The Naples Company uses the percentage-of-completion method and the cost-to-cost method for its long-term construction contracts. On one such contract, Naples expects total revenues of P260,000. During the first year, Naples incurred costs pf P50,000 and billed the customer P30,000 under the contract. At what net amount should Naples Construction in Progress for this contract be reported at the end of the first year? a. P 35,000 b. 65,000

Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter17: Advanced Issues In Revenue Recognition
Section: Chapter Questions
Problem 13E: On March 1, 2019, Elkhart enters into a new contract to build a specialized warehouse for 7 million....
icon
Related questions
Question

 

The Naples Company uses the percentage-of-completion method and the cost-to-cost method for its long-term

construction contracts. On one such contract, Naples expects total revenues of P260,000. During the first

year, Naples incurred costs pf P50,000 and billed the customer P30,000 under the contract. At what net amount

should Naples Construction in Progress for this contract be reported at the end of the first year?

a. P 35,000

b. 65,000

 

Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning