Question
Chapter 7, Problem 2.3Q
Summary Introduction
Case Summary:
A production Company CP has signed an agreement with its client to film a short video of a major sports event that will air throughout the event in the USA. After this, the event will be available on-demand through banner advertisements over the internet. The company planned to treat the contract like a PERT chart and divided the whole task into five categories.
Interpretation:
The probability that the company CP will actually earn the bonus.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Using your results from Problem 6,(a) Calculate the probability that the project will be completedin 38 weeks.(b) Calculate the probability that the project will be completedin 42 weeks
Assume we are planning to develop a room reservation system that is estimated to have 400 story points of features. Let’s say our team’s velocity on two-week sprints ranges between 20 and 25 story points.
Our project will start on Dec 1, 2021. If our customer wants the project to be in production by end of June 22, how likely will the project be successful? Why? Show your calculations.
A company is willing to develop their rocket before the end of current financial
year which is now 28 weeks away. The chief engineer of the company has
decided to use PERT technique in order to plan, schedule and control program
of development for the data given in table below.
What is the probability that the program will be completed by the end of the
current financial year? (all durations are in weeks).
(i) G)
Optimum Duration
Most likely duration
Pesimistic duration
1
2
3
8
13
3
2
8
4
3
8
10
4
7
10
3
6.
3
8
4
9
10
4
8.
4
9.
5
7
9.
12
6.
5
11
7
9.
14
8
4.
00
2.
Chapter 7 Solutions
Practical Operations Management
Ch. 7 - Prob. 1DQCh. 7 - Prob. 2DQCh. 7 - Prob. 3DQCh. 7 - Prob. 4DQCh. 7 - Prob. 5DQCh. 7 - Prob. 6DQCh. 7 - Prob. 1PCh. 7 - Prob. 2PCh. 7 - Prob. 3PCh. 7 - Prob. 4P
Ch. 7 - Prob. 5PCh. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Prob. 9PCh. 7 - Prob. 10PCh. 7 - Prob. 11PCh. 7 - Prob. 12PCh. 7 - Prob. 13PCh. 7 - Prob. 14PCh. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - Prob. 19PCh. 7 - Prob. 20PCh. 7 - Prob. 21PCh. 7 - Prob. 22PCh. 7 - Prob. 23PCh. 7 - Prob. 24PCh. 7 - Prob. 25PCh. 7 - Prob. 26PCh. 7 - Prob. 27PCh. 7 - Prob. 28PCh. 7 - Prob. 29PCh. 7 - Prob. 30PCh. 7 - Prob. 31PCh. 7 - Prob. 32PCh. 7 - Prob. 1.1QCh. 7 - Prob. 1.2QCh. 7 - Prob. 1.3QCh. 7 - Prob. 1.4QCh. 7 - Prob. 2.1QCh. 7 - Prob. 2.2QCh. 7 - Prob. 2.3Q
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A 4-year financial project has net cash flows of $20,000; $25,000; $30,000; and $50,000 in the next 4 years. It will cost $75,000 to implement the project. If the required rate of return is 0.2, conduct a discounted cash flow calculation to determine the NPV.arrow_forward1.) You have determined the following for a given project: Expected completion time of the project = 40 weeks Standard deviation of project completion time = 8 What is the probability of completing the project in more than 44 weeks? answer as a decimal and take it to four places.arrow_forwardThe following represents a project that should be scheduled using CPM: ACTIVITY ABCDEFGH А с IMMEDIATE PREDECESSORS IAABUDR C,D D,E F,G TIMES (DAYS) b a 1 1 3 - NTTTTE 1 1 1 1 2 m 5 WaNNASNU 2 5 4 2 2 6 3 ∞∞NWO3770 9 10 12 8arrow_forward
- A project has the following tasks and duration estimates given. These three tasks are done in succession on a project. Task Optimistic Estimate Most Likely Estimate Pessimistic Estimate Alpha 30 days 40 days 50 days Beta 20 days 25 days 28 days Charlie 4 days 10 days 12 days Delta 25 days 30 days 50 days What is the expected duration for the project? (3 points) What is the variance for the project? (3 points) What is the standard deviation of the project? (3 points) What is the range of the duration of the project given 3 sigma? (3 points)arrow_forwardCreate a risk matrix for this project:Event Cost ($000) ProbabilityEquipment breakdown 40 .20Vendor is late with key segment 200 .60Subcontractor has labor issues 140 .30Weather problems 15 UnknownFunding delays 50 .40 to .60Testing delays 20 .40Explain your reasoning for your placement of the events Weather problems and Funding delays.arrow_forwardThe following information has been computed from a project: Expected total project time = T = 62 weeks Project variance = 81 1- What is the probability that the project will be completed 18 weeks before its expected completion date? 2- Draw Normal Curve & Analysis your solution with conclusionarrow_forward
- The following precedence diagram reflects three time estimates for each activity. Determine: Use Table B1 and Table B2. 9-10-12 3 8 5-7-10 8-10-14 11-12-13 6 11 14-18-26 10.5-13-15.5 10 8-8-8 1 5-6-7 2 4 13-13-13 7 7-10-12 a. The expected completion time for each path and its variance. (Round intermediate calculations to 4 decimal places and final answers to 2 decimal places.) Path Mean Var. Std. Dev. 1-2-3-8-11 37.33 1-2-4-6-11 43.00 5.11 1-2-4-7-11 0.81 1-2-5-9-10-11 46.83 1.25 9-9-9 10-11-12 10-12-14arrow_forwardYour vice president asked you what the Estimate at Completion (EAC) will be for a small project you are working on. You were given a budget of S50,000, and to date you have spent $40,000 but only completed $30,000 worth of work. You are sure the future work will be accomplished at the planned rate. What is the EAC ?arrow_forwardFor this assignment, you will design a risk management plan for a project titled “prolonged waiting times for patients in a large outpatient hospital” that will include the following elements: Risk Register/Matrix (list of at least 5 (five) risks along with the associated impact and probability scores along with risk score) Contingency plan (list of any risks you will plan for in advance along with what triggers the contingency). Be sure to include any information useful to stakeholders on the rationale for the creation of these elements as well as any outside references supporting the risk management plan.arrow_forward
- Problem Statement: Project Control and Monitoring You are working on a manufacturing project having a budget of PKR 3,600,000 and expected time of its completion is one year. There is an ideal condition that your budget and work are evenly spread across the duration of the project that is twelve month. At the end of forth month, the senior management has called a meeting and invited all the stakeholders to brief about the status of the project. You being the PM of this project is giving the presentation to all the attendees and informed that project is on schedule and PKR 1,800,000 have already been spent on the project. Required: Calculate Cost and Schedule Variance What is SPI and CPI of the project? Estimate at completion and Estimated time to complete?arrow_forwardThe decision was made by JMP management that a certain critical development in the overall project will be subcontracted-out to a vendor. JMP has issued a six-month cost plus fixed fee contract for that development, and you are the vendor's project manager. The approved JMP budget for your development is $500,000. A recent Earned Value Analysis that your firm (the vendor) has done shows that you will complete the project four weeks ahead of time, thus depriving your firm of $80,000 of billable time. Among your options are: 1. Since it was the approved budget, go ahead and bill JMP for the entire $500.000. 2. Inform JMP of the project status and completion date, and ask if they'd like to add any features to account for the monies spent. 3. Inform JMP of the project status and completion date. 4. Bill JMP for the $500,000 by adding more work at the end of the project.arrow_forwardSuppose the due date of the project is 24 months and expected time of completion is 28 months, while the probability of completing it is 90%. What will be the standard deviation?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY