Essentials of Systems Analysis and Design (6th Edition)
Essentials of Systems Analysis and Design (6th Edition)
6th Edition
ISBN: 9780133546231
Author: Joseph Valacich, Joey George
Publisher: PEARSON
bartleby

Concept explainers

Question
Book Icon
Chapter 4, Problem 17PE
Program Plan Intro

Economic feasibility analysis of an information system:

Monetary benefits of an information system = $85,000 per year.

One-time costs = $75,000

Recurring cost = $35,000 per year.

Discount rate = 12%

Time period = 5 years

Explanation of Solution

Overall Return on Investment (ROI):

Overall return on investment can be calculated as:

Overall ROI = (Overall NPV / NPV of all costs)

Overall NPV = (NPV of all benefits – NPV of all costs)                     &#

Explanation of Solution

Break-Even Analysis (BEA):

  • Break even analysis is carried out by determining NPV of yearly cash flows.
  • The yearly cash flows are calculated by subtracting present values of recurring costs from the present value of yearly benefits.
  • The overall NPV cash flow is total cash flow of the preceding years.
  • After determining NPV yearly cash flows, it is found that break even occurs between year one and two.
  • This is because year two is the very first year where overall NPV is positive...

Blurred answer
Students have asked these similar questions
You have been made project coordinator for an upcoming tourism workshop to be held in the island of Anguilla. Local, regional and international participants will be in attendance. You have invited 25 participants and 12 presenters as part of your planning. In addition, there are several other tasks to be performed: i. Letters of invitation are to be sent with relevant information. ii. Overall estimates for workshop funding need to be calculated. iii. During the workshop, all attendees and equipment requests will be documented for reporting purposes and also to be used for future analysis when compared with other possible workshops. iv. Final reports will be written to document those persons who attended the workshop as well as to compare the pre- and post-funding estimates. v. Extra expenses incurred at the workshop are also to be noted. vi. A brief presentation highlighting various aspects of Anguilla’s culture and island is to be made to all participants at the beginning of the…
Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $23,000 EV = $20,000 AC = $25,000 BAC = $120,000 What is the cost variance, schedule variance, cost performance index (CPI), and scheduleperformance index (SPI) for the project? How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned? Use the schedule performance index (SPI) to estimate how long it will take to finish this project. Sketch the earned value chart based for this project, using Figure 7-5 as a guide.
Identify a suitable iterative methodology for the scenario given below and justify your choice. Critically evaluate the different stages of the iterative methodology chosen by mapping on to the given scenario. Identify, explain and draw the main use cases of the scenario. Assume that you are working as a project manager in a reputed organization and you have been assigned with a new project to develop a suitable system for the following scenario.    A leading job recruitment and training institution in Oman would like to develop a system to manage all their functional requirements like upload the current job requirements as well the courses they have offered. The website can be used by the job seekers as well as for trainees to take up a training on any course they are offering.  The system should have the features for the clients to Sign in, register, Upload CV, apply for an existing job. The website should also show all the information about a course such as course name, duration,…
Knowledge Booster
Background pattern image
Computer Science
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Text book image
Database Systems: Design, Implementation, & Manag...
Computer Science
ISBN:9781285196145
Author:Steven, Steven Morris, Carlos Coronel, Carlos, Coronel, Carlos; Morris, Carlos Coronel and Steven Morris, Carlos Coronel; Steven Morris, Steven Morris; Carlos Coronel
Publisher:Cengage Learning
Text book image
Database Systems: Design, Implementation, & Manag...
Computer Science
ISBN:9781305627482
Author:Carlos Coronel, Steven Morris
Publisher:Cengage Learning