Essentials of Systems Analysis and Design (6th Edition)
6th Edition
ISBN: 9780133546231
Author: Joseph Valacich, Joey George
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 4, Problem 17PE
Program Plan Intro
Economic feasibility analysis of an
Monetary benefits of an information system = $85,000 per year.
One-time costs = $75,000
Recurring cost = $35,000 per year.
Discount rate = 12%
Time period = 5 years
Explanation of Solution
Overall Return on Investment (ROI):
Overall return on investment can be calculated as:
Explanation of Solution
Break-Even Analysis (BEA):
- Break even analysis is carried out by determining NPV of yearly cash flows.
- The yearly cash flows are calculated by subtracting present values of recurring costs from the present value of yearly benefits.
- The overall NPV cash flow is total cash flow of the preceding years.
- After determining NPV yearly cash flows, it is found that break even occurs between year one and two.
- This is because year two is the very first year where overall NPV is positive...
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
You have been made project coordinator for an upcoming tourism workshop to be held in the island of Anguilla. Local, regional and international participants will be in attendance. You have invited 25 participants and 12 presenters as part of your planning. In addition, there are several other tasks to be performed: i. Letters of invitation are to be sent with relevant information. ii. Overall estimates for workshop funding need to be calculated. iii. During the workshop, all attendees and equipment requests will be documented for reporting purposes and also to be used for future analysis when compared with other possible workshops. iv. Final reports will be written to document those persons who attended the workshop as well as to compare the pre- and post-funding estimates. v. Extra expenses incurred at the workshop are also to be noted. vi. A brief presentation highlighting various aspects of Anguilla’s culture and island is to be made to all participants at the beginning of the…
Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion.
PV = $23,000
EV = $20,000
AC = $25,000
BAC = $120,000
What is the cost variance, schedule variance, cost performance index (CPI), and scheduleperformance index (SPI) for the project?
How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?
Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?
Use the schedule performance index (SPI) to estimate how long it will take to finish this project.
Sketch the earned value chart based for this project, using Figure 7-5 as a guide.
Identify a suitable iterative methodology for the scenario given below and justify your choice. Critically evaluate the different stages of the iterative methodology chosen by mapping on to the given scenario. Identify, explain and draw the main use cases of the scenario.
Assume that you are working as a project manager in a reputed organization and you have been assigned with a new project to develop a suitable system for the following scenario.
A leading job recruitment and training institution in Oman would like to develop a system to manage all their functional requirements like upload the current job requirements as well the courses they have offered. The website can be used by the job seekers as well as for trainees to take up a training on any course they are offering. The system should have the features for the clients to Sign in, register, Upload CV, apply for an existing job. The website should also show all the information about a course such as course name, duration,…
Chapter 4 Solutions
Essentials of Systems Analysis and Design (6th Edition)
Ch. 4 - Prob. 1MCh. 4 - Prob. 2MCh. 4 - Prob. 3MCh. 4 - Prob. 4MCh. 4 - Prob. 5MCh. 4 - Prob. 6MCh. 4 - Prob. 7MCh. 4 - Prob. 8MCh. 4 - Prob. 9MCh. 4 - Prob. 10M
Ch. 4 - Prob. 11MCh. 4 - Prob. 12MCh. 4 - Prob. 13MCh. 4 - Prob. 14MCh. 4 - Prob. 15MCh. 4 - Prob. 16MCh. 4 - Prob. 17MCh. 4 - Prob. 18MCh. 4 - Prob. 19MCh. 4 - Prob. 20MCh. 4 - Prob. 21MCh. 4 - Prob. 22MCh. 4 - Prob. 1RQCh. 4 - Describe several project evaluation criteria.Ch. 4 - Prob. 3RQCh. 4 - Prob. 4RQCh. 4 - Prob. 5RQCh. 4 - Prob. 6RQCh. 4 - What are the potential consequences of not...Ch. 4 - Prob. 8RQCh. 4 - Prob. 9RQCh. 4 - Prob. 10RQCh. 4 - Prob. 11RQCh. 4 - Prob. 12PECh. 4 - Prob. 13PECh. 4 - Prob. 14PECh. 4 - Prob. 15PECh. 4 - Prob. 16PECh. 4 - Prob. 17PECh. 4 - Prob. 18PECh. 4 - Prob. 19PECh. 4 - Prob. 20PECh. 4 - Prob. 21PECh. 4 - Assume monetary benefits of an information system...Ch. 4 - Prob. 23PECh. 4 - Prob. 24PECh. 4 - Prob. 25PECh. 4 - Prob. 26PECh. 4 - Prob. 27PECh. 4 - Prob. 28PECh. 4 - Prob. 29DQCh. 4 - Prob. 30DQCh. 4 - Prob. 31DQCh. 4 - Prob. 32DQCh. 4 - Prob. 33CPCh. 4 - Prob. 34CPCh. 4 - Prob. 35CPCh. 4 - Prob. 36CQCh. 4 - Prob. 37CQCh. 4 - Identify a preliminary set of tangible and...Ch. 4 - Prob. 39CQCh. 4 - If you were assigned to help Jim with this...Ch. 4 - Prob. 41CQCh. 4 - Prob. 42CQCh. 4 - In Question 4, you analyzed the risks associated...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.Similar questions
- university in the process to develop a new attendance system for the students. (a) State an established methodology to ensure the project is successful. (b) Name THREE (3) major stakeholders for the project. (c) Apply the methodology in Q5 (a) for the project and discuss ALL the steps needed, each with specific action.arrow_forwardA Hospital Management System Development Project has a budgeted cost of Rs. 22,700,000/-. The project is to be completed in 11 months. After 4 months, you have completed 24 percent of the project at a total expense of Rs. 2,925,000/-. You, as a Project Manager, needs to submit the monthly performance report to the Steering Committee. Based on EVM methodology, please identify the current progress of the Project. Find Budget at Completion (BAC), Actual Cost(AC), Planned Value (PV) and Earned Value (EV). Calculate the Project Health by finding values of Schedule Variance (SV), Schedule Performance Index (SPI), Cost Variance (CV) and Cost Performance Index (CPI). What these value shows? If the project continues at the current pace, what will be the true cost of the Project or Estimate at completion of the project. What actions, you would suggest or take as a Project Manager, to keep the budget and time under control.arrow_forwardCompute the FP value for the grade calculation of students. Assume that it is an average complexity size project. The information domain values are as follows: number of inputs = 13, number of outputs = 4, number of inquiries = 2, number of external files = 5, number of interfaces 2. The total value of complexity adjustment %3D attributes is 13. CS Seanned with CamScannerarrow_forward
- A government project for tourism enhancement has initiated by the government. The project will itself carried out for 1 year. Meanwhile they need to add a web based information system(WBIS) which should also be fully functional after one year. The requirements are yet not finalized for the WBIS but a core set of almost 100 requirements are available with the project organizers. The detailed requirements can be finalized with the time period of one year. What type of process model can be used by you for this project. Write detail of phases as well as artifacts, deliverable and milestones for each phasearrow_forwardThe nominal effort and duration of a large size project have been estimated to be 10000 PM and 2 Years. The project cost has been negotiated to be Rs. 500,000,000. The product need to be developed in and delivered in 1 year and 5 months. What should be the new cost to be negotiated?Justify whether the proposed reduction in duration of the project development is possible or not.arrow_forwardYou have been made project coordinator for an upcoming tourism workshop to be held in the island of Anguilla. Local, regional and international participants will be in attendance. You have invited 25 participants and 12 presenters as part of your planning. In addition, there are several other tasks to be performed: Letters of invitation are to be sent with relevant information. Overall estimates for workshop funding need to be calculated. iii. During the workshop, all attendees and equipment requests will be documented for reporting purposes and also to be used for future analysis when compared with other possible workshops. Final reports will be written to document those persons who attended the workshop as well as to compare the pre- and post-funding estimates. Extra expenses incurred at the workshop are also to be noted. A brief presentation highlighting various aspects of Anguilla’s culture and island is to be made to all participants at the…arrow_forward
- The present Library Information System (LIS) utilized by your organization will no longer receive support from the company, necessitating the selection of a new system. To select the optimal system for your laboratory. It is important to note that testing must be consistently conducted on the existing system throughout the transition period. Is it feasible to undertake all departments simultaneously, and if so, what are the reasons and methods for doing so?arrow_forwardAt Riverside Financial, where you work as a project manager, you have been asked to conduct user training sessions during the implementation phase for a new information system. You must develop a specific schedule for the tasks (the estimated task duration for each is shown in parentheses): First, you need to send an e-mail message to all department managers announcing the training sessions (3 days). After the e-mail message goes out, two tasks can begin at the same time: You can develop the training material (7 days) and confirm arrangements for the training facility you plan to use (15 days). As soon as the training material is complete, you can work on two tasks at once: Arrange to have copies of handout material printed (7 days) and develop a set of PowerPoint slides (8 days). When the PowerPoint slides are ready, you conduct a practice training session with the instructor who will assist you (3 days). Finally, when the practice session is over, the handout material is ready, and…arrow_forwardSuppose you are working as a lead developer for a software house (This software house is a new startup so the developers are not well trained) and you are asked to deliver the project before the estimated time with the same available resources (i.e. neither the salary nor the practitioners are added).In this kind of situation: Which type of risks are identified? Discuss how would you plan the situation being a team leader (hint: Contingency plan)?arrow_forward
- The following table shows activities with duration, dependency, dependency type, and the number of workers from one small segment of a project network. Draw the segment of the network diagram and then: (a) Show the resource usage (chart) if activities A, B, and C start on day one; (b) Show the new network diagram and the resource usage (chart) when resources are leveled after applying appropriate slack times.arrow_forwardA project has three sequences of activities (paths), two of which are critical. The critical paths of this project can be characterized in the following way: a. The slack times for each task in the entire project are zero. b. The chain of activities (from start to finish) that has the largest sum of activity durations. c. The early start date and early finish date are always the same for each activity on the critical path. d. To reduce the project duration, you must reduce the slack time of a task on the critical path. e. None of the above are correct.arrow_forwardThe Global Treps Project needs to have no less than five primary objectives. Using the SMART framework, define each milestone in a short piece. Incorporating the contents of these checkpoints into a Gantt chart as activities or tasks might help the chart better represent the project's progression. Keep in mind that there is usually no deadline attached to a milestone, so you'll need to plan out the steps necessary to reach that goal.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Information Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage LearningDatabase Systems: Design, Implementation, & Manag...Computer ScienceISBN:9781285196145Author:Steven, Steven Morris, Carlos Coronel, Carlos, Coronel, Carlos; Morris, Carlos Coronel and Steven Morris, Carlos Coronel; Steven Morris, Steven Morris; Carlos CoronelPublisher:Cengage LearningDatabase Systems: Design, Implementation, & Manag...Computer ScienceISBN:9781305627482Author:Carlos Coronel, Steven MorrisPublisher:Cengage Learning
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Database Systems: Design, Implementation, & Manag...
Computer Science
ISBN:9781285196145
Author:Steven, Steven Morris, Carlos Coronel, Carlos, Coronel, Carlos; Morris, Carlos Coronel and Steven Morris, Carlos Coronel; Steven Morris, Steven Morris; Carlos Coronel
Publisher:Cengage Learning
Database Systems: Design, Implementation, & Manag...
Computer Science
ISBN:9781305627482
Author:Carlos Coronel, Steven Morris
Publisher:Cengage Learning