The figure shows the network diagram of a project along with the activity durations (T). In this project what is the slack time for activity B? (Only enter the number, do not try
Q: Q2: For the activities shown below determine: . The duration of project . The critical path by using…
A: ANSWER IS AS BELOW:
Q: For the small project with the relationships shown below. Activity IPA's Duration (Day) A 5 B 7 4 D…
A: An activity-on-node diagram is a visual representation of the network of an entire project schedule.…
Q: Conduct a forward and backwards pass for the activity network diagram that you have constructed…
A: THE ANSWER IS AS BELOW:
Q: 1- Total project finishing time 2- Critical path, 3- Free float for each task. • 4- If Activity B is…
A: The critical path is the path with the longest duration.
Q: Paul Silver, owner of Sculptures International, just initiated a new art project. The following data…
A: a. The network diagram for the project is:
Q: league baseball team. Draw a project network given the information in the table that follows.…
A: Find the answers below: Given Details: Given details: ID Description Predecessor Time…
Q: A project schedule has the following characteristics as shown in table 2 Table 2 Activities 1-2 |…
A: AON diagram
Q: I need help for number 12, please. Based on question number 11, which I already know the answer,…
A:
Q: a) Draw the network diagram. What is the project completion time? What is the critical path? b)…
A: The network diagram is a graphical representation of the project and is made up of a series of…
Q: The following CPM network has estimates of the normal time in weeks listed for the activities: (в(2)…
A: Since you have posted a question with multiple subparts, as per guidelines we need to answer for the…
Q: For the project described above, complete the project network diagram using the activity in the box…
A: Find the given details below: Given details Activity Predecessors Duration(Days) A - 4 B -…
Q: Draw the network diagram based on the information given below. Calculate the ES, EF, LS, LF and…
A: 1. During forward pass in case of more than two preceding activities the early start will be…
Q: The network diagram and task times for a project are shown below. Aj A4 A5 A3 Task Duration (days)…
A: This question is related to the project management subject, here, This subject falls under…
Q: You are provided with the following information for a project, with activity durations given in…
A:
Q: The aritical path for the network activities shown below is with completion time of weeks. Activity…
A: Answer: For determining the critical path, we have to draw the network diagram of the mentioned…
Q: Consider the following project network and activity times (in weeks): a. Identify the critical…
A: a) A-D-F-H b) Adding all the critical path A+D+F+H = 5+6+3+8 =22
Q: Given the following information, a. Draw a project network. b. Complete the forward and backward…
A: Note: - Since we can answer only up to three subparts we will answer the first three(a, b, and c)…
Q: Construct a Network Diagram showing the various logical activity relationships from this…
A: A project schedule network diagram shows the sequence of the task that is performed to complete a…
Q: The table below shows the complete project plan and includes all the activities with its immediate…
A: A network diagram is a visual representation of a project which helps to calculate the project…
Q: Using the following information, create a project network diagram. Calculate, ES, EF, LS and LF for…
A: 1. During forward pass in case of more than two preceding activities the early start will be…
Q: Please assist in detailed explanation on the following question in Project Scheduling: 1) - A…
A: Since it has been mentioned that the arcs need to be labelled with activity name and duration it is…
Q: The network diagram for a new project your company is undertaking is as shown: Start +Einish a.…
A: Given data is
Q: a) Calculate each activity duration using the last digit of your student number For example, if your…
A: Below is the solution:-
Q: (i) Construct a network diagram showing the various logical activity relationships from this…
A: For each activity, we have immediate predecessor data and Time in days, using the above table,…
Q: Draw a network representation of the project (nodes = activities, arrows = precedence constraints).…
A: A project schedule network diagram shows the sequence of the task that is performed to complete a…
Q: a. For each activity, calculate: ESD, EFD, LSD, LFD, FF, and TF. (Report your answers in the table…
A: A network diagram is a visual representation that helps to identify the activity relationship and…
Q: (a) Construct a project network. (b) Determine the expected times and variances for each activity.…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: Using the network diagram constructed in Problem 1,(a) Calculate the completion time for the…
A: The completion time of the project can be calculated as below:
Q: Reliable Garage is completing production of the J2000 kit car. The following data are available for…
A:
Q: a) Construct a network for this project b) Find a project schedule to minimize the completion time…
A: Given data is
Q: Ql: For activitics shown in table below, find the new time of project after updating, if the project…
A: ANSWER IS AS BELOW:
Q: Paul Silver, owner of Sculptures International, just initiated a new art project. The following data…
A:
Q: Consider the following project activities: | Duration Activity Predecessor (DAY) 4 A A 3 A 5 D E C F…
A: Activity Predecessor Duration A - 4 B A 3 C A 3 D B 5 E C 2 F C 1 G D, E 6 H F, G 5
Q: Use the Program Evaluation and Review Technique to represent the project in an activity network. In…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: (i) Construct a Network Diagram showing the various logical activity relationships from this…
A: A project schedule network diagram shows the sequential and analytical relationship between tasks in…
Q: Find the project details in the below table, draw the network activity diagram and identify the…
A: Critical path can be defined as the path which is having the longest duration.
Q: Immediate Estimated Activity Predecessors Duration A t+5 months В t+1 month C В t+2 months A, C t+4…
A: The critical path method (CPM), or critical path analysis (CPA), is a calculation for planning a…
Q: 3. Draw a project network from the following information. What activity(s) is a burst activity? What…
A: A network diagram is the graphical representation of project activities or tasks and their duration…
Q: Project Management In the below Precedence Diagram ( The activities durations are in weeks ) If…
A: Here, in the question, we have Network diagram, for each activity node, I have following data like…
Q: Consider a small project consisting of the following activities: Activity…
A: Find the Given details below: Activity ImmediatePredecessors Duration(Weeks) a - 6 b - 12 c…
Q: Activity Preceding Time A 8 -- B 3 -- A 7 D А, В 3 E C 4 F 6 a. Draw the network diagram. b.…
A: given, Activity Preceding Time A - 8 B - 3 C A 7 D A,B 3 E C 4 F D 6
Q: 1. Organize the information above in an activity precedence table showing the activity, precedent,…
A: Below is the solution:-
Q: a. Calculate the expected time and variance for each activity. . Calculate the activity slacks and…
A: D(duration)=given in the question as normal time ES (Early start)= The first activity from where the…
Q: For each of the following network diagrams, determine both the critical path and the expected…
A: Since we only answer up to 3 sub-parts, we'll answer the first 3. Please resubmit the question and…
Q: The network dlagram and task times for a project are shown below. A2 A4 A5 A3 Task Duration (days)…
A: Using Forward Path, find Early Start of the activity = Early Finish of predecessor activity Early…
Q: • Draw the Network diagram. • Calculate expected time and variance for each activity. • Find the…
A: Let: a= OPTIMISTIC TIME b= PESSIMISTIC TIME m= MOST LIKELY TIME Te = EXPECTED TIME = (a+4m+b)/6…
Q: Draw a project network. b. What are the critical activities? c. What activity has the most slack…
A: The Path is mentioned in red path
Q: Draw the network diagram based on the information given below. Calculate the ES, EF, LS, LF and…
A: Using the details given in the table, the following network diagram can be prepared.
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 3 images
- Instructions ASSIGNMENT PROJECT SCENARIO: You are married and you are the father or mother of a family of five with kids ages 10, 13 and 15) and a dog. The family has decided to take a camping trip when the children are out of school for the summer. The planned family camping trip is the project you will use to complete this assignment. INSTRUCTIONS: Create a Responsibility Matrix for no less than seven activities to be addressed in preparation for the family camping trip. Every member of the family must be assigned primary responsibility to complete at least or more activities for the project. Also, decide whether the dog will go on the camping trip with the family or whether arrangements will be made for someone to care for the dog while the family is away. Based on your decision regarding the dog, you must include at least one activity associated with the dog as part of the project responsibility matrix. Within the matrix, use "R" to indicate which individual has primary…a. Develop a network for this projectPlease do not give solution in image format thanku Scenario: Your a Sr. Project Manager . In Jan of 2019 you were awarded a $5 million dollar contract and you are to be complete by Nov 31, 2019. Your liquidating damages are 5,000 a day for everyday you are not finished. You are allowed 10 days of weather delays, however you incurred 21 days. Your T&Cs also specify you are to request extensions and extended weather impact delays within 24hrs of the impact. Your contract manager failed to do so for 5 of the days. Your productivity was .66 and therefore you missed your deadline. You completed the project on Feb 15, 2020. Your discussion to explain how much did you lose from the liquidating damages, what type of contract this could be that restricted you to LDs and completions date, what was your final contract value after liquidating damages and Cost Overrun for labor and equipment at $35,000 a week past your completion date.
- expalin all these in details a . SPECIFIC – Goal is to provide H&P food firm)a media coverage for the launch event of the app. b. MEASURABLE – There must be at least 5 local Media companies to cover the launch event and 3 newspaper and magazine editors. c. ATTAINABLE - To get media coverage budget will be $25000. d. RELEVANT – e. TIME BOUND – All the arrangements must be made 5 days prior to the launch event for better preparation. PLEASE PROVIDE CORRECT ANSWER WITH EXPLANATIONEX6-12 (Algo) You are creating a customer database... You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Given the information below, complete the forward and backward pass, compute activity slack, and identify the critical path. How long will this project take? ABCDACHSX K L Description Systems Subsystem A design Subsystem B design Subsystem C design Program A Program B Program C Subsystem A test Subsystem B test Subsystem C test Integration Integration test days. Predecessor None A A A B с D E F G H, I, J K Time (days) 7 3 1 3 5 15 5 3 3 5 3A developer is subdividing I some land for a residential development in the Calins. This is the activity table. Due to ctivity I was delayed a long wet season delayed by 10. weeks. What project completion time? the was. full impact of the delay on the Cade/ Activity A B C D E s Ст H 1 hy J K L purchase land **** prepare plans submit plans to cancil arrange finance do find survey do road works Time/meeks) Predecessor 1.2 8 12 3 2 submit subdivision plans inst all sewera storm water mains delave electricity a phone lines остан d advertise for sale sell blocks repay cans 10 6 DATE 63 12 12 2 A♡ с D E B E ww B G, J FHIK.
- (1) Suppose a project manager is reviewing the project management plan, the work performance data, and the project schedule. She is getting ready to do next? Work the project plan. Plan the project schedule. Start Control Schedule. Create the WBS. (2) During the Control Schedule process, what is one of the most common outputs? Stakeholder meeting Team meeting Vacation request Change requestmpletion Status: onds. A Moving to another question will save this response. Question 7 Changes in accounting estimates are: 1poi O A. Reported in future periods only. O B. Accounted for in current and future periods. O C. Reported in past periods only. O D. Reported as prior period adjustments. A Moving to another question will save this response. ESUS DIC esc 3 E fab A(Please do not give solution in image format thanku) Imagine you have been assigned a project to get your office premises renovated in the minimum possible number of days. Discuss planning details of the same in terms of: Any 3 objectives of the project • Any 3 methods used to assess the cost • Any 3 methods used to estimate the schedule of the project
- 1. If you want to manage the default settings for all of the components you intend to use for a project, you would access the Components tab of the option of Project Manager. A. Project Description B. Project Properties C. Insert Component D. ProjectsBriefly describe each of the following terms as used in project management (i) Milestone (ii) float (iii) contract (iv) dummy activity (v) Deliverable (vi) Resource loading (vii) resources levellingCreative Homework/Short Project Imagine that you are building your own e-commerce site. Having a keen understanding of the importance of de- fining and putting in place a set of conversions and metrics in advance of launching the site, you have incorporated the definitions and develop- ment of specific conversions for tracking into the planning of the website. List which actions on the site would indicate a conversion for track- ing purposes and how they would align with the goals of your business. Because this is your web- site, feel free to assume the inclusion of any sorts of features or elements (conventional or uncon- ventional) that you believe would be valuable in terms of the website's look and feel that would enable better tracking and analysis of marketing performance.