An automated machine runs for an 8-hr shift and requires an operator to run it. There are a few planned breakouts such as a 45-minute lunch break and a 10-minute production update break in the morning and a15-minute break during the shift.
There are unplanned breakdown reports that have shown a repeatable average of 50 minutes per shift. The machine requires 25 minutes of tooling changeover and 25 minutes for adjustments to get a good product yield. Idling & minor stoppages account for an average of 10 minutes per shift.
The machine only produces 3% defective product which includes any start-up adjustment losses.
Calculate the Overall Equipment Effectiveness (OEE) for the equipment given the data.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 3 steps with 2 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Design a process for the following activitiy, preparing for an exam.arrow_forwardQ6 need in 10 minutearrow_forwardManagement of Mittel Company would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.7 days Wait time (from order to start of production) 16.9 days Process time 2.7 days Move time 1.0 days Queue time 4.3 days 1. Compute the throughput time. 2. Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your percentage answer to nearest whole percent.) 3. What percentage of the throughput time was spent in non–value-added activities? (Round your percentage answer to nearest whole percent.)arrow_forward
- A production process at Brianna Bryant Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). a) is the bottleneck. 1.8 units/hr Sawing minutes per unit (round your response to two decimal places). 5 units/hr Sanding Drilling 5 units/hr b) The bottleneck time is c) The throughput time of the overall system is minutes (round your response to two decimal places). d) If the firm operates 11 hours per day, 20 days per month, the monthly capacity of the manufacturing process is Welding 2.5 units/hr Assembly 0.8 units/hr Assembly 0.8 units/hr Assembly 0.8 units/hr units (enter your response as a whole number). Qarrow_forwardA production process at Brianna Bryant Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). a) is the bottleneck. 1.8 units/hr Sawing minutes per unit (round your response to two decimal places). 5 units/hr Sanding Drilling 5 units/hr b) The bottleneck time is c) The throughput time of the overall system is minutes (round your response to two decimal places). d) If the firm operates 11 hours per day, 20 days per month, the monthly capacity of the manufacturing process is Welding 2.5 units/hr Assembly 0.8 units/hr Assembly 0.8 units/hr Assembly 0.8 units/hr units (enter your response as a whole number). Qarrow_forwardA production machine is available for 24 hours each day. The machine produces 35 units each day. A unit takes 15 minutes to process. What is the overall equipment effectiveness (OEE) of this machine?arrow_forward
- Describe how THE PROCESS DIAGRAM BELOW they could be improved and make recommendations for their improvement.arrow_forwardThe following table shows the process times in minutes (or minutes/unit - how many minutes to process one unit) of a six-station serial production line (1-2-3-4-5-6). Station 1 2 3 4 5 6 Which station(s) is (are) the bottleneck(s)? Station 2 Station 5 Stations 3 and 4 Stations 2 and 5 Process Time (minutes/unit) 8 11 7 7 11 4arrow_forwardThese four phases make up a machine cycle, which is also known as a process loop. What percentage of a machine's cycle time do you value the most? Should I be concerned about replacing parts of the machine cycle when they wear out? Is the problem of switching modules improved by adding a second module?arrow_forward
- H4. Explain properly and show all calculation stepsarrow_forwardUse MOST to determine the number of TMUs associated with each of the following scenarios: A line supervisor grabs a job order (paper) within reach, walks 10 steps, then lays the order on top of a stack of other orders. The supervisor then returns to her original position. A B G A B P Aarrow_forwardDraw a current state value stream map indicating the customer, supplier, information flow, and relevant metrics. What is the takt time? What is the total lead time (processing+waiting)? What is the total value added and non-value added time? What is the VA/NVA percentage? How can the system be improved and draw a new value stream map?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.