Table 3 gives time estimates in weeks for each activity (Durations are Time Expected obtained using PERT) Activity Preceded Duration Resources 1 Order review 2 Order vendor parts 3 Produce standard parts 4 Design custom parts 5 Software development 6 Manufacture custom parts 7 Assemble 8 Test 5 15 20 13 18 10 10 5 1 1 1 1 4 23,6 2,5 Ryan Carly Ryan Lauren Connor Ryan Dawn Test Assuming that you have been engaged to programme the project activities indicated in Table 3 and Figure A8.1B (Air Control Project: Time Plan without Resources), USE CCPM (Critical Chain Project Management) to ESTIMATE the project duration by showing each and every stage of your programming process (indicate technical dependency with resources imposed).

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Table 3 gives time estimates in weeks for each activity (Durations are Time Expected obtained using PERT)
Activity
Preceded
1
Order review
2
Order vendor parts
3 Produce standard
parts
4 Design custom parts
Software development
5
6 Manufacture custom
parts
7 Assemble
8
Test
Duration
5
15
20
13
18
10
10
5
1
1
1
4
2,3,6
2,5
Resources
Ryan
Carly
Ryan
Lauren
Connor
Ryan
Dawn
Test
Assuming that you have been engaged to programme the project activities indicated in Table 3 and Figure A8.1B (Air
Control Project: Time Plan without Resources),
USE CCPM (Critical Chain Project Management) to ESTIMATE the project duration by showing each and every stage of
your programming process (indicate technical dependency with resources imposed).
Transcribed Image Text:Table 3 gives time estimates in weeks for each activity (Durations are Time Expected obtained using PERT) Activity Preceded 1 Order review 2 Order vendor parts 3 Produce standard parts 4 Design custom parts Software development 5 6 Manufacture custom parts 7 Assemble 8 Test Duration 5 15 20 13 18 10 10 5 1 1 1 4 2,3,6 2,5 Resources Ryan Carly Ryan Lauren Connor Ryan Dawn Test Assuming that you have been engaged to programme the project activities indicated in Table 3 and Figure A8.1B (Air Control Project: Time Plan without Resources), USE CCPM (Critical Chain Project Management) to ESTIMATE the project duration by showing each and every stage of your programming process (indicate technical dependency with resources imposed).
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.