Production and Operations Analysis, Seventh Edition
7th Edition
ISBN: 9781478623069
Author: Steven Nahmias, Tava Lennon Olsen
Publisher: Waveland Press, Inc.
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 10.3, Problem 8P
a.
Summary Introduction
Interpretation: The direct cost of the project is to be computed after the successive reduction of the project time by one week.
Concept Introduction: Network diagram is a graphical representation of tasks and events happening in a project. It depicts the workflow and is used to compute the total duration of the project.
B.
Summary Introduction
Interpretation: The optimal project completion time and the total project cost are to be computed when the indirect costs amount to $150.
Concept Introduction: Network diagram is a graphical representation of tasks and events happening in a project. It depicts the workflow and is used to compute the total duration of the project.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration
per week:
Activity Duration (weeks) Precedes Crash Cost/Week
A (start)
B
C
E
F (end)
3
2
6
2
3
Activity
B, C
E
F
F
A
B
Suppose that Rafay is only given 9 weeks (instead of 12) to complete the project. By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an
activity down to 0 weeks duration.
$380
$130
$240
Each Activity
Should be Reduced
BY
(weeks)
0 week(s)
week(s)
$150
$400
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week:
Activity Duration (weeks) Precedes Crash Cost/Week
A (start)
B, C
B
$370
$120
C
$200
E
$150
F (end)
$420
Suppose that Rafay is only given 9 weeks (instead of 11) to complete the project. By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration.
Each Activity
Should be Reduced
BY
(weeks)
week(s)
3
2
5
2
3
Activity
A
E
F
F
A project consists of seven activities, lettered A through F below. For each activity, the estimated normal time in number of weeks, crash
time, normal cost, crash cost, and its preceding activity are given.
Normal Time Crash Time
Normal Cost
Crash Cost
Immediate
Activity
(weeks)
(weeks)
(Peso)
(Peso)
Predecessor(s)
A
4
3
2,000
2,600
B
1
2,200
2,800
3
500
500
D
8
4
2,300
2,600
A
E
6
900
1,200
В
F
3
3,000
4,200
G
4
1,400
2,000
D, E
If you wish to reduce the time required to complete this project by one week, which activity should be crashed?
O Activity C
O Activity D
O Activity E
O Activity B
O Activity A
Chapter 10 Solutions
Production and Operations Analysis, Seventh Edition
Ch. 10.2 - Prob. 1PCh. 10.2 - Prob. 2PCh. 10.2 - Prob. 3PCh. 10.2 - Prob. 4PCh. 10.2 - Prob. 5PCh. 10.2 - Prob. 6PCh. 10.3 - Prob. 7PCh. 10.3 - Prob. 8PCh. 10.3 - Prob. 9PCh. 10.3 - Prob. 10P
Ch. 10.4 - Prob. 11PCh. 10.4 - Prob. 12PCh. 10.4 - Prob. 13PCh. 10.4 - Prob. 14PCh. 10.4 - Prob. 15PCh. 10.4 - Prob. 16PCh. 10.5 - Prob. 17PCh. 10.5 - Prob. 18PCh. 10.5 - Prob. 19PCh. 10.5 - Prob. 20PCh. 10.5 - Prob. 21PCh. 10.6 - Prob. 22PCh. 10.6 - Prob. 23PCh. 10.6 - Prob. 24PCh. 10.6 - Prob. 25PCh. 10 - Prob. 26APCh. 10 - Prob. 27APCh. 10 - Prob. 28APCh. 10 - Prob. 29APCh. 10 - Prob. 30AP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Activity Duration (weeks) Precedes Crash Cost/Week A (start) B 224IN 2 A C E F (end) Suppose that Rafay is only given 8 weeks (instead of 10) to complete the project. By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration. Each Activity Should be Reduced BY (weeks) week(s) 1 Activity B, C $380 $110 EFF $220 $140 $400arrow_forwardConsider a project that has been modeled as in Table 1 Draw the PERT/CPM network for this project and determine the project’s expected completion time µP and its critical path. Suppose the standard deviations of the activity durations are σA = 2, σB = 1, σC = 0, σD = 2, σE = 3, and σF = 0. Then please estimate the standard deviation of the overall project’s standard deviation σP . Suppose for the standard Normal random variable Z, we know P[−1 ≤ Z ≤ +1] ' 68%, P[−2 ≤ Z ≤ +2] ' 95%, and P[−3 ≤ Z ≤ +3] ' 99.7%. Then, approximately what time T is one for which there is only a less than 2.5% chance for the completion time to beat (be shorter than)?arrow_forwardThe following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week Crash Cost/Week Activity Duration (weeks) Precedes A (start) B, C $380 $130 B E C F $240 E F $160 F (end) $450 Suppose that Rafay is only given 7 weeks (instead of 9) to complete the project. By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration. Each Activity Should be Reduced BY (weeks) 0 week(s) 1 week(s) 2 week(s) 0 week(s) 0 week(s) What is the total crashing cost? $ Enter your response as a whole number.) 2 2 4 1 3 Activity A B C ELL Farrow_forward
- The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Activity Duration (weeks) Precedes Crash Cost/Week A (start) B с E F (end) 2 2 5 2 3 Activity B. C E F F A Suppose that Rafay is only given 7 weeks (instead of 10) to complete the project. By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration, Each Activity Should be Reduced BY (weeks) $380 $110 week(s) $200 $160 $450arrow_forwardA project consists of seven activities, lettered A through F below. For each activity, the estimated normal time in number of weeks, crash time, normal cost, crash cost, and its preceding activity are given. Normal Time Crash Time Normal Cost Crash Cost Immediate Activity (weeks) (weeks) (Peso) (Peso) Predecessor(s) A 4 3 2,000 2,600 2 1 2,200 2,800 3 500 500 D 8. 4 2,300 2,600 A E 6 3 900 1,200 F 3 2 3,000 4,200 G 4 2 1,400 2,000 D, E What is the maximum time that can be crashed? O Not in the choices Seven weeks Five weeks O Four weeks O Six weeksarrow_forwardYour hospital has applied for certification as a level 1 stroke center. It is critical that the following project is completed in 18 weeks, before the next Joint Commission survey. Project activity times are listed in the table attached as an image. Determine the minimum cost-schedule for this project to be completed in 18 weeks. Assume a linear relationship between crash cost and crash time. For example, crash cost per week for activity A can be calculated as: ($650 - $200)/(4-2) = $225. 2. What is the difference in total project costs between the earliest completion time of the project using normal times and the minimum cost-schedule you found in part 1?arrow_forward
- The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Duration Crash (weeks) Cost/Week Activity A (start) Precedes В, С $370 $110 $220 B E C 4 F E 1 F $150 F (end) $420 Suppose that Rafay is only given 6 weeks (instead of 9) to complete the project. By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration. Each Activity Should be Reduced Activity BY (weeks) А week(s)arrow_forwardYou are the project manager of the software installation project in the table below. You would like to find the minımum-cost schedule for your project. There is a $500-per-week penalty for each week the project is delayed beyond week 25. In addition, your project team determined that indirect project costs are $2,000 per week. Normal Cost Crash Time Crash Cost ($) 3,000 3,000 10,000 Normal Time (weeks) Immediate Activity Predecessor(s) (weeks) (S) A 1 3,000 6,000 C A 9. 8. 12,000 8 2. А, В 10 3,000 9.000 4,000 5,000 2,000 3.000 5,000 9,000 7,000 12 6. E, F 2 1 G 5.000 C, F 8 2,000 8.000 a. What would be your target completion week? The target completion week is week (Enter your response as an integer.)arrow_forwardGiven the following activity network: Three nodes - A1, A2, A3; two paths - A1, A2 and A1, A3. Activity A1 takes 5 weeks, A2 takes 7 weeks, and A3 takes 4 weeks with a 50% probability and 10 weeks with a 50% probability. What is the project completion time under the worst-case scenario, that is, A3 is late and takes 10 weeks? A. 15 B. 10 C. 12 D. 9arrow_forward
- A project is scheduled to complete in six months duration. There are two activities in the project. The actual cost of Activity 1 is SAR 300,000 and that of Activity 2 is SAR 200,000. The planned value of these activities is SAR 280,000 and 150,000 respectively. On reviewing, the current project status is Activity 1 is 100% completed and Activity 2 is only 75% completed. (i) Perform the earned value calculations of the above project scenario and fill the given table. (ii) What do you infer about the project schedule and cost based on your calculations? Earned Value Planned Value Actual Cost Cost Variance Activity Scheduled Variance Cost performance Index Schedule performance Index Month 1arrow_forwardA project is scheduled to complete in six months duration. There are two activities in the project. The actual cost of Activity 1 is SAR 300,000 and that of Activity 2 is SAR 200,000. The planned value of these activities is SAR 280,000 and 150,000 respectively. On reviewing, the current project status is Activity 1 is 100% completed and Activity 2 is only 75% completed. (i) Perform the earned value calculations of the above project scenario and fill the given table. Activity Month 1 Earned Value Planned Value Actual Cost Cost Variance Scheduled Variance Cost performance Index Schedule performance Index (ii) What do you infer about the project schedule and cost based on your calculations?arrow_forwardUsing the information given and the project completiontime calculated in Problem 9(a), reduce the completion time ofthe project by 5 weeks in the most economical wayarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY