![FINANCIAL ACCOUNTING](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
FINANCIAL ACCOUNTING
10th Edition
ISBN: 9781259964947
Author: Libby
Publisher: MCG
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
- JUBAIL BUILDERS is constructing a multi-unit residential complex. In the prior year, JUBAIL BUILDERS entered into a contract with a customer for a specific unit that is under construction. JUBAIL has determined that the contract is a single performance obligation satisfied over time. JUBAIL BUILDERS gathered the following information for the contract during the year.
JUBAIL BUILDERS-Year Ended December 31, 2018:
Costs to date |
10,500,000 |
Future expected costs |
7,000,000 |
Work certified to date |
12,600,000 |
Expected Sales value |
22,400,000 |
Revenue taken in earlier period |
8,400,000 |
Costs taken in earlier periods |
6,650,000 |
Calculate the amounts to be included in the statement of profit or loss in respect of revenue and costs for the year ended December 31, 2018 on both methods (I) Input Method (cost basis), and (II) Output Method (Sales Basis)
Calculate the total expected profit for the year 2018?
Expert Solution
![Check Mark](/static/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by stepSolved in 3 steps
![Blurred answer](/static/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- A construction company is constructing an office building under contract for Codwell Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1,550,000 each quarter. The total contract price is $18,600,000 and the construction company estimates total costs of $17,750,000. They also estimate that the building will take 3 years to complete, and commences construction on January 2, 2021.At December 31, 2021, the construction company estimates that it is 30% complete with the construction, based on costs incurred. What is the total amount of Revenue from Long-Term Contracts recognized for 2021 and what is the balance in the Accounts Receivable account assuming Codwell Company has not yet made its last quarterly payment? Revenue Accounts Receivable Question 2 options: a $6,200,000 $6,200,000 b $5,325,000 $1,550,000 c $5,580,000 $1,550,000 d $5,325,000…arrow_forwardplease help mearrow_forwardAt the beginning of 2009, Florida Road Construction entered into a contract to build a road for the government. Construction will take four years. Th e following information as of 31 December 2009 is available for the contract: Total revenue according to contract $10,000,000 Total expected cost $ 8,000,000 Cost incurred during 2009 $ 1,200,000 Assume that the company estimates percentage complete based on costs incurred as a percentage of total estimated costs. Under the completed contract method, how much revenue will be reported in 2009? C . $1,500,000.arrow_forward
- Grein's Construction Company, entered into a fixed-price contract with Alexa Co. on July 1, 2024, to construct a four-story office building. At that time, Grein's estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,420,000. The building was completed on December 31, 2026. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows: Costs incurred to date Estimated costs to complete Billings to Axelrod, to date At 12-31-2024 $366,000 3,294,000 727,000 Year 2024 2025 2026 At 12-31-2025 $ 2,814,000 1,876,000 2,310,000 Gross Profit (Loss) Recognized At 12-31-2026 $4,747,000 0 Assuming Grein's recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years. If there is a loss, put the number in…arrow_forwardOriole Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $2050000 each quarter. The total contract price is $18222000 and Oriole estimates total costs of $17100000. Oriole estimates that the building will take 3 years to complete, and commences construction on January 2, 2021. At December 31, 2021, Oriole estimates that it is 20% complete with the construction, based on costs incurred.At December 31, 2022, Oriole Construction estimates that it is 70% complete with the building; however, the estimate of total costs to be incurred has risen to $17300000 due to unanticipated price increases. What is the total amount of Construction Expenses that Oriole will recognize for the year ended December 31, 2022? $8690000 $8325600 $12110000 $8465600arrow_forwardCurtiss Construction Company, Incorporated, entered into a fixed-price contract with Axelrod Associates on July 1, 2024, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,480,000. The building was completed on December 31, 2026. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows: Percentage of completion Costs incurred to date Estimated costs to complete Billings to Axelrod, to date At 12-31-2024 At 12-31-2025 $367,000 3,303,000 728,000 $ 2,856,000 1,904,000 2,330,000 Ren 1 and 2 10% Dan 3 60% Answer is not complete. Complete this question by entering your answers in the tabs below. Required: 1. Compute gross profit or loss to be recognized as a result of this contract for each of the three…arrow_forward
- Eureka Co. started work on a P10M fixed price construction contract in 20x1. The performance obligation in the contract is satisfied overtime. Eureka Co. measures its progress based on professional survey of performance completed to date (i.e., an output method). The estimated total contract costs are P6M. Information on the contract is as follows: 20x1 20x2 Costs incurred per year 2,700,000 1,980,000 Progress on the contract 42% 80% The customer accepted all billings but defaulted in its payment in 20x2. Eureka Co. assessed, on December 31,20x2, that it cannot collect 4% of the total contract price. Requirement: Compute for the revenues, costs of construction and profits recognized in 20x1 and 20x2, repectively.arrow_forwardTullis Construction enters into a long-term fixed price contract to build an office tower for $10,600,000. In the first year of the contract Tullis incurs $3,000,000 of cost and the engineers determined that the remaining costs to complete the project are $5,000,000. Tullis billed $5,000,000 in year 1 and collected $3,100,000 by the end of the end of the year. How should Tullis report Construction in Progress and Billings on Construction in Progress at the end of year 1 on the balance sheet assuming the use of the completed - contract method? O A. asset of $2,000,000 O B. liability of $1,900,000 O C. asset of $1,900,000 O D. liability of $2,000,000arrow_forwardOn April 1, 2025, Sandhill Inc. entered into a cost plus fixed fee contract to construct an electric generator for Sweet Acacia Corporation. At the contract date, Sandhill estimated that it would take 2 years to complete the project at a cost of $2,060,000. The fixed fee stipulated in the contract is $468,000. Sandhill appropriately accounts for this contract under the percentage-of-completion method. During 2025, Sandhill incurred costs of $762,200 related to the project. The estimated cost at December 31, 2025, to complete the contract is $1,297,800. Sweet Acacia was billed $584,000 under the contract. Prepare a schedule to compute the amount of gross profit to be recognized by Sandhill under the contract for the year ended December 31, 2025. (If an amount reduces the account balance then enter with negative sign., e.g. -45 or parentheses e.g. (45).) SANDHILL INC. Computation of Gross Profit to be Recognized on Uncompleted Contract Year Ended December 31, 2025 Total Contract Price…arrow_forward
- Curtiss Construction Company, Incorporated, entered into a fixed price contract with Axelrod Associates on July 1, 2024, to construct a four story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,240,000 The building was completed on December 31, 2026 Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows Percentage of completion Cests incurred to date Estimated costs to complete Billings to Axelrod, to date Required: At 12-11-2024 10% At 12-31-2025 $2,688,000 1,792,000 AT 12-11-2026 60% 100% $ 4,534,000 4,240,000 $363,000 3,267,000 724,000 2,250,000 1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years. Curtiss concludes that the contract does not qualify for revenue…arrow_forwardYellowStone Construction is constructing an office building under contract for LimeStone Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1300000 each quarter. The total contract price is $15600000 and YellowStone estimates total costs of $17500000. YellowStone estimates that the building will take 3 years to complete, and commences construction on January 2, 2021. At December 31, 2022, YellowStone Construction estimates that it is 75% complete with the building; however, the estimate of total costs to be incurred has risen to $17750000 due to unanticipated price increases.YellowStone Construction completes the remaining 25% of the building construction on December 31, 2023, as scheduled. At that time the total costs of construction are $18500000. What is the total amount of Revenue from Long-Term Contracts and Construction Expenses that YellowStone will recognize for the year ended December 31, 2023? Revenue Expenses…arrow_forwardColorado Inc. constructed a factory during 2020 and 2021 under contract with Pacific Machinery Co. Relevant data are summarized below: Contract price Cost Gross profit Contract billings $3,000,000 2020 1,200,000 2021 600,000 2020 800,000 2021 400,000 2020 1,500,000 2021 1,500,000 Colorado Inc. recognizes revenue over time with respect to this contract. In its December 31, 2020, balance sheet, Colorado would report: ● The contract asset, cost and profit in excess of billings, $500,000. The contract liability, billings in excess of cost, of $300,000. The contract asset, contract amount in excess of billings, of $1,500,000. The contract asset, deferred profit, of $400,000.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education
![Text book image](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337272094/9781337272094_smallCoverImage.gif)
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337619202/9781337619202_smallCoverImage.gif)
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
![Text book image](https://www.bartleby.com/isbn_cover_images/9780134475585/9780134475585_smallCoverImage.gif)
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
![Text book image](https://www.bartleby.com/isbn_cover_images/9781259722660/9781259722660_smallCoverImage.gif)
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
![Text book image](https://www.bartleby.com/isbn_cover_images/9781259726705/9781259726705_smallCoverImage.gif)
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education