field after the amount you enter. Abbreviations used: DL= Direct labor.) = $ 2,610 = DL efficiency variancearrow_forwardGuillermo's Oil and Lube Company is a service company that offers oil changes and lubrication for automobiles and light trucks. On average, Guillermo has found that a typical oil change takes 30 minutes and 6.4 quarts of oil are used. In June, Guillermo's Oil and Lube had 1,000 oil changes. Guillermo's Oil and Lube Company provided the following information for the production of oil changes during the month of June: Actual number of oil changes performed: 1,000Actual number of quarts of oil used: 6,960 quartsActual price paid per quart of oil: $5.30Standard price per quart of oil: $5.25 1. What if the actual number of quarts of oil purchased in June had been 6880 quarts, and the materials price variance was calculated at the time of purchase? If required, round your answers to the nearest cent. What would be the materials price variance (MPV)? What would be the materials usage variance (MUV)?arrow_forwardYour company has received an order for 20 units of aproduct. Th e labor cost to produce the item is $9.50 per hour. Th esetup cost for the item is $60 and material costs are $25 per unit. Th e item is sold for $92. Th e learning rate is 80 percent. Overheadis assessed at a rate of 55 percent of unit labor cost.(a) Determine the average unit cost for the 20 units if the fi rstunit takes four hours.(b) Determine the minimum number of units that need to bemade before the selling price meets or exceeds the averageunit cost.arrow_forward
- According to the National Education Association (NEA), teachers generally spend more than 40 hours each week working on instructional duties. The following data show the number of hours worked per week for a sample of 13 high school science teachers and a sample of 11 high school English teachers. High school science teachers 53 56 54 54 55 58 49 61 54 54 52 53 54 High school English teachers 52 47 50 46 47 48 49 46 55 44 47 a. What is the median number of hours worked per week for the sample of 13 high school science teachers? b. What is the median number of hours worked per week for the sample of 11 high school English teachers? c. Create a box plot for the number of hours worked for high school science teachers. d. Create a box plot for the number of hours worked for high school English teachers. e. Comment on the differences between the box plots for science and English teachers.arrow_forwardCodeHead Software Inc. does software development. One important activity in software development is writing software code. The manager of the WordPro Development Team determined that the average software programmer could write 25 lines of code in an hour. The plan for the first week in May called for 4,650 lines of code to be written on the WordPro product. The WordPro Team has five programmers. Each programmer is hired from an employment firm that requires temporary employees to be hired for a minimum of a 40-hour week. Programmers are paid 32.00 per hour. The manager offered a bonus if the team could generate more lines for the week, without overtime. Due to a project emergency, the programmers wrote more code in the first week of May than planned. The actual amount of code written in the first week of May was 5,650 lines, without overtime. As a result, the bonus caused the average programmers hourly rate to increase to 40.00 per hour during the first week in May. Instructions 1. If the team generated 4,650 lines of code according to the original plan, what would have been the labor time variance? 2. What was the actual labor time variance as a result of generating 5,650 lines of code? 3. What was the labor rate variance as a result of the bonus? 4. The manager is trying to determine if a better decision would have been to hire a temporary programmer to meet the higher programming demand in the first week of May, rather than paying out the bonus. If another employee was hired from the employment firm, what would have been the labor time variance in the first week? 5. Which decision is better, paying the bonus or hiring another programmer?arrow_forwardEthics in Action In August, Lannister Company introduced a new performance measurement system in manufacturing operations. One of the new performance measures is lead time, which is determined by tagging a random sample of items with a log sheet throughout the month. The log sheets recorded the time that the sample items started production and the time that they ended production, as well as all steps in between. At the end of the month, the controller collected the log sheets and computed the average lead time of the tagged products. This number was reported to central management and was used to evaluate the performance of the plant manager. Because of the poor lead time results reported for August, the plant was under extreme pressure to reduce lead time in September. The following memo was intercepted by the controller. Date: September 3 To: Hourly Employees From: Plant Manager During last month, you may have noticed that some of the products were tagged with a log sheet. This sheet records the time that a product enters production and the time that it leaves production. The difference between these two times is termed the lead time. Our plant is evaluated on improving lead time. From now on, I ask all of you to keep an eye out for the tagged items. When you see a tagged item, it is to receive special attention. Work on that item first, and then immediately move it to the next operation. Under no circumstances should tagged items wait on any other work that you have. Naturally, report accurate information. I insist that you record the correct times on the log sheet as the product goes through your operations. How should the controller respond to this discovery?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningEssentials of Business Analytics (MindTap Course ...StatisticsISBN:9781305627734Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. AndersonPublisher:Cengage LearningManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College Pub
- Financial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Essentials of Business Analytics (MindTap Course ...
Statistics
ISBN:9781305627734
Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:Cengage Learning
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
What is variance analysis?; Author: Corporate finance institute;https://www.youtube.com/watch?v=SMTa1lZu7Qw;License: Standard YouTube License, CC-BY