Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted for the year at $600,000 divided into two departments: Fabrication, $420,000, and Assembly, $180,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require 8 direct labor hours in Fabrication and 4 direct labor hours in Assembly. The bass boats require 4 direct labor hours in Fabrication and 8 direct labor hours in Assembly. Each product is budgeted for 250 units of production for the year. If required, round all per unit answers to the nearest cent. a. Determine the total number of budgeted direct labor hours for the year in each department. Fabrication direct labor hours Assembly direct labor hours b. Determine the departmental factory overhead rates for both departments. Fabrication Department rate $ per dlh Assembly Department rate $ per dlh c. Determine the factory overhead allocated per unit for each product using the department factory overhead allocation rates. Total factory overhead $ per speed boat Total factory overhead $ per bass boat
Variance Analysis
In layman's terms, variance analysis is an analysis of a difference between planned and actual behavior. Variance analysis is mainly used by the companies to maintain a control over a business. After analyzing differences, companies find the reasons for the variance so that the necessary steps should be taken to correct that variance.
Standard Costing
The standard cost system is the expected cost per unit product manufactured and it helps in estimating the deviations and controlling them as well as fixing the selling price of the product. For example, it helps to plan the cost for the coming year on the various expenses.
Multiple Production Department Factory
The total factory overhead for Bardot Marine Company is budgeted for the year at $600,000 divided into two departments: Fabrication, $420,000, and Assembly, $180,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require 8 direct labor hours in Fabrication and 4 direct labor hours in Assembly. The bass boats require 4 direct labor hours in Fabrication and 8 direct labor hours in Assembly. Each product is budgeted for 250 units of production for the year.
If required, round all per unit answers to the nearest cent.
a. Determine the total number of budgeted direct labor hours for the year in each department.
Fabrication | direct labor hours |
Assembly | direct labor hours |
b. Determine the departmental factory overhead rates for both departments.
Fabrication Department rate | $ per dlh |
Assembly Department rate | $ per dlh |
c. Determine the factory overhead allocated per unit for each product using the department factory overhead allocation rates.
Total factory overhead | $ per speed boat |
Total factory overhead | $ per bass boat |