Question
Chapter 10, Problem 3P
Summary Introduction
To determine: To draw an activity chart for a machine operator
Introduction: An activity chart is the type of chart that is used to observe the present method and propose improvement. The study helps to improve the utilization of a machine, operator, and a combination of machine and operator.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
What is the bottleneck of the process is which worker ?
5. Flo's Quick-Lube performs fast oil changes (A) and checks for tire pressure and wear (B) and
brakes and alignment (C) according to the process flow indicated by the diagram below. Each
incoming car is put on a jack while one technician performs task A and another simultaneously
performs task B and a third performs task C (which must follow task B due to the limited space
under the vehicle on the jack). The server for task A takes on average 3 minutes to process a job,
the server for task B takes on average 2 minutes to process a job, and the server for task C takes
on average 2 minutes to process a job. Server A can be operated in parallel with Servers B and C.
All processing times are random and exponentially distributed, and jobs are allowed to queue in
front of each server. (You can assume that the number of jacks is sufficient to allow any length of
queue.)
(a)
AND
B
A
C
Figure 1: Flo's Process Flow
What is the capacity of the process (in orders/minute)?
Course: work study and method engineering
Sigma Company has noted a learning rate of 80% while launching test for its product ET. It takes 90 hours to produce the first unit of the batch. Determine the total time for 12unit batch?
Chapter 10 Solutions
Principles Of Operations Management
Ch. 10 - Prob. 1EDCh. 10 - Prob. 1DQCh. 10 - Prob. 2DQCh. 10 - Prob. 3DQCh. 10 - Prob. 4DQCh. 10 - Prob. 5DQCh. 10 - Prob. 6DQCh. 10 - Prob. 7DQCh. 10 - Prob. 8DQCh. 10 - Prob. 9DQ
Ch. 10 - Prob. 10DQCh. 10 - Prob. 11DQCh. 10 - Prob. 12DQCh. 10 - Prob. 13DQCh. 10 - Prob. 14DQCh. 10 - Prob. 1PCh. 10 - Prob. 2PCh. 10 - Prob. 3PCh. 10 - Prob. 4PCh. 10 - Prob. 5PCh. 10 - Prob. 6PCh. 10 - Prob. 7PCh. 10 - Prob. 8PCh. 10 - Prob. 9PCh. 10 - Prob. 10PCh. 10 - Prob. 11PCh. 10 - Prob. 12PCh. 10 - Prob. 13PCh. 10 - Prob. 14PCh. 10 - Prob. 15PCh. 10 - Prob. 16PCh. 10 - Prob. 17PCh. 10 - Prob. 18PCh. 10 - Prob. 19PCh. 10 - Prob. 20PCh. 10 - Prob. 21PCh. 10 - Prob. 22PCh. 10 - Virginia College promotes a wide variety of...Ch. 10 - Prob. 24PCh. 10 - Prob. 25PCh. 10 - Prob. 26PCh. 10 - Prob. 27PCh. 10 - Prob. 28PCh. 10 - Prob. 29PCh. 10 - Prob. 30PCh. 10 - Prob. 31PCh. 10 - Prob. 32PCh. 10 - Prob. 33PCh. 10 - Prob. 34PCh. 10 - Prob. 35PCh. 10 - Prob. 36PCh. 10 - Prob. 37PCh. 10 - Prob. 39PCh. 10 - Prob. 40PCh. 10 - Prob. 41PCh. 10 - Prob. 42PCh. 10 - Prob. 44PCh. 10 - Prob. 1CSCh. 10 - Prob. 2CSCh. 10 - Prob. 3CSCh. 10 - Prob. 4CSCh. 10 - Prob. 1.1VCCh. 10 - Prob. 1.2VCCh. 10 - Prob. 1.3VCCh. 10 - Prob. 2.1VCCh. 10 - Prob. 2.2VCCh. 10 - Prob. 2.3VCCh. 10 - Prob. 2.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Kiko Teddy Bear is a manufacturer of stuffed teddy bears. Kiko would like to be able to produce 40 teddy bears per hour on its assembly line. The following information will assist in answering the questions that follow: Task Information for Kiko Teddy Bear Work Element Task Description Immediate Predecessor Task time (in seconds) A Cut teddy bear pattern None 90 B Sew teddy bear cloth a 75 C stuff teddy bear b 50 D glue on eyes c 20 E glue on nose c 15 F sew on mouth c 35 G attach manufacturer's label b 15 H Inspect and pack teddy bear d,e,f,g 40 a. Draw a precedence diagram. b. What cycle time would provide the desired output? c. What is the maximum possible output of the line? d. What is the theoretical minimum number of workstations using the cycle time computed in” b “ above? e. Assign tasks to workstations using the cycle time in “b” above. f. Calculate the efficiency and idle time percentage of the line.arrow_forwardRock View Restaurant is a new fast food restaurant chain. The Operations Manager has dividedits normal drive-through service process into the following tasks:Tasks Description Task Time(InSeconds)PredecessorsA Take order 25 NoneB Receive payment 20 AC Gather drinks 35 AD Gather food 32 AE Put food etc. in bag 25 C,DF Give food to customer 10 B,E Currently, Rock View Restaurant has a single window with one person who takes the order, gather the food, collects the money and gives the food to the customer. This takes an average of 147 seconds per customer so only 25.5 cars can be served.…arrow_forwardRock View Restaurant is a new fast food restaurant chain. The Operations Manager has dividedits normal drive-through service process into the following tasks:Tasks Description Task Time(InSeconds)PredecessorsA Take order 25 NoneB Receive payment 20 AC Gather drinks 35 AD Gather food 32 AE Put food etc. in bag 25 C,DF Give food to customer 10 B,E Currently, Rock View Restaurant has a single window with one person who takes the order, gather the food, collects the money and gives the food to the customer. This takes an average of 147 seconds per customer so only 25.5 cars can be served.…arrow_forward
- Rock View Restaurant is a new fast-food restaurant chain. The Operations Manager has dividedits normal drive-through service process into the following tasks: Tasks Description Task Time (In Seconds) Predecessors A Take Order 25 None B Receive payment 20 A C Gather drinks 35 A D Gather Food 32 A E Put food etc. In bag 25 C,D F Give food to Customer 10 B,E Currently, Rock View Restaurant has a single window with one person who takes the order,gather the food, collects the money and gives the food to the customer. This takes an average of147 seconds per customer so only 25.5 cars can be served. Rock View Restaurant wants toincrease its drive-through capacity to 60 cars per hour by forming a multi-window line.1. Calculate the efficiency of the newly design process.arrow_forwardEddys Pizza is currently redesigning its order-processing and pizza-making procedures for itsoperations which usually start at 5pm and close at 2am. For Eddys to meet customers’ speedydelivery requirement, six elements must be completed as summarised in the table below.WorkElementDescription Precedence Time (Mins)1 Receive customer order - 32 Shape dough 1 23 Prepare toppings 1 34 Assemble Pizza 2, 3 45 Bake pizza 4 46 Select complementary drink - 17 Deliver pizza 5, 6 4i. Draw the precedence diagram for the pizza making process.ii. If the demand for pizza is 90 pieces during the operating time, calculate the desired cycletime iii. Balance the line and calculate its efficiencyarrow_forwardRockness Recycling refurbishes rundown business students. The process uses a moving belt, which carries each student through the five steps of the process in sequence. The five steps are as follows: STEP DESCRIPTION TIME REQUIREDPER STUDENT 1 Unpack and place on belt 1.2 minutes 2 Strip off bad habits 1.0 minutes 3 Scrub and clean mind 1.5 minutes 4 Insert modern methods 0.8 minute 5 Polish and pack 1.0 minutes One faculty member is assigned to each of these steps. Faculty members work a 40-hour week and rotate jobs each week. Mr. Rockness has been working on a contract from General Eclectic, which requires delivery of 2,000 refurbished students per week. A representative of the human resources department has just called complaining that the company hasn’t been receiving the agreed-upon number of students. A check of finished goods inventory by Mr. Rockness reveals that there is no stock left. a. Calculate the maximum output for each step. b. Which step…arrow_forward
- Rock View Restaurant is a new fast-food restaurant chain. The Operations Manager has dividedits normal drive-through service process into the following tasks: Tasks Description Task Time (In Seconds) Predecessors A Take Order 25 None B Receive payment 20 A C Gather drinks 35 A D Gather Food 32 A E Put food etc. In bag 25 C,D F Give food to Customer 10 B,E Currently, Rock View Restaurant has a single window with one person who takes the order,gather the food, collects the money and gives the food to the customer. This takes an average of147 seconds per customer so only 25.5 cars can be served. Rock View Restaurant wants toincrease its drive-through capacity to 60 cars per hour by forming a multi-window line.i. Using the LOT heuristic, assign the tasks to the windows to produce the desiredservice rate making sure that the precedence relationship is maintained.arrow_forwardRock View Restaurant is a new fast-food restaurant chain. The Operations Manager has dividedits normal drive-through service process into the following tasks: Tasks Description Task Time (In Seconds) Predecessors A Take Order 25 None B Receive payment 20 A C Gather drinks 35 A D Gather Food 32 A E Put food etc. In bag 25 C,D F Give food to Customer 10 B,E Currently, Rock View Restaurant has a single window with one person who takes the order,gather the food, collects the money and gives the food to the customer. This takes an average of147 seconds per customer so only 25.5 cars can be served. Rock View Restaurant wants toincrease its drive-through capacity to 60 cars per hour by forming a multi-window line.1. Draw the precedence diagram to represent the process at Rock view restaurant.arrow_forwardRock View Restaurant is a new fast-food restaurant chain. The Operations Manager has dividedits normal drive-through service process into the following tasks: Tasks Description Task Time (In Seconds) Predecessors A Take Order 25 None B Receive payment 20 A C Gather drinks 35 A D Gather Food 32 A E Put food etc. In bag 25 C,D F Give food to Customer 10 B,E Currently, Rock View Restaurant has a single window with one person who takes the order,gather the food, collects the money and gives the food to the customer. This takes an average of147 seconds per customer so only 25.5 cars can be served. Rock View Restaurant wants toincrease its drive-through capacity to 60 cars per hour by forming a multi-window line.1. Calculate the cycle time in seconds.arrow_forward
- 17.22. Updike Upholstery cuts and sews fabric for custom ordered chairs, ottomans, and sofas. Often, the more complicated patterns are for the smaller pieces, where cutting is more time-consuming than sewing. Thus, cutting and sewing times vary. Today's list of jobs, shown below, are for an important customer who needs them shipped out (in one shipment) as soon as possible. Determine the sequence of jobs that will complete the customer's order as quickly as possible, and notify the customer when the order is expected to ship. Jobs Cutting Sewing А 4 2 6. 3 1 3 4 3 1 Earrow_forward7- Assume that as a method engineer, we suspect that a worker walks more than normal during a production process. Hence, we are interested in the detailed movements of the worker to test our doubt. Then which tool would exactly help us? a) Cause and Effect Chart 2056 b) Flow Diagram c) Flow Process Chart d) Process Maps e) Activity Chart for One Workerarrow_forwardA work sampling study was conducted to establish the standard time for an operation The observation of the study is givein below: • Total number of observations 220 . Manual (Hand controiled work) = 34 %3D Machine controlled work = 126 Machine idle time = 60 Average performance rating 80% No. of parts produced during the study 36 Allowance for personal needs and fatigue 10% Study conducted for 3 days Availsble working hours / day 8 hrs Calculáte the Standard time for this operation? %3Darrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY