Practical Operations Management
Practical Operations Management
2nd Edition
ISBN: 9781939297136
Author: Simpson
Publisher: HERCHER PUBLISHING,INCORPORATED
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 7, Problem 9P
Summary Introduction

Interpretation: Late start time is to be determined when early start time is 7.

Concept Introduction: Critical path is the arrangement of project activities which gives an estimate time duration under which project will be completed. The project activities may include float activities which can be delayed focusing on the shortest time duration.

PERT diagram is a graphical project management tool used to organize and analyze project and its activity. It defines time duration for a project and also for each activity in a project.

Blurred answer
Students have asked these similar questions
An activity on a PERT network has these time estimates: optimistic = 2, most likely = 3, and pessimistic = 6. What is its expected activity time and variance? 3.67; 1 O 4.33; 1 O 3.33; 0.44 O 4; 0.44
A project consist of 5 activities A,B,C,D,E with ES, EF, LS and LF of A (0, 6, 9, 15); B (0, 7, 0, 7); C (6, 13, 15, 22); D (7, 13, 7, 13); E (13, 22, 13, 22). Normal Time (in month), Crash time (in month), Normal cost (in million Rp), Crash cost (in million Rp) from each activity are A (6, 4, 20, 24); B (7, 5, 30, 35); C (7, 6, 10, 13); D (6, 4, 20, 26); E (9, 8, 88, 90)   a. What activities are in the critical path? How long is the project duration? b. If we want to crash the project for 2 months, what activities need to be crashed? How much additional cost required?
The information in the table below is available for a large fund-raising project. Activity Activity Times (days) Activity Cost ($) Immediate Predecessor A 3 100 None B 4 150 None C 2 125 A D 5 175 B E 2 150 B F 4 200 C, D G 6 75 C H 2 50 C, D, E I 1 100 E J 4 75 D, E K 5 350 F, G L 3 150 G, H, I M 4 400 I, J N 4 175 K, M O 1 200 H, M P 5 150 N, L, O   Draw the precedence network diagram. Perform the CPM (Critical Path Method) and give the complete activity schedule table, the project completion time, and the critical path. Plot on the same graph the total project costs per day, starting from day one to the completion date, assuming the earliest start times and then assuming the latest start times. What implications does the time differential have for cash flows and project scheduling? Show step by step solution
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY