Interpretation: Early finish time of Task C is to be determined.
Concept Introduction: Critical path is the arrangement of project activities which gives an estimate time duration under which project will be completed. The project activities may include float activities which can be delayed focusing on the shortest time duration.
PERT diagram is a graphical project management tool used to organize and analyze project and it’s activity. It defines time duration for a project and also for each activity in a project.
Early start time: The rule for early start time of a task is that it is equal to largest early finish time of the task’s immediate predecessors.
Early finish time: The early finish time of a task is addition of both task time and early start time of the task.
Late start time: The late start time of a task can be computed by subtracting task time and late finish time of the project.
Late finish time: The rule for late finish time of a task is that it is equal to the smallest late start time of the task’s immediate follower.
It is given that there are two immediate predecessors for Task C,that is, Task A and Task B. It is given that early finish time of task A is 3 days and task B is 5 days.
Want to see the full answer?
Check out a sample textbook solutionChapter 7 Solutions
Practical Operations Management
- James Lawson has decided to run for a seat as Congressman from the House of Representatives, District 34, in Florida. He views his 8-month campaign for office as a majorproject and wishes to create a work breakdown structure (WBS) to help control the detailed scheduling. So far, he has developed the following pieces of the WBS: Help Lawson by providing details where the blank lines appear. Are there any other major (Jevel-2) activities to create? If so, add an ID no. 1.6 and insert them.arrow_forwardThe Cove at UP is looking to open a new location. Guillermo Santiago has been developing a project plan and has identified the following tasks, precedence relations, and normal task durations. \ tasks predecessors task duration start 0 A start 7 B A 20 C A 34 D B 39 E C,D 6 F D 15 G E,F 33 end G 0 Guillermo has studied project management at the University of Portland and knows that the starting and ending time of any task may be determined from the information in the table using the critical path method. Assume the following notation when answering the questions below: \ Metric Description ES Early start time for task EF Early finsh time for task LS Late start time for task LF Late finsh time for task TS Total slack for task FS Free slack for task IS Independent slack for task SS safety slack for task Please provide the CPM result for each of the following metrics: ES_{end} = LS_{D} = TS_{D} = EF_{G} = LF_{G} =arrow_forwardEd is planning to build a treehouse as a present for his son's upcoming 10th birthday. The details for each task are as follows: DE F G AD C,E F 12 Task A B Preceding Task Duration (day) | 12 A B 10 12 5 Cost (RM) 50 140 120 60 70 80 60 (a) Obtain the following: • The number of days it will take for Ed to finish building the treehouse. • Which tasks are cannot be delayed at all without delaying the whole project. • The total cost of building the treehouse. (b) Due to illness, Ed has to begin building the treehouse later than planned. He reckons that he must reduce the build duration by 3 days to complete the treehouse by his son's birthday. He has determined the crash cost and crash time for each task as follows: Task А В С DE F G Crash Time (day) | 12 8 9 8 10 5 6 Crash Cost (RM) | 50 170 180 70 95 80 60 Obtain the following: • All tasks that are crashed and by how much. • The new total cost for building the treehouse.arrow_forward
- Dayagsky Construction Firm, Inc. will soon begin to work on a building for US tea that was initially started by another firm that has gone out of business. The construction firm’s schedule of activities and related expected completion time for US tea project are presented in the following time table: Activity Code Activity Description Estimated Time (in weeks) A - B Obtain on-site work permits 2 B – E Repair damages done by vandals 8 B – C Inspect construction materials left on site 1 C – E Order and receive construction materials 2 C – D Apply for waiver to…arrow_forwardA Work Breakdown Structure (WBS) identifies deliverables, activities, and tasks. Which statement describes a task?arrow_forwardA project has a budget of $300,000 and is expected to last 10 months, with the work results and budget spread evenly across all months. The project just completed its 3rd month, the work is on schedule, and $65,000 has been spent. What is the cost variance? How efficient (in %) must work progress be to complete on time and within budget?arrow_forward
- The table below contains data for the installation of new equipment in a manufacturing process a Excello Corporation. Your company is responsible for the installation project. Indirect costs are $10,000 per week, and a penalty cost of $9,000 per week will be incurred by your company for every week the project is delayed beyond week12. Activity Immediate Predecessor(s) ABCDEFG long dash- long dash- ABCDEFG A B C D, E E Normal Time Crash Time Normal Cost Crash Cost (weeks) (weeks) ($) ($) 1 14,000 2 3,000 1 40,000 3 22,000 1 8,000 4 13,000 2 16,000 3234 1 6 63 7,000 3,000 12,000 12,000 8,000 5,000 9,000 a. What is the shortest time duration for this project regardless of cost? (Enter your response as a whole number.) b. What is the minimum total cost associated with completing the project in 12 weeks? C. What is the total time of the minimum cost schedule? (enter your response as whole numbers). The total project's duration according to minimum cost schedule is? The minimum cost schedule…arrow_forwardAn activity originally estimated to cost $100,000 and require 30 weeks to complete. Now the activity is on week 10 and $35,000 were spent and is 40% completed. What is the BCWS for this activity?arrow_forwardColonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin. Activity A B C D E F G H IMG_A2D52FAF8F3D-1.jpeg Activity This answer has not been graded yet. A B с (c) Develop the activity schedule for the project. D Survey building site Develop initial design Obtain board approval E F G Description H Select architect Establish budget Finalize design Obtain financing 0 Hire contractor L L | (a) Draw a project network. (Submit a file with a maximum size of 1 MB.) Choose File No file chosen Immediate Predecessor Earliest Start (b) Identify the critical path. (Enter your answers as a comma-separated list.) 4 A, B с Latest Start с D, E E F, G Time (weeks) 5 5 9 Earliest Finish 13 4 7 15 11 6 9 Latest Finish 4 Slack (d) Does it appear…arrow_forward
- A project consist of 5 activities A,B,C,D,E with ES, EF, LS and LF of A (0, 6, 9, 15); B (0, 7, 0, 7); C (6, 13, 15, 22); D (7, 13, 7, 13); E (13, 22, 13, 22). Normal Time (in month), Crash time (in month), Normal cost (in million Rp), Crash cost (in million Rp) from each activity are A (6, 4, 20, 24); B (7, 5, 30, 35); C (7, 6, 10, 13); D (6, 4, 20, 26); E (9, 8, 88, 90) a. What activities are in the critical path? How long is the project duration? b. If we want to crash the project for 2 months, what activities need to be crashed? How much additional cost required?arrow_forwardDraw a A-O-A network diagram for the project having 9 activities with the following inter-relationship. C follows D but precedes F; C follows B but precedes H; G follows F but precedes I; E follows A but precedes I; D follows A; H and I terminate at the same time; A and B start at the same timearrow_forwardA large Southeast city is requesting federal funding for a park-and-ride project. One of the requirements in the request application is a network plan for the design phase of the project. Sophie Kim, the chief engineer, wants you to develop a project network plan to meet this requirement. She has gathered the activity time estimates and their dependencies shown here. ID Description A Survey B Soils report с Traffic design D Lot layout E Approve design F G Drainage H Landscape I Signage J Illumination Bid proposal The project is expected to take The critical path is: Early start for Activity E is: Late finish for Activity F is: Slack for Activity C is: Predecessor None A A A B, C, D E E E E F, G, H, I Time (days) 9 22 25 6 76 20 24 24 25 9 days. day(s).arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.