I need help for number 12, please.
Based on question number 11, which I already know the answer, find number 12. First image is the answer for number 11.
11. Building a backyard swimming pool consists of nine major activities. The activities and their immediate predecessors are shown. Develop the project network.
For number 12, see the second image
12. Assume that the activity time estimates (in days) for the swimming pool construction project in Problem 11 are as follows:
a. What are the critical activities?
b. What is the expected time to complete the project?
c. Based only on the critical path, what is the estimated probability that the project can be completed in 25 or fewer days?
Trending nowThis is a popular solution!
Step by stepSolved in 3 steps with 3 images
- Asssistarrow_forwardCharlie Cook was able to determine the activity times for constructing his chemical contaminant tracking machine. Cook would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Q Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A B C D 7 8 2 1 Charlie's earliest start (ES) and earliest finish (EF) are: A A Activity A EFGH ES EF 7 5 7 11 8 B B C, E D, Farrow_forwardIn your innovative project, you are requested to produce a documentary film about the training experience of the property development team. The table 1 below shows the following activities: After the script has been approved and the location confirmed (activity A), filming of the documentary can begin; there are six scenes to be filmed (activities B through G) and, due to the nature of the documentary, there are several dependencies that determine when each activity can be completed. Once the final scene has been filmed, the documentary can be cut and edited before presenting it to the customers for review. The project begins at time 0. This means that the activity A starts with 0 and has an estimated duration of 2 days; see further details in Table 1 below. Table 1 Activity Description Estimated duration Immediate in days Predecessor(s) A Develop and obtain approval for the script В Film scene 1 A Film scene 2 1 A D Film scene 3 2 B E Film scene 4 4 В Film scene 5 2 B; C G Film scene…arrow_forward
- Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity A B с D Time (weeks) 5 8 2 1 Immediate Predecessor(s) A A Dave's earliest start (ES) and earliest finish (EF) are: Activity A Activity EFGH ES Time (weeks) 3 EF 5 5 10 7 Immediate Predecessor(s) B B C, E D, Farrow_forwardConsider a project that has been modeled as in the table below. Part a) Draw the PERT/CPM network for this project and determine the project’s expected completion time μP and its critical path. Part b) Suppose the standard deviations of the activity durations are σA = 2, σB = 1, σC = 0, σD = 2, σE = 3, and σF = 0. Then please estimate the standard deviation of the overall project’s standard deviation σP . Part c) Suppose for the standard Normal random variable Z, we know P[−1 ≤ Z ≤ +1] ' 68%, P[−2 ≤ Z ≤ +2] ' 95%, and P[−3 ≤ Z ≤ +3] ' 99.7%. Then, approximately what time T is one for which there is only a less than 2.5% chance for the completion time to beat (be shorter than)? *Please answer a-c and type your work and answers or write them neatly please* Thank youarrow_forwardPlease solve my Problem as Soon as possible. Thank You!arrow_forward
- Need help don't understand. Please include answers and explanation.arrow_forwardBelow is a network diagram that represents a university revamp project. The project manager analyzes this project using the critical path (CP) method. Activity durations are indicated on the networkarrow_forwardWhat is the value of the missing item labeled (a) in the table above? Round to the nearest integer. What is the value of the missing item labeled (b) in table above? Round to two decimals. Draw the network diagram for this project. Clearly label the earliest start, earliest finish, latest start, latest finish and slack for each activity. Specify the critical path and the critical activities. State the expected C.P. duration State the variance of the critical path. What is the probability that the dashboard will be delivered within 20 days?arrow_forward
- A project has 7 activities P, Q, R, S, T, U, and V. Three time estimates (optimistic, most-likely, pessimistic) are used for each activity. Write down your answers to all parts of the question in the box given below. Give your answer to 3 decimal places. (Note (a) has of 2 parts and (b) has of 3 parts) For activity Q, these time estimates are as follows: optimistic time = 9, most-likely time = 14, pessimistic time = 20. Write down the average activity time for Q the variance of activity time for Q. The critical path of this project has a mean project time of 44 days and a standard deviation of 5 days. Assume project completion time is normally distributed. Find the probability that the project will be completed in 47 days. Find the probability that the project will take more than 40 days. We want to set a deadline for this project completion. If the probability of meeting this set deadline is 0.88, what will be the deadline for this project.arrow_forwardThe following represents a project that should be scheduled using CPM a. Complete the table b. Draw the Network Diagram c. What is the critical path? d. What is the expected project completion time?' e. What is the probability of completing this project within 16 days?arrow_forwardA contractor needs to complete a project. The project involves 10 activities (labeled A, B, ..., J) with precedence relationship in network below. The estimate (in weeks) of the duration of each activityis in the table below. a. The mean and variance of the activity time for A~F are given in the table. Find the mean and variance of the activity time for the remaining arcs.b. Identify the critical path and then compute the mean and variance of the project completion time.c. What is the probability that the project is completed between 32 and 36 weeks?d. What completion time should the contractor claims to be 95% sure of completing the project by then?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.