Please try to solve in 30 minute People are served in a process with two sequential resources. The capacities of the resources are 2 and 1.8 people per minute. What is the capacity of this process in terms of people per minute
Q: The manager of the Personnel Department at City Enterprises has been reading about time-driven ABC…
A: Given, Interviewing: 45 minutes. Hiring: 60 minutes. Assessment: 75 minutes. Separation…
Q: Additional Algo 4-10 Integrated Work Electricians are trained in a process with two resources. The…
A: Capacity planning is the process of determining the resources and infrastructure required to meet…
Q: How many good parts will be produced? How many parts will have been damaged and removed?
A: THE ANSWER IS AS BELOW:
Q: If an eight - inch -square cake serves four people, how many 12 inch square cakes are needed to…
A: An equivalent is described as a property or a state of being the same or equal. It is important to…
Q: 'n a system with a single capacity 1 server with Random.Exponential(0.25) minutes inter-arrival time…
A: The Utilization Rate is the rate at which you use the all-out accessible season of your assets. It…
Q: An ice cream stand has a single window and one employee to serve customers. During their busy…
A: Utilization is characterized as the measure of a representative's accessible time utilized for…
Q: The check-out area of a grocery store has the average customer interarrival time = 2 minutes, the…
A: Given, Interarrival time of customers = 2 minutes. In one minute period, 1÷2 = 0.5 customers arrive…
Q: Hilltop Restaurant is located in Dempsey Hill. The restaurant has a capacity of 35 tables to serve…
A: As per Little's law, L = λ×W Here, L = Average number of customers in the system λ = Average…
Q: Panini, a popular sandwich shop, offers 3 types of sandwiches: grilled vegetables, grilled chicken,…
A: Following formula can be used to calculate implied utilization rate: Firstly, the workload needs to…
Q: n a manufacturing process, a molded part spends 7 hours in inventory before being placed in a…
A: The objective of the question is to calculate the percentage of value-added time in the total time…
Q: McDonalds has a drive-through window and, during peak lunch times, can handle a maximum of 85 cars…
A: Productivity is the measurement of actual output that a company is able to produce by inputting the…
Q: Consider the following tasks that must be assigned to four workers on a conveyor-paced assembly line…
A: This concept is from labor and working machine hours in operations management, where we calculate…
Q: What is the mean assembly time per product unit for size C in terms of hour? a) 0,1136 b) 0,0251 c)…
A: The answer is as follows:
Q: An architect has five projects to complete. She estimates that three of the projects willrequire one…
A: Compute the time required to complete the project: Time required to complete=1+1+1+3+4=10
Q: ew equipment, it was possible to transfer one of the workers to another department, and equipment…
A: The answer is as below:
Q: A Company that makes shopping carts for supermarkets and other stores recently purchased some new…
A: Given Information: Before Purchase of new equipment:- Number of workers used = 6 Wage of a worker =…
Q: If value for an airline passenger is defined as reaching from point A (departure terminal of home…
A: The steps that an airplane company can follow to minimize the total time from departure terminal A…
Step by step
Solved in 2 steps
- . In the welding operations of a bicycle manufacturer, a bike frame has a flow time of about 11.5 hours. The time in the welding operation is spent as follows: 2 hours waiting in front of the cutting machine for the batch to start, 2 hours waiting for the setupof the machine, 1 hour waiting for the other pieces of the batch to go through cutting, 1 minute at the cutting machine, and 3 hours waiting for the transfer to the welding machine. Then, at the welding machine, the unit spends 1 hour waiting in front of the welding machine for the batch to start, 1 hour waiting for the setup of the welding machine, 0.5 hour waiting for the other pieces of the batch to go through welding, 0.5 minute at the welding machine, and 1 hour waiting for the transfer to the next department. Determine the exact flow time. What is the value-added percentage of the flow time?Need explanation and correct answer. Make sure, the answer is correct.In the welding operations of a bicycle manufacturer, a bike frame has a flow time of about 12.75 hours. The time in the welding operation is spent as follows: 2 hours waiting in front of the cutting machine for the batch to start, 2 hours waiting for the setup of the machine, 2 hour waiting for the other pieces of the batch to go through cutting, 1 minute at the cutting machine, and 2 hours waiting for the transfer to the welding machine. Then, at the welding machine, the unit spends 1 hour waiting in front of the welding machine for the batch to start, 1 hour waiting for the setup of the welding machine, 0.75 hour waiting for the other pieces of the batch to go through welding, 0.25 minute at the welding machine, and 2 hour waiting for the transfer to the next department. (Round your percentage answer to 4 decimal places.) Determine the exact flow time. What is the value-added percentage of the flow time? 0.0604 percent
- In the welding operations of a bicycle manufacturer, a bike frame has a flow time of about 11.5 hours. The time in the welding operation is spent as follows: 2 hours waiting in front of the cutting machine for the batch to start, 2 hours waiting for the setup of the machine, 1 hour waiting for the other pieces of the batch to go through cutting, 1 minute at the cutting machine, and 3 hours waiting for the transfer to the welding machine. Then, at the welding machine, the unit spends 1 hour waiting in front of the welding machine for the batch to start, 1 hour waiting for the setup of the welding machine, 0.5 hour waiting for the other pieces of the batch to go through welding, 0.5 minute at the welding machine, and 1 hour waiting for the transfer to the next department. Determine the exact flow time. What is the value-added percentage of the flow time?(round percentage answer to 4 decimal places.) answer:_______percentPatients are arriving at a clinic at a rate of two per minute. Each patient's visit consists of four steps: check in, record vital signs, receive treatment, and check out. A receptionist takes 1 minute to check a patient in. A nurse takes 2 minutes to record the patient's vital signs. A doctor spends 10 minutes with a patient. A staff member takes 3 minutes to check a patient out. What is the process capacity in patients per hour?In the welding operations of a bicycle manufacturer, a bike frame has a flow time of about 16.65 hours. The time in the welding operation is spent as follows: 3 hours waiting in front of the cutting machine for the batch to start, 3 hours waiting for the setup of the machine, 1 hour waiting for the other pieces of the batch to go through cutting, 1 minute at the cutting machine, and 3 hours waiting for the transfer to the welding machine. Then, at the welding machine, the unit spends 2 hour waiting in front of the welding machine for the batch to start, 2 hour waiting for the setup of the welding machine, 0.65 hour waiting for the other pieces of the batch to go through welding, 0.4 minute at the welding machine, and 2 hour waiting for the transfer to the next department. (Round your percentage answer to 4 decimal places.) Determine the exact flow time. What is the value-added percentage of the flow time? percent cetion MacBook Air ww.
- A manufacturing company has a small production line dedicated to the production of a particular product. The line has four stations in serial. Inputs arrive at station 1 and the output from station 1 becomes the input to station 2. The output from station 2 is the input to station 3 and so on. The output from station 4 is the finished product. Station 1 can process 2,700 units per month, station 2 can process 2,500/month, station 3 can process 2,300/month, and station 4 can process 2,100/month. What station sets the maximum possible output from this system? What is that maximum output number?Panini, a popular sandwich shop, offers 3 types of sandwiches: grilled vegetables, grilled chicken, and pastrami. Demand (sandwiches per hour) are Grilled Vegetables = 25, Grilled Chicken = 15, and Pastrami = 10. There are up to five steps in the process of making sandwiches, listed below with processing times. Step Grilled Vegetables Grilled Chicken Pastrami Cut bread 0.75 minutes 0.75 minutes 0.75 minutes Grill 1.4 minutes 1.4 minutes Slice meat 3 minutes Toast 2 minutes 2 minutes 2 minutes Wrap 0.5 minutes 0.5 minutes 0.5 minutes Only 50 percent of customers want their sandwich toasted, no mattor which sandwich is ordered. Suppose Panini employs 1 worker at each step. Instructions: Round all answers to 1 decimal place. (a) What is the implied utilization of each of the five steps in this process? 62.5 % 93.3 % 50.이% 83.3 % 41.7 % Cut Grill Slice Toast Wrap (b) What is the actual and maximum flow rates of the three sandwich types? per hour Veg Chicken per hourA manufacturing company has a small production line dedicated to the production of a particular product. The line has four stations in serial. Inputs arrive at station 1 and the output from station 1 becomes the input to station 2. The output from station 2 is the input to station 3 and so on. The output from station 4 is the i nished product. Station 1 can process 2,700 units per month, station 2 can process 2,500/month, station 3 can process 2,300/month, and station 4 can process 2,100/month. What station sets the maximum possible output from this system? What is that maximum output number?
- The check-out area of a grocery store has the average customer interarrival time = 2 minutes, the average processing time of each cashier = 6 minutes, and in total 4 cashiers. The average waiting time for each customer is 8 minutes. What is the average number of customers in the system (including waiting and using the service)? a 3 b 7 c 6 d 4A work cell in a local manufacturer has a workstation with 4 machines that form a line (Machine 1-Machine 2-Machine 3-Machine 4). Each unit needs to pass through each machine in order to be completed. Each machine has a production capacity of four units per hour. What is the process time of the work cell in minutes per unit? 15 4 8 16A Company that makes shopping carts for supermarkets and other stores recently purchased some new equipment that reduces the labor content of the jobs needed to produce the shopping carts. Prior to buying the new equipment, the company used 6 workers, who produced an average of 78 carts per hour. Workers receive $10 per hour, and machine coast was $36 per hour. With the new equipment, it was possible to transfer one of the workers to another department, and equipment cost increased by $13 per hour while output increased by four carts per hour.a) Compute the multifactor productivity (MFP) (labor plus equipment) under the Prior to buying the new equipment. The MFP (carts/$) = (round to 4 decimal places).b) Compute the % growth in productivity between the Prior to and after buying the new equipment. The growth in productivity = % (round to 2 decimal places)