Chapter 9, Problem 5.1GAP
To determine
Concept introduction:
Direct material variances:
Direct material variances refer to the difference between the standard direct material cost and actual direct material cost incurred. Direct material cost variances are categorized into following two categories:
- Direct material Rate variance: this variance shows the difference of standard rate and actual rate of material. The formula to calculate this variance is as follows:
- Direct material usage variance: this variance shows the difference of standard usage and actual usage of material. The formula to calculate this variance is as follows:
- Direct material cost or spending variance: this variance shows the difference of
standard cost and actual cost of material. The formula to calculate this variance is as follows:
To calculate:
Direct Material Price, Quantity, and Spending variances.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Pickul Awning manufactures awnings and uses a standard cost system. The company allocates overhead based on the number of direct labor hours. The following are the
company's cost and standards data:
(Click the icon to view the standards.)
Requirement 1. Calculate the standard cost of one awning.
Standard cost
Direct materials
Direct labor
Variable MOH
Fixed MOH
Total standard cost
Standard cost per unit
Requirement 2a. Calculate the direct material variances. (Enter the variances as positive numbers. Enter currency amounts to the nearest cent and your answers to the nearest whole dollar. Label the variance as fa
First determine the formula for the price variance, then compute the price variance for direct materials.
Determine the formula for the quantity variance, then compute the quantity variance for direct materials.
= DM price variance
) =
First determine the formula for the efficiency variance, then compute the efficiency variance for direct labor.
x(
x(
x (
x(
= DM quantity…
Inputs
Direct materials
Direct labor
Variable manufacturing overhead
Actual output
Raw materials purchased
Actual cost of raw materials purchased
Raw materials used in production
Actual direct labor-hours
Actual direct labor cost
Actual variable overhead cost
The company has reported the following actual results for the product for September:
Standard Quantity or
Hours per Unit of
Output
Required:
a. Compute the materials price variance for Septer
b. Compute the materials quantity variance for September.
c. Compute the labor rate variance for September.
a. Materials price variance
b. Materials quantity variance
Labor rate variance
Labor efficiency variance
variable overhead spending variance
Variable overhead efficiency variance
C.
d.
9.40 liters
0.60 hours
0.60 hours
11,600 units
110,000 liters
$1,010,500
$
$
e.
f.
d. Compute the labor efficiency variance for September.
e. Compute the variable overhead spending variance for September.
109,070 liters
6,380 hours
f. Compute the variable…
Ehrlich Inc. makes a product with the following standard costs for direct
material and direct labor:
Quantity/Hours
Price /Rate
Per Unit
Direct Material
6.00 lbs
$ 3.80
Direct Labor
1.5 hrs
$ 16.00
During the most recent month, 6,300 units were produced. The costs associated
with the month's production of this product were as follows:
Quantity/Hours
Price /Rate
Materials purchased
42,000 lbs
$3.00/per lbs.
Materials used in production
32,000 lbs
Direct labor
9,950 hrs
$14.50/per hr.
Chapter 9 Solutions
Managerial Accounting
Ch. 9 - Briefly describe the difference between budgetary...Ch. 9 - What are standard costs? When are they set?Ch. 9 - Prob. 3QCh. 9 - Prob. 4QCh. 9 - Prob. 5QCh. 9 - Prob. 6QCh. 9 - Prob. 7QCh. 9 - Prob. 8QCh. 9 - Prob. 9QCh. 9 - How do the master budget, flexible budget, and...
Ch. 9 - Prob. 11QCh. 9 - What type of variance is calculated by comparing...Ch. 9 - Prob. 13QCh. 9 - Prob. 14QCh. 9 - Prob. 15QCh. 9 - Prob. 16QCh. 9 - Prob. 17QCh. 9 - Prob. 18QCh. 9 - What are the two variable overhead variances? What...Ch. 9 - Prob. 20QCh. 9 - Prob. 21QCh. 9 - Prob. 22QCh. 9 - Prob. 23QCh. 9 - Prob. 1MCCh. 9 - Prob. 2MCCh. 9 - Variances are always noted as favorable or...Ch. 9 - What type of budget is ail integrated set of...Ch. 9 - Prob. 5MCCh. 9 - Prob. 6MCCh. 9 - Prob. 7MCCh. 9 - Prob. 8MCCh. 9 - Prob. 9MCCh. 9 - Prob. 10MCCh. 9 - Prob. 1MECh. 9 - Creating Grading Scale Based on Ideal, Tight but...Ch. 9 - Prob. 3MECh. 9 - Prob. 4MECh. 9 - Calculating Unknown Values for Direct Labor...Ch. 9 - Prob. 6MECh. 9 - Prob. 7MECh. 9 - Prob. 8MECh. 9 - Prob. 9MECh. 9 - Prob. 10MECh. 9 - Prob. 11MECh. 9 - Prob. 12MECh. 9 - Preparing Journal Entries to Record Direct Labor...Ch. 9 - Prob. 1ECh. 9 - Prob. 2ECh. 9 - Interpreting Direct Materials Price, Quantity...Ch. 9 - Calculating Direct Materials and Direct Labor...Ch. 9 - Calculating Direct Materials and Direct Labor...Ch. 9 - Prob. 6ECh. 9 - Prob. 7ECh. 9 - Prob. 8ECh. 9 - Prob. 9ECh. 9 - Preparing Journal Entries to Record Direct...Ch. 9 - Prob. 11ECh. 9 - Calculating Fixed Manufacturing Overhead Spending,...Ch. 9 - Prob. 13ECh. 9 - Prob. 14ECh. 9 - Prob. 15ECh. 9 - Prob. 16ECh. 9 - Prob. 17ECh. 9 - Determining Actual, Standard Costs, and Variances...Ch. 9 - Prob. 1.1GAPCh. 9 - Prob. 1.2GAPCh. 9 - Prob. 1.3GAPCh. 9 - Prob. 2.1GAPCh. 9 - Prob. 2.2GAPCh. 9 - Prob. 2.3GAPCh. 9 - Prob. 3.1GAPCh. 9 - Prob. 3.2GAPCh. 9 - Prob. 3.3GAPCh. 9 - Prob. 4GAPCh. 9 - Prob. 5.1GAPCh. 9 - Prob. 5.2GAPCh. 9 - Prob. 5.3GAPCh. 9 - Prob. 6.1GAPCh. 9 - Prob. 6.2GAPCh. 9 - Prob. 6.3GAPCh. 9 - Prob. 7.1GAPCh. 9 - Prob. 7.2GAPCh. 9 - Prob. 7.3GAPCh. 9 - Preparing Journal Entries to Record Fixed...Ch. 9 - Prob. 9.1GAPCh. 9 - Prob. 9.2GAPCh. 9 - Prob. 10.1GAPCh. 9 - Prob. 10.2GAPCh. 9 - Prob. 1.1GBPCh. 9 - Prob. 1.2GBPCh. 9 - Prob. 1.3GBPCh. 9 - Prob. 2.1GBPCh. 9 - Prob. 2.2GBPCh. 9 - Prob. 2.3GBPCh. 9 - Prob. 3.1GBPCh. 9 - Prob. 3.2GBPCh. 9 - Prob. 3.3GBPCh. 9 - Prob. 4GBPCh. 9 - Prob. 5.1GBPCh. 9 - Prob. 5.2GBPCh. 9 - Prob. 5.3GBPCh. 9 - Prob. 6.1GBPCh. 9 - Prob. 6.2GBPCh. 9 - Prob. 6.3GBPCh. 9 - Prob. 7.1GBPCh. 9 - Prob. 7.2GBPCh. 9 - Prob. 7.3GBPCh. 9 - Prob. 8GBPCh. 9 - Prob. 9.1GBPCh. 9 - Prob. 9.2GBPCh. 9 - Calculating Variable Manufacturing Overhead, Fixed...Ch. 9 - Prob. 9.4GBPCh. 9 - Prob. 9.5GBPCh. 9 - Prob. 9.6GBPCh. 9 - Prob. 10.1GBPCh. 9 - Prob. 10.2GBP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Delano Company uses two types of direct labor for the manufacturing of its products: fabricating and assembly. Delano has developed the following standard mix for direct labor, where output is measured in number of circuit boards. During the second week in April, Delano produced the following results: Required: 1. Calculate the yield ratio. 2. Calculate the standard cost per unit of the yield. 3. Calculate the direct labor yield variance. 4. Calculate the direct labor mix variance.arrow_forwardMaking journal entries Assume that during the month of April the production report of Algonquin Adhesives Inc. in E8-10 revealed the following information: Make journal entries to charge materials (use the materials purchase price variance) and labor to Work in Process. (Remember to retrieve the standard costs from E8-10 before solving this exercise.)arrow_forwardMulliner Company showed the following information for the year: Required: 1. Calculate the standard direct labor hours for actual production. 2. Calculate the applied variable overhead. 3. Calculate the total variable overhead variance.arrow_forward
- Rath Company showed the following information for the year: Required: 1. Calculate the standard direct labor hours for actual production. 2. Calculate the applied variable overhead. 3. Calculate the total variable overhead variance.arrow_forwardKamen Manufacturing Co. estimates the following labor and overhead costs for the period: Required: Use the four-variance method for overhead analysis. Calculate the variances for direct labor and overhead. Prove that the overhead variances equal over- or underapplied factory overhead for the period.arrow_forwardStandard direct materials cost per unit from variance data The following data relating to direct materials cost for October of the current year are taken from the records of Good Clean Fun Inc., a manufacturer of organic toys: Determine the standard direct materials cost per unit of finished product, assuming that there was no inventory of work in process at either the beginning or the end of the month.arrow_forward
- Direct materials, direct labor, and factory overhead cost variance analysis Mackinaw Inc. processes a base chemical into plastic. Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 40,000 units of product were as follows: Each unit requires 0.3 hour of direct labor. Instructions Determine (A) the direct materials price variance, direct materials quantity variance, and total direct materials cost variance; (B) the direct labor rate variance, direct labor time variance, and total direct labor cost variance; and (C) the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance.arrow_forwardCost and production data for Binghamton Beverages Inc. are presented as follows: Required: Calculate net variances for materials, labor, and factory overhead. Calculate specific materials and labor variances by department, using the diagram format in Figure 8-4. Comment on the possible causes for each of the variances that you computed. Make all journal entries to record production costs in Work in Process and Finished Goods. Determine the balance of ending Work in Process in each department. Assume that 4,000 units were sold at $40 each. Calculate the gross margin based on standard cost. Calculate the gross margin based on actual cost. Why does the gross margin at actual cost differ from the gross margin at standard cost. As the plant controller, you present the variance report in Item 1 above to Paul Crooke, the plant manager. After reading it, Paul states: “If we present this performance report to corporate with that large unfavorable labor variance in Blending, nobody in the plant will receive a bonus. Those standard hours of 5,500 are way too tight for this production process. Fifty-eight hundred hours would be more reasonable, and that would result in a favorable labor efficiency variance that would more than offset the unfavorable labor rate variance. Please redo the variance calculations using 5,800 hours as the standard.” You object, but Paul ends the conversation with, “That is an order.” What standards of ethical professional practice would be violated if you adhered to Paul’s order? How would you attempt to resolve this ethical conflict?arrow_forwardApplying Overhead in a Standard Costing System Privack Corporation has a standard cost system in which it applies overhead to products base the standard direct labor-hours allowed for the actual output of the period. Data concerning most recent year appear below: Required: 1. Compute the predetermined overhead rate for the year. Be sure to include the total budget fixed overhead and the total budgeted variable overhead in the numerator of your rate. 2. Compute the amount of overhead that would be applied to the output of the period.arrow_forward
- Predetermined Overhead Rates, Overhead Variances, Unit Costs Primera Company produces two products and uses a predetermined overhead rate to apply overhead. Primera currently applies overhead using a plantwide rate based on direct labor hours. Consideration is being given to the use of departmental overhead rates where overhead would be applied on the basis of direct labor hours in Department 1 and on the basis of machine hours in Department 2. At the beginning of the year, the following estimates are provided: Department 1 Department 2 Direct labor hours 640,000 128,000 Machine hours 16,000 192,000 Overhead cost $384,000 $1,152,000 Actual results reported by department and product during the year are as follows: Department 1 Department 2 Direct labor hours 627,200 134,400 Machine hours 17,600 204,800 Overhead cost $400,000 $1,232,000 Product 1 Product 2…arrow_forwardPredetermined Overhead Rates, Overhead Variances, Unit Costs Primera Company produces two products and uses a predetermined overhead rate to apply overhead. Primera currently applies overhead using a plantwide rate based on direct labor hours. Consideration is being given to the use of departmental overhead rates where overhead would be applied on the basis of direct labor hours in Department 1 and on the basis of machine hours in Department 2. At the beginning of the year, the following estimates are provided: Department 1 Department 2 Direct labor hours 640,000 128,000 Machine hours 16,000 192,000 Overhead cost $384,000 $1,152,000 Actual results reported by department and product during the year are as follows: Department 1 Department 2 Direct labor hours 627,200 134,400 Machine hours 17,600 204,800 Overhead cost $400,000 $1,232,000 Product 1 Product 2…arrow_forwardRequired Information [The following information applies to the questions displayed below.] The Platter Valley factory of Bybee Industries manufactures field boots. The cost of each boot includes direct materials, direct labor, and manufacturing (factory) overhead. The firm traces all direct costs to products, and it assigns overhead cost to products based on direct labor hours. Required: 1. Compute the factory overhead flexible-budget varlance, the factory overhead spending varlance, and the efficiency variance for variable factory overhead for March and state whether each variance is favorable (F) or unfavorable (U). 2. Provide the appropriate journal entry to record the variable overhead spending variance and a second entry to record the variable overhead efficiency variance for March. Assume that the company uses a single account, Factory Overhead, to record overhead costs. No The company budgeted $11,925 variable factory overhead cost, $96,750 for fixed factory overhead cost and…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningManagerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningExcel Applications for Accounting PrinciplesAccountingISBN:9781111581565Author:Gaylord N. SmithPublisher:Cengage Learning
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,Principles of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Excel Applications for Accounting Principles
Accounting
ISBN:9781111581565
Author:Gaylord N. Smith
Publisher:Cengage Learning
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Principles of Cost Accounting
Accounting
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Cengage Learning
What is variance analysis?; Author: Corporate finance institute;https://www.youtube.com/watch?v=SMTa1lZu7Qw;License: Standard YouTube License, CC-BY