Question
Book Icon
Chapter 11, Problem 11.54BP

1.

To determine

To calculate: The standard direct material cost for one blanket.

2.

To determine

To calculate: The actual cost per yard of fabric purchased.

3.

To determine

To calculate: The direct material price and quantity variances.

4.

To determine

To calculate: The standard direct labor cost for one blanket.

5.

To determine

To calculate: The actual direct labor cost per hour.

6.

To determine

To calculate: The direct labor rate and efficiency variances.

7.

To determine

To analyze: Each variance and the factors that may have caused that variance.

8.

To determine

To explain: The relatedness of all variances and what variance caused the other variance.

Blurred answer
Students have asked these similar questions
Northern Defense manufactures radar systems. It has just completed the manufacture of its first newly designed system, RS-32. Manufacturing data for the RS-32 follow: (Click icon to view data) Requirement Calculate the total variable costs of producing 2, 4, and 8 units. Begin by calculating the cumulative total time in labor-hours using the cumulative average-time learning model. (Round the cumulative average time per unit to the nearest whole number.) Cumulative number of Cumulative average time Cumulative total time: per unit: Labor-hours Labor-hours 3700 units 2 4 8 3700 ← Data table Direct material cost Direct manufacturing labor time for first unit Learning curve for manufacturing labor time per radar system Direct manufacturing labor cost Variable manufacturing overhead cost Using the formula for an 85% learning curve, b = In 0.85 In 2 Print = $ $ $ -0.162519 0.693147 81,000 per unit of RS-32 3,700 direct manufacturing labor-hours 85% cumulative average timeª Done 28 per direct…
Highland Company produces a lightweight backpack popular with college students. Standard variable costs relating to a single backpack are given below:   Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials ?question mark $ 6.00 per yard $ ?question mark Direct labor ?question mark ?question mark   ?question mark Variable manufacturing overhead ?question mark $ 2 per direct labor-hour ?question mark Total standard cost per unit $ ?question mark Overhead is applied to production based on direct labor-hours. During March, 800 backpacks were manufactured and sold. Selected information relating to the month’s production is given below:   Materials Used Direct Labor Variable Manufacturing Overhead Total standard cost allowed* $ 19,200   $ 9,200 $ 1,600 Actual costs incurred $ 11,100   ?question mark $ 4,740 Materials price variance ?question mark       Materials quantity variance $ 3,000 U     Labor rate variance     ?question mark…
Pretty Draperies manufactures curtains.  A certain window requires the following: Direct materials standard:                            10 square yards at $5 per yard Direct labor standard:                                    5 hours at $10   During the second quarter, the company made 1,500 curtains and used 14,000 square yards of fabric costing $68,600.  Actual direct labor hours used totaled 7,600 hours for $79,800.   Compute the direct manufacturing labor rate (price) and quantity (efficiency) variances for the quarter (show calculations):                                                                                                                          DL rate variance $_____________________                                                                                                  Circle one:          Favorable            Unfavorable                                                                                                  DL quantity variance $__________________…

Chapter 11 Solutions

Managerial Accounting (5th Edition)

Ch. 11 - Compute the standard cost of direct materials...Ch. 11 - Compute the standard cost of direct labor...Ch. 11 - Explain a direct material variance (Learning...Ch. 11 - Prob. 11.4SECh. 11 - Calculate direct material variances when the...Ch. 11 - Calculate direct labor variances (Learning...Ch. 11 - Prob. 11.7SECh. 11 - Prob. 11.8SECh. 11 - Calculate fixed overhead variances (Learning...Ch. 11 - Calculate and interpret fixed overhead variances...Ch. 11 - Prob. 11.11SECh. 11 - Calculate and interpret overhead variances...Ch. 11 - Record costing transactions (Learning Objective 7)...Ch. 11 - Record standard costing transactions (Learning...Ch. 11 - Identify ethical standards violated (Learning...Ch. 11 - Vocabulary (Learning Objectives 1, 2, 3, 4, 5, 6)...Ch. 11 - Calculate standard cost and gross profit per unit...Ch. 11 - Calculate standard cost per unit (Learning...Ch. 11 - Calculate and explain direct material variances...Ch. 11 - Calculate missing direct material variables...Ch. 11 - Calculate and explain direct labor variances...Ch. 11 - Calculate and interpret direct material and direct...Ch. 11 - Calculate the material and labor variances...Ch. 11 - Record materials and labor transactions (Learning...Ch. 11 - Calculate the standard cost of a product before...Ch. 11 - Recognize advantages and disadvantages of standard...Ch. 11 - Compute and interpret overhead variances (Learning...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Make journal entries in a standard costing system...Ch. 11 - Prepare a standard cost income statement (Learning...Ch. 11 - Calculate standard cost and gross profit per unit...Ch. 11 - Calculate the standard cost per unit (Learning...Ch. 11 - Calculate and explain direct material variances...Ch. 11 - Calculate missing direct material variables...Ch. 11 - Calculate and explain direct labor variances...Ch. 11 - Prob. 11.38BECh. 11 - Prob. 11.39BECh. 11 - Prob. 11.40BECh. 11 - Prob. 11.41BECh. 11 - Recognize advantages and disadvantages of standard...Ch. 11 - Calculate and interpret overhead variances...Ch. 11 - Prob. 11.44BECh. 11 - Prob. 11.45BECh. 11 - Prob. 11.46BECh. 11 - Prob. 11.47BECh. 11 - Prob. 11.48BECh. 11 - Prob. 11.49APCh. 11 - Comprehensive standards and variances problem...Ch. 11 - Comprehensive standards and variances problem...Ch. 11 - Prob. 11.52APCh. 11 - Prob. 11.53APCh. 11 - Prob. 11.54BPCh. 11 - Comprehensive standards and variances problem...Ch. 11 - Comprehensive standards and variances problem...Ch. 11 - Work backward through labor variances (Learning...Ch. 11 - Determine all variances and make journal entries...Ch. 11 - Calculate labor variances in a hotel (Learning...
Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Text book image
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
What is variance analysis?; Author: Corporate finance institute;https://www.youtube.com/watch?v=SMTa1lZu7Qw;License: Standard YouTube License, CC-BY