On February 1, 2023, Ivanhoe Contractors agreed to construct a building at a contract price of $5,840,000. Ivanhoe estimated total construction costs would be $4,032,000 and the project would be finished in 2025. Information relating to the costs and billings for this contract is as follows: Total costs incurred to date Estimated costs to complete Customer billings to date Collections to date 2023 Fill in the correct amounts on the following schedule. For percentage-of-completion accounting and cost-recovery accounting, show the gross profit that should be reported for 2023, 2024, and 2025. 2024 2023 2024 $1,512,000 $2,664,000 2,520,000 1,776,000 2,240,000 4,032,000 2,040,000 3,540,000 2025 Percentage-of-Completion Gross Profit 2023 2024 2025 2025 $4,620,000 -0- 5,640,000 5,540,000 LA Cost-Recovery Gross Profit

Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter17: Advanced Issues In Revenue Recognition
Section: Chapter Questions
Problem 26E
icon
Related questions
Question

do not give solution in image format 

On February 1, 2023, Ivanhoe Contractors agreed to construct a building at a contract price of $5,840,000. Ivanhoe estimated total
construction costs would be $4,032,000 and the project would be finished in 2025. Information relating to the costs and billings for
this contract is as follows:
Total costs incurred to date
Estimated costs to complete
Customer billings to date
Collections to date
2023
Fill in the correct amounts on the following schedule. For percentage-of-completion accounting and cost-recovery accounting, show
the gross profit that should be reported for 2023, 2024, and 2025.
2024
2023
2024
$1,512,000
$2,664,000
2,520,000 1,776,000
2,240,000 4,032,000
2,040,000 3,540,000
2025
Percentage-of-Completion
Gross Profit
2023
2024
2025
69
2025
$4,620,000
-0-
5,640,000
5,540,000
DA
Cost-Recovery
Gross Profit
Transcribed Image Text:On February 1, 2023, Ivanhoe Contractors agreed to construct a building at a contract price of $5,840,000. Ivanhoe estimated total construction costs would be $4,032,000 and the project would be finished in 2025. Information relating to the costs and billings for this contract is as follows: Total costs incurred to date Estimated costs to complete Customer billings to date Collections to date 2023 Fill in the correct amounts on the following schedule. For percentage-of-completion accounting and cost-recovery accounting, show the gross profit that should be reported for 2023, 2024, and 2025. 2024 2023 2024 $1,512,000 $2,664,000 2,520,000 1,776,000 2,240,000 4,032,000 2,040,000 3,540,000 2025 Percentage-of-Completion Gross Profit 2023 2024 2025 69 2025 $4,620,000 -0- 5,640,000 5,540,000 DA Cost-Recovery Gross Profit
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning