Practical Operations Management
2nd Edition
ISBN: 9781939297136
Author: Simpson
Publisher: HERCHER PUBLISHING,INCORPORATED
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 7, Problem 8P
Summary Introduction
Interpretation: Technique that better reflects uncertainty in project management is to be stated.
Concept Introduction: Critical path is the arrangement of project activities which gives an estimate time duration under which project will be completed. The project activities may include float activities which can be delayed focusing on the shortest time duration.
PERT diagram is a graphical project management tool used to organize and analyze project and it’s activity. It defines time duration for a project and also for each activity in a project.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Explain the limitations and cons of CPM/PERT?
What roles do the typical process management responsibilities of planning, organising, and regulating play in project administration?
How are the mean activity times and activity variancescomputed in probabilistic CPM/PERT analysis?
Chapter 7 Solutions
Practical Operations Management
Ch. 7 - Prob. 1DQCh. 7 - Prob. 2DQCh. 7 - Prob. 3DQCh. 7 - Prob. 4DQCh. 7 - Prob. 5DQCh. 7 - Prob. 6DQCh. 7 - Prob. 1PCh. 7 - Prob. 2PCh. 7 - Prob. 3PCh. 7 - Prob. 4P
Ch. 7 - Prob. 5PCh. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Prob. 9PCh. 7 - Prob. 10PCh. 7 - Prob. 11PCh. 7 - Prob. 12PCh. 7 - Prob. 13PCh. 7 - Prob. 14PCh. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - Prob. 19PCh. 7 - Prob. 20PCh. 7 - Prob. 21PCh. 7 - Prob. 22PCh. 7 - Prob. 23PCh. 7 - Prob. 24PCh. 7 - Prob. 25PCh. 7 - Prob. 26PCh. 7 - Prob. 27PCh. 7 - Prob. 28PCh. 7 - Prob. 29PCh. 7 - Prob. 30PCh. 7 - Prob. 31PCh. 7 - Prob. 32PCh. 7 - Prob. 1.1QCh. 7 - Prob. 1.2QCh. 7 - Prob. 1.3QCh. 7 - Prob. 1.4QCh. 7 - Prob. 2.1QCh. 7 - Prob. 2.2QCh. 7 - Prob. 2.3Q
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Project B is the development of a facility in a remote area, of about GHS 5 million in value, of approximately 18 months’ planned duration. It is 30 per cent completed. Earned Value analysis shows that the project is not achieving its planned cost or progress targets. The project is also not achieving quality requirements. Some of the specialized components used for this project are only oSbtainable from overseas suppliers and are difficult to transport over the rough terrain near the project site. There has been a delay on ordering these components. The transportation of these components, which must be booked several months ahead, has not been arranged, and there is also difficulty with obtaining tradespeople with the requisite set of skills to install them. There are also several other risks associated with this project, including a quite basic business case, rudimentary project charter, poor definition of expected project outcomes, exchange rate risks and the potential for…arrow_forwardHow do PERT and CPM differ from each other?arrow_forwardProject B is the development of a facility in a remote area, of about GHS 5 million in value, of approximately 18 months’ planned duration. It is 30 per cent completed. Earned Value analysis shows that the project is not achieving its planned cost or progress targets. The project is also not achieving quality requirements. Some of the specialized components used for this project are only obtainable from overseas suppliers and are difficult to transport over the rough terrain near the project site. There has been a delay on ordering these components. The transportation of these components, which must be booked several months ahead, has not been arranged, and there is also difficulty with obtaining tradespeople with the requisite set of skills to install them. There are also several other risks associated with this project, including a quite basic business case, rudimentary project charter, poor definition of expected project outcomes, exchange rate risks and the potential for…arrow_forward
- How can a business analyst communicate requirements (and associated models) for a project in project management.arrow_forwardBased on the Project Oxygen at Google: What are limits/ dangers of implementing project oxygen widely at Google?arrow_forwardList two outputs for each of the Project Risk Management processes (note that the Implement Risk Responses process is not discussed in this chapter)arrow_forward
- What are the primary components of process planning in project management, and how do they contribute to the successful execution of a project?arrow_forwardProvide examples of IT project ROM, budgeted, and final cost estimates.arrow_forward8 EARNED VALUE ANALYSIS The following project is reported to be at the end of its 8 week. Find the cost and schedule variances. Also find the CPI, SPI, CSI, ETC and EAC for the project. Find the condition of the project at the this reporting period. PV AC Budget ($) Duration Actual Cost % D-8 Activity Predecessor (s) (week) ($) Complete 300 400 A 3 100 A3 В 4 200 180 100 B:4 C 7 250 300 90 A 8 600 400 50 400 200 В 40 150 180 F В 4 100 G C 4 100 200 40 500 H D, E 2 300 F, G 3 J H, I 1 100 ㅇ CO 프 (-)arrow_forward
- Define Time–Cost Models and Project Crashing?arrow_forwardRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) A BCDEFG с This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are c) The project length for the leadership training program development project = d) Slack time for each of the activities is: days. Activity A B C ס ח ד 0 F B A, D C E, F G Slack Time Time (days) 4 6 1 103510arrow_forwardFarihah is a project manager for a systems development project involving a new database application for her organization’s human resources department. Despite Farihah’s best efforts at estimating the time requirements for the project, the team has missed the deadline for completing the Analysis Phase and producing the System Proposal. Farihah had estimated during her 6-week Planning Phase that Analysis would require 2 months, but the team finished the System Proposal 2 weeks behind their planned target date. Based on her discussions with the team members, Farihah believes that the system is more complex than she originally thought. Should Farihah adjust her timeline, or can she try to make up for the lost two weeks? Farihah needs your advice.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY