Question
Chapter 7, Problem 5P
Summary Introduction
Interpretation: Type of probability distribution with which path lengths through a network can be modeled is to be determined.
Introduction:
PERT diagram is a graphical project management tool used to organize and analyze project and it’s activity. It defines time duration for a project and also for each activity in a project.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
(b) Identify all of the paths on the network diagram and note how long they are, using Figure 6- 8 as a guide for how to represent each path. Be sure to round up the duration for all activities.
What is the answer in the shortest path and shortest duration?
What is the difference between an activity-on-arrow (AOA)network and an activity-on-node (AON) network? Which isprimarily used in this chapter?
Chapter 7 Solutions
Practical Operations Management
Ch. 7 - Prob. 1DQCh. 7 - Prob. 2DQCh. 7 - Prob. 3DQCh. 7 - Prob. 4DQCh. 7 - Prob. 5DQCh. 7 - Prob. 6DQCh. 7 - Prob. 1PCh. 7 - Prob. 2PCh. 7 - Prob. 3PCh. 7 - Prob. 4P
Ch. 7 - Prob. 5PCh. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Prob. 9PCh. 7 - Prob. 10PCh. 7 - Prob. 11PCh. 7 - Prob. 12PCh. 7 - Prob. 13PCh. 7 - Prob. 14PCh. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - Prob. 19PCh. 7 - Prob. 20PCh. 7 - Prob. 21PCh. 7 - Prob. 22PCh. 7 - Prob. 23PCh. 7 - Prob. 24PCh. 7 - Prob. 25PCh. 7 - Prob. 26PCh. 7 - Prob. 27PCh. 7 - Prob. 28PCh. 7 - Prob. 29PCh. 7 - Prob. 30PCh. 7 - Prob. 31PCh. 7 - Prob. 32PCh. 7 - Prob. 1.1QCh. 7 - Prob. 1.2QCh. 7 - Prob. 1.3QCh. 7 - Prob. 1.4QCh. 7 - Prob. 2.1QCh. 7 - Prob. 2.2QCh. 7 - Prob. 2.3Q
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The Mobicom Corporation is in the design phase of a system project. The project manager wants to develop a network analysis diagram to plan the activities of designing the system outputs. The activities are as follows. ACTIVITY PRECEDING TIME[WEEKS] A ----- 5 B ---- 6 C ---- 4 D A,B 7 E C 8 F C,D 10 G D 8 Required Draw a network diagram for the design phasearrow_forwardThe Student Affairs Department at UCC has developed a sequence of activities for the University’s Sports Day. The Director has published the activities as shown in the table. All students are expected to participate and all activities are expected to be completed. The activities and immediate predecessors appear in the following table. Develop a network for this problem. ACTIVITY IMMEDIATE PREDECESSOR A -- B -- C -- D B E A, D F C G E, F Copy the following table in your answer booklet. Determine the values for the gray spaces hence complete the copied table. Activity Completion Times Early Start Early Finish Late Start Late Finish Slack On Critical Path A 2 B 5 C 1 D 3 E 2 F 6 G 8 CRITICAL…arrow_forwardActivities A, B, C, and D are on the critical path of the network diagram below: The cost and duration of performing these activities is: Task A: $2,500 in 4 days Task B: $5,000 in 3 days Task C: $10,000 in 6 days Task D: $8,000 in 8 days At the end of day 10, tasks A and B are complete and task C is 25% complete. The amount spent thus far is $11,000. Given this information, how will you summarize the status of the project? Ahead of schedule, over budget Ahead of schedule, under budget Behind schedule, under budget Behind schedule, over budgetarrow_forward
- What is the difference between an activity-on-arrow(AOA) network and an activity-on-node (AON) network?arrow_forwardIn making a forward pass through a network, three activities are immediate predecessors for activity T and one following activity. What is the late start time for activity T? Group of answer choices: - the LS of the following activity plus the activity time of T - the smallest EF for the three activities that are immediate predecessors for activity T - the LF of the following activity minus the activity time of T - the LS of the following activity minus the activity time of T - the largest EF for the three activities that are immediate predecessors for activity Tarrow_forwardThe project duration in a network model can be determined by the largest value of which variable associated with the critical path?arrow_forward
- The table below represents a IS project set of activities, its expected completion time (weeks) and preceding activities. Activity Expected Time (weeks) Preceding activities A 5 None B 4 None C 10 A D 8 B E 14 B F 6 C, D G 7 D, E, F H 3 F, G Draw a network diagram for the IS project shown above. For each activity, calculate its earliest completion time (TE) and latest completion time (TL). Label TE and TL on the network diagram. Calculate the slack time for each activity.arrow_forwardConsider the project given on the table, construct a network diagramarrow_forwardImagine the benefits of route planning with in-car navigation. Consider the downsides. Consider all the worst-case scenarios to prepare.arrow_forward
- Find the following: 1- The optimum period and the corresponding time 2- The network plan detailed in the table below, noting that the additional cost is $ 1500 per week Activity Normal duration Normal cost Crash duration Crash cost weeks 2$ 2000 weeks 2$ 1-2 11 9. 10000 1-3 17 3000 14 12000 2-3 8. 6. 3600 6. 6000 3-4 6000 4 11000arrow_forwardWhat's the best way to resolve this problem? Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are given in the following table: Activity a m b Immediate Predecessor(s) Activity a m b Immediate Predecessor(s) A 3 5 9 - G 1 2 3 A, E B 4 5 6 - H 4 6 8 F C 1 2 3 - I 10 11 12 G D 7 8 9 C J 15 17 19 C E 1 3 5 B, D K 4 8 12 H, I F 5 10 15 A, E b) Activities on the critical path for the project are C - D - E - F - H - K c) For the given project, the earliest start (ES) and earliest finish (EF) are: For the given project, the latest start (LS) and latest finish (LF) are: (Round your responses to two decimal places.) Referring to the…arrow_forwardRoss Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Activity A B E F a Time (weeks) 4 2 8 5 1 6 m 9 9 12 6 3 9 b 12 24 18 9 4 21 Immediate Predecessor(s) A A A B C, E Activity G H I J K a 3 1 7 4 1 Time (weeks) a) The expected (estimated) time for activity C is h) The unrinnan for nativitu Cin Mwenke (Daund voir mananan to tun desimal almann I m 3 1 7 8 1 b 5 1 7 12 4 weeks. (Round your response to two decimal places.) Immediate Predecessor(s) C, E F D F D, G, H I, Jarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY