(i) Construct a network diagram showing the various logical activity relationships from this information (ii) Perform a forward and backward pass to complete the activity boxes (iii) Highlight the critical path on your diagram and state the earliest project completion time.
Q: (1i) Construct a network diagram showing the various logical activity relationships from this…
A: A project schedule network diagram indicates the sequential and analytical relationship between…
Q: The following table lists the activities for a small part of a project with various durations and…
A: PERT is the project management technique used to schedule the tasks flow and predict the completion…
Q: ACTIVITY PREC. ACT. TIME ESTIMATES (days) to 2 6. A. 2. D. 2 B. 7 C, D G. 2. r.G 2. ) Construct a…
A: As per the guidelines, the first 3 subparts are solved. Expected time = to+4×tm+tp6 Using the…
Q: SESSION 2– Individual exercise (for marks) Given the following activity precedence table, please…
A: The question is related to Critical Path Analysis. The details are given.
Q: A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C.…
A: Network diagram as per given information:
Q: a) What are the activities on the critical path (using the letters provided) b) What is the shortest…
A: We are allowed to do first three sub-parts only. The answer is as below:
Q: The figure shows the network diagram of a project along with the activity durations (T). In this…
A: A project schedule network diagram shows the sequential and analytical connection between tasks in a…
Q: Which of the following activities is not part of defining a project?a. The project triangleb. The…
A: An organization has numerous projects running at a time and numerous projects in the pipeline to be…
Q: 1. Organize the infomation above in an activity precedence table showing the activity, precedent and…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: 2. As project manager, you need to reduce the project duration as requested by the client. To make…
A: Given data is
Q: . Identify the critical path. . Develop the activity schedule for the project. If your answer is…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: Q1- The schedule for one of the projects was as in Table No. (1), answer the following- 1- Draw the…
A: Below is the solution:-
Q: Explain how you will employ scope management to a new project you have been tasked to manage.
A: Project scope is a task or work that needs to be completed in order to deliver the product within…
Q: With the use of a diagram, show (illustrate) the typical levels of project staffing related to each…
A: A project is initiated with an objective and to fulfill the objective the company defines the…
Q: 1- Calculate the total project time and floats 2- Identify activities on the critical path
A: In this question table data, we have activity information, for each activity, we have been given…
Q: (a) Draw a project netvork. (Submit a file vith a maximum size of 1 MB.) Browse. No file selected.…
A: A project schedule network diagram shows the sequential and analytical association between tasks in…
Q: The project manager at Golden Projects is preparing status reports for other project stakeholders.…
A: Operation management in an organization aims at providing the highest efficiency possible. It…
Q: Discuss an example of a work-related project that is able to be broken down into structure, tasks,…
A: CPM/PERT charts are very resourceful tools that used to help in scheduling and managing complex…
Q: Define a process in project management with the help of an example?
A: Project management: Project management is defined as it is a structured process of…
Q: A project manager has compiled a list of major activities that will be required to install a…
A: A manager wants to put in a computer data system within the company. The activity, immediate…
Q: Subject: Critical Path Method as a Project Management Technique Please answer the following…
A: Given data is
Q: A chart that shows both the time and sequence for completing the activities in a project is?…
A: A chart that shows both the time and sequence for completing the activities in a project is a Gantt…
Q: The information of a project is shown below. Activity A, 7 days, 13 workers, IP =none Activity B, 3…
A: Activity Duration Immediate Predecessor A 7 - B 3 - C 4 - D 3 A E 6 B F 8 C
Q: The most critical responsibilities Anne has to marshal, schedule and manage on a daily basis are…
A: There are some resource which are to be considered during the life time of the project. Such project…
Q: A project manager has compiled a list of major activities that will be required to install a…
A:
Q: Construct a Network Diagram showing the various logical activity relationships from this…
A: A project schedule network diagram shows the sequence of the task that is performed to complete a…
Q: I need a detailed explanation and assistance to solve this problem: A company decides to plan a…
A: Drawing the project network as shown in the diagram using AOA convention we represent the activities…
Q: 1. (SHOW YOUR COMPLETE WORK) The activities needed for a new project your company is undertaking are…
A: In Project Management, the estimated time to complete the project is calculated using the project…
Q: To properly evaluate, project managers were asked to prepare AON and AOA of the project based on the…
A: Given data is
Q: Using the below project network diagram, what is the Earliest Start (ES) time of activity G? The…
A: ES or Earliest starting time indicating the minimum possible time for starting an activity. Here, we…
Q: The Scott Corey accounting firm is installing a new computer system. Several things must be done to…
A: The method of analyzing the set of activities related to the project of the company is known as the…
Q: i. Calculate the expected time for each activity ii. Draw a Gantt Chart from the same information…
A: As per Bartleby guidelines we can only solve first 3 sub par Below is the solution:-
Q: Project Planning Practice Draw or make a Gantt Chart for the following Activities Draw or make…
A:
Q: cts to implement in project man
A: To be a good project manager, one must have a wide range of abilities. It requires a variety of…
Q: Using the network diagram constructed in Problem 1,(a) Calculate the completion time for the…
A: The completion time of the project can be calculated as below:
Q: a) Construct a network for this project b) Find a project schedule to minimize the completion time…
A: Given data is
Q: Three recent college graduates have formed a partnership and have opened an advertising firm. Their…
A: Expected time Te=Optimistic Time +4×Most Likely Time +Pessimistic Time6 Variance σ2=Pessimistic Time…
Q: Ql: For activitics shown in table below, find the new time of project after updating, if the project…
A: ANSWER IS AS BELOW:
Q: To design a new app, a project manager has gathered the time information for each activity as shown…
A: Activity Optimistic Most Likely Pessimistic Immediate Predecessors A 1 4 7 - B 2 6 10 - C 3 3…
Q: (i) Construct a network diagram showing the various logical activity relationships from this…
A: A project schedule network diagram shows the sequential and analytical relationship between tasks in…
Q: (i) Construct a Network Diagram showing the various logical activity relationships from this…
A: A project schedule network diagram shows the sequential and analytical relationship between tasks in…
Q: Assess the planning, monitoring, and controlling of projects using the Program Evaluation and Review…
A: The Program Evaluation Review Technique (PERT) is a technique used in project management to…
Q: Questions 1. Organize the information above in an activity precedence table showing the activity,…
A: Answer of all pats are below:-
Q: Why is it critical to determine the sequence of activities in a project? Discuss diagrams that…
A: Sequence of activities in a project A project manager is in charge of the project's overall…
Q: Part 2: The activity list shown below represents the activities, the job logic and activities'…
A: The AOA network diagram is the graphical representation that represents the activities and their…
Q: 1. Organize the information above in an activity precedence table showing the activity, precedent,…
A: Below is the solution:-
Q: The following is NOT one of the advantages of CPM and PERT: a) Straightforward concept and not…
A: Option A is incorrect Project management and review techniques often called the PERT approach and…
Step by step
Solved in 2 steps with 2 images
- b) Table Q1a shows the logic for a particular project. Time (days) Activity A Precedence 2 В A 3 C A 4 D A E B 3 F B,C H E 5 F 4 J H 3 G,H, I J,K K 4 L Table Q1a. Logic for project activities A through L. (i) Construct a Network Diagram showing the various logical activity relationships from this information. (ii) Perform a forward and backward pass completing the activity boxes. (ii) Highlight the critical path on your diagram and state the earliest project completion time. c) Provide an example of an ethical dilemma in engineering project management and explain how a code of ethics might be used to help the project manager in the decision making process.a) Explain the purposes of a dummy activity in a network diagram. (b) Table 1 shows the activities of a project and their durations. Table 1Activity Preceding Activity Duration (Days)A – 9B – 3C A 8D A 2E A 3F C 2G C 6H C 1J B,D 4K F,J 1L E,H,G,K 2M E,H 3N L,M 4 i. Draw the project network.ii. Determine its critical path and completion time.iii. Calculate the total float for the non-critical chains. 2. a) Outline FOUR different types of stockholding casts. b) i) Explain the periodic review system of inventory control.ii) State TWO disadvantages of the periodic review system. c) Explain FOUR major functions of an office. d) A common trend in the office management in many large manufacturing organizations today is to set up an ‘organization and method’ (O&M) team, which is normally directly answerable to the Chief Executive Officer. Highlight FOUR responsibilities of such a team. 3. a) State FOUR objectives of maintenance in a manufacturing plant. b) Explain the purpose of the…on in OMGT 1013 x (1) Facebook - usl-tuguegarao.neolms.com/student take_quiz_assignment/display/23380965?part=14&r ODE 606 ÖMGT 1013 Item 14 of 78 Refer to the given information below for a particular project. Activity Immediate Predecessors Time (weeks) A None 2 BD 4. 3 E F Compute the slack time for activity D A. LL
- #3) Consider the following project, all durations are in days. Construct a precedence diagram, find the critical path and which tasks have slack and how much each has. Which tasks would you recommend crashing to reduce the project duration by six days assuming that it costs the same to crash each task and no task by be crashed to less than half its original duration and tasks A and N cannot be crashed at all? Task Predecessors A B с D E F G H I J K L M N A A A B E с с G H D K L F, I, J, M Most Likely Duration 4 12 7 12 10 7 18 13 10 13 10 11 7 3#3) Consider the following project, all durations are in days. Construct a precedence diagram, find the critical path and which tasks have slack and how much each has. Which tasks would you recommend crashing to reduce the project duration by six days assuming that it costs the same to crash each task and no task by be crashed to more than half its original duration and tasks A and N cannot be crashed at all? Task Predecessors Most Likely Duration A - 8 B A 12 C A 6 D A 12 E B 10 F E 7 G C 18 H C 13 I G 10 J H 13 K D 10 L K 11 M L 7 N F, I, J, M 4 Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.(a) What is Work Breakdown Structure (WBS)? Explain in light of a building construction project while clearly give emphasis on task, duration and resources. (b) Explain the five different proformas of Planning Commission of Pakistan used in project life cycle phases. (c) Explain the following. 1. Present worth analysis 2. Effective interest rate . please solve this perfectly. subject: : Project Planning, Management & Engineering Economics 3. Project life cycle
- scenarios of a project activities (tables given below) and their required times to be completed in addition to their predecessors for developing a Website' : Activity Description Duration (days) Preceding Activities A Determine user needs 8 Review s/w and languages Purchase software 10 Design format and style 10 E Write programs A F Review outcome product with user 12 G Make revisions 4 C H Select server site E I Install on server 14 D, F Test G, H, I 3. Highlight the total time to complete the project (days) 4. Calculate the late finishing time (backwards calculations)tles and their precedence relationships. (a) Develop a complete Activity-On-Node for the project whlch has the EF, ES, LF, LS and Slack for each activity. (10 points) (b) Determine the Critical Path. (5 polnts) Immedlate Predecess Duratlon Activity Description (Weeks) or Develop the specification Design the process Source and purchase development and production instances Complete the Functional Requirements Application development Quality Assurance Testing Pilot production run Evaluate product design Evaluate application performance Write documentation report None A. 6. 6. E and F 2. H. 1. 3 J H & I "It's your attitude, not your aptitude that will determine your altitude,"-Zig Ziglar 2. Roll- out to production instance 403 CO15 2234 BOC ABC DEFGIEX6-21 (Algo) Given the following information, compute... Given the following information, compute the early, late, and slack times for the project network. Additional Lag Relationships ID Task Duration Predecessor Lag Interview users 10 Define new features A Start-start A to B Finish-finish A to B Order components Build prototype Finish-start C to D 7 E Test Finish-start C to E 4 Finish-finish D to E 4 F Field test 10 E Lag 5 A Lag 4 6 10 Lag 4 B D F 8 3 Lag 7 6. 10 Lag 6 What is the ES for Activity D? What is the LF for Activity E? What is the slack for the start of Activity E? What is the slack for the end of Activity E? What is the slack for the end of Activity B? What is the length of the project? time periods. AB
- The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS ACTIVITY A ABCDEFGH B-E-G-H b. What is the critical path? A-C-F-H OA-D-F-H A-D-G-H A A B C,D D, E F,G Project completion time a LLL23312 TIMES (DAYS) m •WNNW: 3 2 2 3 4 4 4 4 b 5 3 3 4 11 c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 2 decimal places. days 565Draw Network Diagram and calculate the earliest expected time to complete the project a. b. Activity Time Activity (weeks) ABCDEFG 3425432 Immediate Predecessor(s) none ABR Completion time for the project is Critical path: C E, FTable 3 gives time estimates in weeks for each activity (Durations are Time Expected obtained using PERT) Activity Preceded 1 Order review 2 Order vendor parts 3 Produce standard parts 4 Design custom parts Software development 5 6 Manufacture custom parts 7 Assemble 8 Test Duration 5 15 20 13 18 10 10 5 1 1 1 4 2,3,6 2,5 Resources Ryan Carly Ryan Lauren Connor Ryan Dawn Test Assuming that you have been engaged to programme the project activities indicated in Table 3 and Figure A8.1B (Air Control Project: Time Plan without Resources), USE CCPM (Critical Chain Project Management) to ESTIMATE the project duration by showing each and every stage of your programming process (indicate technical dependency with resources imposed).