Question
Chapter 10.2, Problem 5P
A.
Summary Introduction
Interpretation: Thepredecessors of every activity in the project are to be determined.
Concept Introduction: Network diagram is a graphical representation of tasks and events happening in a project. It depicts the workflow and is used to compute the total duration of the project.
B.
Summary Introduction
Interpretation: The network diagram of the project is to be redrawn with only one pseudo activity.
Concept Introduction: Network diagram is a graphical representation of tasks and events happening in a project. It depicts the workflow and is used to compute the total duration of the project.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The Mobicom Corporation is in the design phase of a system project. The project manager wants to develop a network analysis diagram to plan the activities of designing the system outputs. The activities are as follows.
ACTIVITY
PRECEDING
TIME[WEEKS]
A
-----
5
B
----
6
C
----
4
D
A,B
7
E
C
8
F
C,D
10
G
D
8
Required
Draw a network diagram for the design phase
Find the following:
1- The optimum period and the corresponding time
2- The network plan detailed in the table below, noting that the
additional cost is $ 1500 per week
Activity Normal duration Normal cost Crash duration Crash cost
weeks
2$
2000
weeks
2$
1-2
11
9.
10000
1-3
17
3000
14
12000
2-3
8.
6.
3600
6.
6000
3-4
6000
4
11000
Consider the project given on the table, construct a network diagram
Chapter 10 Solutions
Production and Operations Analysis, Seventh Edition
Ch. 10.2 - Prob. 1PCh. 10.2 - Prob. 2PCh. 10.2 - Prob. 3PCh. 10.2 - Prob. 4PCh. 10.2 - Prob. 5PCh. 10.2 - Prob. 6PCh. 10.3 - Prob. 7PCh. 10.3 - Prob. 8PCh. 10.3 - Prob. 9PCh. 10.3 - Prob. 10P
Ch. 10.4 - Prob. 11PCh. 10.4 - Prob. 12PCh. 10.4 - Prob. 13PCh. 10.4 - Prob. 14PCh. 10.4 - Prob. 15PCh. 10.4 - Prob. 16PCh. 10.5 - Prob. 17PCh. 10.5 - Prob. 18PCh. 10.5 - Prob. 19PCh. 10.5 - Prob. 20PCh. 10.5 - Prob. 21PCh. 10.6 - Prob. 22PCh. 10.6 - Prob. 23PCh. 10.6 - Prob. 24PCh. 10.6 - Prob. 25PCh. 10 - Prob. 26APCh. 10 - Prob. 27APCh. 10 - Prob. 28APCh. 10 - Prob. 29APCh. 10 - Prob. 30AP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Nikos Anastopoulos of EMPROSS Strategic IT Consultants, leads the development of a new football stadium. He developed the activities, durations, and predecessor relationships in the following table for delivering company valuations. Activity Predecessor Duration in Weeks A - 5 B - 3 C A, B 8 D C 3 E - 4 F E 10 G F 8 H E 18 I D 20 J D, G, I 7 K I 5 L H 10 6A. Draw the Network Diagram, and identify and discuss the project duration and the critical path using the following activity notation: the first pic: First: Draw the precedence diagram. Second: Using the notation given identify the duration of the project: you can type it. Third: identify the critical part and explain the critical path. Fourth: Explain your answer. This can be done by describing the process and the observations done once the answer has been found. 6B. Draw the project’s Gantt chart First: The…arrow_forwardDr. Ell has been given a budget of $5,000 to organize a conference at her university in less than 2.5 months' time (9 weeks) via an educational grant. She has a team of 2 research assistants and after some deliberation, they identified the following activities that are required to be completed for hosting a successful conference. Immediate Predecessor Activity A B с D E F G H Description Deciding Dates and Number of sessions Determining Venue for conference Sending out a Call for Papers Inviting Special Speakers Responding to presenters Organizing Sessions with papers Getting registrations and confirmations Last minute Edits and Finalizing Program Dr. Ell has approached you, her student, to help her figure this out, as a part of her Management Science class assignment. Please give your respo with appropriate explanations, tables, and formulas, where relevant, to the following questions: BUAE U H 000000 1. PART 1. PERT/CPM with varying times a. Follow a PERT/CPM model to identify the…arrow_forwardThe Student Affairs Department at UCC has developed a sequence of activities for the University’s Sports Day. The Director has published the activities as shown in the table. All students are expected to participate and all activities are expected to be completed. The activities and immediate predecessors appear in the following table. Develop a network for this problem. ACTIVITY IMMEDIATE PREDECESSOR A -- B -- C -- D B E A, D F C G E, F Copy the following table in your answer booklet. Determine the values for the gray spaces hence complete the copied table. Activity Completion Times Early Start Early Finish Late Start Late Finish Slack On Critical Path A 2 B 5 C 1 D 3 E 2 F 6 G 8 CRITICAL…arrow_forward
- Problem 1 Solve the scheduling data for the following project and compute the relevant information; include the information on your network; (Draw the network and implement the Critical Path Method (CPM); Precedence diagramming to determine the critical path (CP) and all of the relevant information for the project). Feel free to use any of these two node designs (Use ES for the first activity = 0) Highlight the overall duration of the project with the critical path ES Activities EF Activity ES Duration LS Cr. Duration TF EF FF TE LF LS FF LF Activities' label Duration Predecessors A 3 A FF B FF/2 В 2 C 3 D C E 2 B/1 F 3 Е, D Continue into the next page for problem 2 →arrow_forwardConsider the following TABLE Activity preceding activity Duration (days A - B - C A D C E B &C Required Discuss the rules for drawing networks and illustrate the above by drawing its network.arrow_forwardPatel and Associates, Inc., is an accounting firm that has three new clients. Project leaders will be assigned to the three clients. Based on the different backgrounds and experiences of the leaders, the various leader-client assignments differ in terms of projected completion times. The possible assignments and the estimated completion times in days are as follows. Min s.t. Ellis Jackson Smith Project Leader Client 1 Jackson Client 2 Client 3 Ellis Smith (a) Develop a network representation of this problem. (Submit a file with a maximum size of 1 MB.) Choose File No file chosen (b) Formulate the problem as a linear program. (Express your answers in the form X;; where X;; is 1 if leader i is assigned to client j and 0 otherwise.) Xij ≥ 0 for all i, j. Solve. Relationship X11 X12 X13 X21 X22 X23 X31 1 X32 2 X33 3 Client 10 16 32 14 22 40 22 24 34 Value Time (days) (c) What is the total time required (in days)? daysarrow_forward
- M7-3 Assignment Use Microsoft Project software to solve this assignment problem. Submit your project file and provide your answers on the attached answer sheet template. Consider the following network with tasks duration in days: TPPM Assignment 7 - Page 13 (Note: Tack is a dummy task. It must be included in the relationships, but its duration is set duration Task Pastimet Lily Optimatic FedCat A 1000 2 • GOO 12 7 2 2500 D 12 800 9 800 24 12 2400 G 11 4 800 H " 5 1200 2 5000 25 17 9 4200 K 3000 L 2500 M 12 30 3000 N 1. Set the Project start on Monday 11/1/20 Thursday 11/26/20, Friday 11/27/20, 12/25/20, and 1/1/21 are holidays 2. Determine critical path and its duration. When the project will end date? 3. There is a possiblity that the starting task K may be delayed by 3 days. Will this impact the project completion date? If yes, when will be the new finish date? (After checking this out, please restore the project to its original schedule). 4. Assign the following resources to the…arrow_forwardAmate Self-Test 2 LENGDODA 1. Scott and Associates, Inc., is an accounting firm that has three new clients. Project leaders will be assigned to the three clients. Based on the different backgrounds and experiences of the leaders, the various leader-client assignments differ in terms of projected completion times. The possible assignments and the estimated completion times in days are as follows: Client Project Leader 2 3 16 32 Jackson Ellis 22 40 Smith 24 34 a. Develop a network representation of this problem. b. Find the optimal solution using the Hungarian method. What is the total time required? - 212 14 • EDIFICAarrow_forwardScott and Associates, Inc., is accounting firm that has three new clients. Project leaders will be assigned to the three clients. Based on the different backgrounds and experiences of the leaders, the various leader- client assignments differ in terms of projected completing times. The possible assignments and the estimated completion times in days are as follows: Client Project Leader 1 2 3 Abby 10 16 32 Bovi 14 22 40 Claire 22 24 34 Develop a network representation of this problem. Formulate the problem as a linear program.arrow_forward
- What is the difference between an activity-on-arrow (AOA)network and an activity-on-node (AON) network? Which isprimarily used in this chapter?arrow_forwardDuration and requirement of workforce for each activity is tabulated below for a network Activity Duration Number of men 1-2 3 5 2-4 2 3 2-3 3 7 3-4 0 0 3-5 3 2 4-5 7 2 3-6 2 1 5-6 6 6 4-6 5 5 (i) Draw the network and comment on the scheduling of activities to smoothen the development of the workforce (ii) Indicate the maximum crew size in each case (iii) Re-schedule the activities for smooth development (iv) Find the project schedule if only 4 men are availablearrow_forwardDraw a network diagram, including ES, EF, LS, LF, Float and Duration for the following scenario:arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY