Construct an activity network diagram using Table 3a.
Activity |
A |
B |
C |
D |
E |
F |
G |
Predecessors |
- |
- |
A |
A,B |
D |
C,E |
E |
Expected Time(WKS) |
7 |
9 |
12 |
8 |
9 |
6 |
5 |
Table 3a Activity Durations and relationship
- Conduct a forward and backwards pass for the activity network diagram that you
have constructed and identify the critical path and its duration.
- Calculate the slack on all of the activities, and proceed to analyze how knowing the slacks can help to manage
schedule risk the a project
3b. Assuming that there is the risk of exceeding the project schedule baseline for 7 weeks, critically evaluates the options available that could be used to bring the project on track
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by stepSolved in 2 steps with 1 images
Knowledge Booster
Similar questions
- B indicate critical path C what is expected completion for the project? D what is the probability that the project will take more than 30 days to complete?arrow_forwardBM HL Assignment 1- Due Date 24 March 2022 5. Construct an activity-on-arrow precedence diagram for each of the following cases. Note that each case requires the use of a dummy activity. ja) Draw AON diagram of the activity above! b) Determine the critical path! Activity Precedes Activity Duration (weeks) A В 3 C 4 D A E А, В F C 7 G D,E 4 H F,G 5 65Narrow_forwardDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity A B с D Time (weeks) 5 8 2 1 Immediate Predecessor(s) A A Dave's earliest start (ES) and earliest finish (EF) are: Activity A Activity EFGH ES Time (weeks) 3 EF 5 5 10 7 Immediate Predecessor(s) B B C, E D, Farrow_forward
- Paragraph 1. Draw the Activity on Node network. 2. Perform the CPM calculations using the forward and backward pass. ABCDEFGH 3. List the activities that are on the critical path. 4. Complete the table with the following headings. Activity Duration ES Q Search 62853652 EF A A, B B D. E C, D F, G LS Styles hp LF TF D FF PA IF Earrow_forwardb) – Draw the Activity-on-Node (AON) diagram using the following representation for every node: Activity Description Expected Time ES EF LS LF Slack C.) Complete the following table, determine the expected time of completion assuming that the project starts at week 0 (zero) and identify the critical path for this project. Demonstrate all your calculations. On Critical Path? Activity Activity Description ES EF LS LF Slack Yes or No Locate new facilities 2 Order furniture Interview prospective staff Hire and train staff 3 4. Remodel facilities Receive and set up furniture Move in and start up 6 7 a) Complete the following table, calculate the project variance and project standard deviation. Demonstrate all your calculations.arrow_forwardFor the project below, develop the network diagram, perform CPM calculations, mark the critical path, and complete the table. Assume interruptible activities. Activity Duration IPA Type Rel Lag ES A B C D E F G LO 7 8 10 4 6 2 A A A C,D E,F SS SS FF FF 2 2 EF LS LF TF FFarrow_forward
- Please help to solvearrow_forwardAoN diagram 1. Organize the information above in an activity precedence table showing the activity, precedent and duration (calculated using the PERT weighted average formula and round to the nearest integer). 2. Draw an AON network diagram and calculate its early start, early finish, late start and late finish times, floats (Free and total) for each activity. Make sure you fully label all nodes in the network. 3. Identify the project’s critical path and its length.arrow_forwardEvent Event Predecessor Time A - 2 B A 6 C A 4 D A 2 E B 4 F B;C;D 5 G B 3 H E;F 2 Based on table above : a) create the network planning b) identification of the critical path c) project time requirementsarrow_forward
- Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Time Activity (weeks) 6 7 ABCO 3 2 Immediate Predecessor(s) A A D Dave's earliest start (ES) and earliest finish (EF) are: Time Activity (weeks) 4 EFGHI 6 10 7 Immediate Predecessor(s) B B C, E D,Farrow_forwardShown below is the project network diagram for a small office renovation project. The numbers in the nodes are the activity times. What is the slack time for activity A? 7 5 3 0arrow_forward########## i want answer within one hour, i will upvote. Thanks in advancearrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.