Chapter 11, Problem 11.56BP

Comprehensive standards and variances problem (Learning Objectives 1, 2, 3, 4, 5, & 6)

Dolson Manufacturing produces ceramic teapots. Dolson allocates overhead based on the number of direct labor hours. The company is looking into using a standard cost system and has developed the following standards (one “unit” is a batch of 100 teapots).

Standards:
Direct material 70 pounds per batch at $4.00 per pound
Direct labor 3.0 hours per batch at $19.00 per hour
Variable MOH standard rate $3.00 per direct labor hour
Predetermined fixed MOH standard rate $6.00 per direct labor hour
Total budgeted fixed MOH cost $1,560

Actual cost and operating data from the most recent month follows:

Purchased 5,670 pounds at a cost of $3.90 per pound
Used 5,000 pounds in producing 70 batches
Actual direct labor cost of $4,554 at an average direct labor cost per hour of $19.80
Actual variable MOH cost $736
Actual fixed MOH cost $1,660

All manufacturing overhead is allocated on the basis of direct labor hours.

Requirements

  1. 1. Calculate the standard cost of one batch.
  2. 2. Calculate the following variances:
    1. a. The direct material variances.
    2. b. The direct labor variances.
    3. c. The variable manufacturing overhead variances.
    4. d. The fixed manufacturing overhead variances.
  3. 3. Have the company’s managers done a good job or a poor job controlling materials, labor, and overhead costs? Why or why not?
  4. 4. Describe how the company’s managers can benefit from the standard costing system. Do you think the company should continue with the standard cost system?
Blurred answer
Students have asked these similar questions
Healthfirst (HF) Ltd has recently started to produce a face shield and product's standard cost data are as follows: Cost per unit Direct materials Perspex (0.5 meters @ $15 per meter) $ 7.50 Direct materials Hardened Plastic (0.25 meters at $20.00 per meter) 5.00 Direct manufacturing labour (0.5 hr @ $30.00 per hr) Manufacturing overhead Total Cost 15.00 Required Should HF accept the offer. Show all computations. 30.00 $57.50 Additional information 45% of the Manufacturing overhead changes with the number of units produced. Additionally, if production of face shields is discontinued, 20% of the remaining fixed cost will be avoided. The budgeted production used to compute overheads is 10,000 units per quarter. HF has been approached by another company who is willing to supply the face shields at $50. Per unit. The space used to manufacture face shields can be used to Generate $ 120,000 in contribution margin per quarter.
Average labor cost for the first 700 units of a product is RO 50 and the average labor cost of first 1400 units is RO 45. Average time per unit is 100 minutes. The learning ratio and the average labour cost for first 2800 units will be: a. 80% and RO 36.000 b. 90% and RO 40.500 c. 85% and RO 38.250 d. 95% and RO 42.750
Catch a Wave Company manufactures surfboards.  Its standard cost information follows:                                                             Standard          Standard Price                        Standard Unit                                                             Quantity          (Rate)                                      Cost                                         Fiberglass                                           15 sq. ft.          $5 per sq. ft.                            $75.00 Direct labor                                         10 hrs              $15 per hour                           150.00 Variable manufacturing overhead                              $6 per direct labor hour            60.00 Fixed manufacturing overhead                                   $8 per direct labor hour            80.00   The company expected to require 2,500 hours of direct labor.   Catch a Wave has the following actual results for the month of June:                         Number of…

Chapter 11 Solutions

Managerial Accounting (5th Edition)

Ch. 11 - Compute the standard cost of direct materials...Ch. 11 - Compute the standard cost of direct labor...Ch. 11 - Explain a direct material variance (Learning...Ch. 11 - Prob. 11.4SECh. 11 - Calculate direct material variances when the...Ch. 11 - Calculate direct labor variances (Learning...Ch. 11 - Prob. 11.7SECh. 11 - Prob. 11.8SECh. 11 - Calculate fixed overhead variances (Learning...Ch. 11 - Calculate and interpret fixed overhead variances...Ch. 11 - Prob. 11.11SECh. 11 - Calculate and interpret overhead variances...Ch. 11 - Record costing transactions (Learning Objective 7)...Ch. 11 - Record standard costing transactions (Learning...Ch. 11 - Identify ethical standards violated (Learning...Ch. 11 - Vocabulary (Learning Objectives 1, 2, 3, 4, 5, 6)...Ch. 11 - Calculate standard cost and gross profit per unit...Ch. 11 - Calculate standard cost per unit (Learning...Ch. 11 - Calculate and explain direct material variances...Ch. 11 - Calculate missing direct material variables...Ch. 11 - Calculate and explain direct labor variances...Ch. 11 - Calculate and interpret direct material and direct...Ch. 11 - Calculate the material and labor variances...Ch. 11 - Record materials and labor transactions (Learning...Ch. 11 - Calculate the standard cost of a product before...Ch. 11 - Recognize advantages and disadvantages of standard...Ch. 11 - Compute and interpret overhead variances (Learning...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Make journal entries in a standard costing system...Ch. 11 - Prepare a standard cost income statement (Learning...Ch. 11 - Calculate standard cost and gross profit per unit...Ch. 11 - Calculate the standard cost per unit (Learning...Ch. 11 - Calculate and explain direct material variances...Ch. 11 - Calculate missing direct material variables...Ch. 11 - Calculate and explain direct labor variances...Ch. 11 - Prob. 11.38BECh. 11 - Prob. 11.39BECh. 11 - Prob. 11.40BECh. 11 - Prob. 11.41BECh. 11 - Recognize advantages and disadvantages of standard...Ch. 11 - Calculate and interpret overhead variances...Ch. 11 - Prob. 11.44BECh. 11 - Prob. 11.45BECh. 11 - Prob. 11.46BECh. 11 - Prob. 11.47BECh. 11 - Prob. 11.48BECh. 11 - Prob. 11.49APCh. 11 - Comprehensive standards and variances problem...Ch. 11 - Comprehensive standards and variances problem...Ch. 11 - Prob. 11.52APCh. 11 - Prob. 11.53APCh. 11 - Prob. 11.54BPCh. 11 - Comprehensive standards and variances problem...Ch. 11 - Comprehensive standards and variances problem...Ch. 11 - Work backward through labor variances (Learning...Ch. 11 - Determine all variances and make journal entries...Ch. 11 - Calculate labor variances in a hotel (Learning...
Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Text book image
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Text book image
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Text book image
Excel Applications for Accounting Principles
Accounting
ISBN:9781111581565
Author:Gaylord N. Smith
Publisher:Cengage Learning
Text book image
Essentials of Business Analytics (MindTap Course ...
Statistics
ISBN:9781305627734
Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:Cengage Learning
Text book image
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
How to Estimate Project Costs: A Method for Cost Estimation; Author: Online PM Courses - Mike Clayton;https://www.youtube.com/watch?v=YQ2Wi3Jh3X0;License: Standard Youtube License