Task 6. The following are consumed for the production of one unit: ➤ 18 kg of material A (price 1 € / kg and 3 m²) material B (price 2 € / m²) Direct labour per unit of product Estimated (planned) variable overheads per year Responsibility centre 14,000, € 1: Direct labour 70,000 h ===== ===== Responsibility centre 21 000, € Responsibility centre 1: 20 hours; rate 0,30€/h Responsibility centre 2: 30 hours; rate 0,50€/h Calculates: 1. variable production costs per unit 2. unit cost of production 3. full cost of one unit 2: Direct labour 180 000 h Estimated (planned)fixed overheads and general operating expenses per year Production costs - 100,000 € Selling expenses -30 000 € Administration expenses -15 000 €

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter6: Activity-based, Variable, And Absorption Costing
Section: Chapter Questions
Problem 5PB: Wrappers Tape makes two products: Simple and Removable. It estimates it will produce 369,991 units...
icon
Related questions
Question
Task 6.
The following are consumed for the production of one
unit:
➤ 18 kg of material A (price 1 € / kg and 3 m²)
material B (price 2 € / m²)
Direct labour per
unit of product
Estimated (planned)
variable overheads
per year
Responsibility centre
14,000, €
1:
Direct labour
70,000 h
=====
=====
Responsibility centre
21 000, €
Responsibility
centre 1:
20 hours; rate
0,30€/h
Responsibility
centre 2:
30 hours; rate
0,50€/h
Calculates:
1. variable production costs per unit
2. unit cost of production
3. full cost of one unit
2:
Direct labour
180 000 h
Estimated
(planned)fixed
overheads and
general operating
expenses per year
Production costs -
100,000 €
Selling expenses -30
000 €
Administration
expenses -15 000 €
Transcribed Image Text:Task 6. The following are consumed for the production of one unit: ➤ 18 kg of material A (price 1 € / kg and 3 m²) material B (price 2 € / m²) Direct labour per unit of product Estimated (planned) variable overheads per year Responsibility centre 14,000, € 1: Direct labour 70,000 h ===== ===== Responsibility centre 21 000, € Responsibility centre 1: 20 hours; rate 0,30€/h Responsibility centre 2: 30 hours; rate 0,50€/h Calculates: 1. variable production costs per unit 2. unit cost of production 3. full cost of one unit 2: Direct labour 180 000 h Estimated (planned)fixed overheads and general operating expenses per year Production costs - 100,000 € Selling expenses -30 000 € Administration expenses -15 000 €
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Essentials of Business Analytics (MindTap Course …
Essentials of Business Analytics (MindTap Course …
Statistics
ISBN:
9781305627734
Author:
Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:
Cengage Learning
Financial & Managerial Accounting
Financial & Managerial Accounting
Accounting
ISBN:
9781337119207
Author:
Carl Warren, James M. Reeve, Jonathan Duchac
Publisher:
Cengage Learning