Principles Of Operations Management
Principles Of Operations Management
11th Edition
ISBN: 9780135173930
Author: RENDER, Barry, HEIZER, Jay, Munson, Chuck
Publisher: Pearson,
Question
Book Icon
Chapter 10, Problem 9P

a)

Summary Introduction

To draw: An activity chart to change the right rear tire on an automobile with only one person working

Introduction: Activity chart is the type of chart that is used to observe the present method and propose improvement. The study helps to improve the utilization of machine, operator, and the combination of machine and operator.

b)

Summary Introduction

To draw: An activity chart to change the right rear tire on automobile with two people working

Introduction: Activity chart is the type of chart that is used to observe the present method and propose improvement. The study helps to improve the utilization of machine, operator, and the combination of machine and operator.

Blurred answer
Students have asked these similar questions
A Methods and Measurements Analyst needs to develop a time standard for a certain task. The task involves use of a ruler, square, and portable electric saw to mark and cut the "notch" in a rafter (a standard carpentry task of home construction). In a preliminary study, he observed one of his workers performing this task five times. The observations were made in an air-conditioned, well-lit training facility, at ground level, with all tools and equipment clean and readily available.  Observation: 1 2 3 4 5 Task time (seconds): 82 74 80 83 76 a. What is the actual average time for this task? b. What is the normal time for this task if the employee worked at a 20% faster pace than is typical for adequately trained workers? c. What is standard time for this task if allowances sum to 14%? d. If the analyst then thought more carefully about his experiment and decided that the allowances needed to be increased to match the real (outside, not air-conditioned)…
How are devices such as flow process charts and worker-machine charts useful?
Claudine Soosay recorded the following times assembling a watch: Observation No. 1 2 3 4 5 6 7 8 Performance rating is given as 95%. a) The average time of Claudine for the operation = Time (minutes) 0.11 0.09 0.11 0.09 0.15 0.10 0.09 0.10 Observation No. 9 10 11 12 13 14 15 16 minutes (round your response to three decimal places). Time (minutes) 0.11 0.09 0.11 0.10 0.11 0.12 0.14 0.10
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.