buidling for an agreed upon contract price of $2,400,000 and construction is estimated to take three years at a total estimated cost of $2,000,000. Assuming costs may fluctuate over the 3-year construction period. Which statement is most accurate regarding revenue recognition for this contract? The builder should recognize revenue over time using the cost-to-cost (percentage of completion) method. The builder should wait to recognize revenue until the full construction is complete at the end of the three year period. The builder should recognize recognize revenue across the three year construction period as they collect cash payments. The builder should recognize all revenue for the contract at the start of construction when the contract is initially signed.

Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter17: Advanced Issues In Revenue Recognition
Section: Chapter Questions
Problem 10C
icon
Related questions
Question
A builder enters into a contract with a customer to redesign and update an office
buidling for an agreed upon contract price of $2,400,000 and construction is
estimated to take three years at a total estimated cost of $2,000,000. Assuming
costs may fluctuate over the 3-year construction period. Which statement is most
accurate regarding revenue recognition for this contract?
The builder should recognize revenue over time using the cost-to-cost (percentage of
completion) method.
The builder should wait to recognize revenue until the full construction is complete at
the end of the three year period.
The builder should recognize recognize revenue across the three year construction
period as they collect cash payments.
The builder should recognize all revenue for the contract at the start of construction
when the contract is initially signed.
Transcribed Image Text:A builder enters into a contract with a customer to redesign and update an office buidling for an agreed upon contract price of $2,400,000 and construction is estimated to take three years at a total estimated cost of $2,000,000. Assuming costs may fluctuate over the 3-year construction period. Which statement is most accurate regarding revenue recognition for this contract? The builder should recognize revenue over time using the cost-to-cost (percentage of completion) method. The builder should wait to recognize revenue until the full construction is complete at the end of the three year period. The builder should recognize recognize revenue across the three year construction period as they collect cash payments. The builder should recognize all revenue for the contract at the start of construction when the contract is initially signed.
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning