he following table shows activities with duration, dependency, dependency type, and the number of workers from one small segment of a project network. Draw the segment of the network diagram and then: (a) Show the resource usage (chart) if activities A, B, and C start on day one; (b) Show the new network diagram and the resource usage (chart) when resources are leveled after applying appropriate slack times.

Database System Concepts
7th Edition
ISBN:9780078022159
Author:Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Publisher:Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Chapter1: Introduction
Section: Chapter Questions
Problem 1PE
icon
Related questions
Question

The following table shows activities with duration, dependency, dependency type, and the number of workers from one small segment of a project network. Draw the segment of the network diagram and then: (a) Show the resource usage (chart) if activities A, B, and C start on day one; (b) Show the new network diagram and the resource usage (chart) when resources are leveled after applying appropriate slack times.

 

 

This table outlines the details of various activities within a project. Each activity is characterized by its duration, predecessors, dependency type, and the number of workers involved. Here's a detailed explanation:

| Activity | Duration | Predecessor (dependency) | Dependency Type | Number of Workers |
|----------|----------|--------------------------|-----------------|-------------------|
| A        | 2        | -                        | D               | 2                 |
| B        | 4        | -                        | D               | 2                 |
| C        | 10       | -                        | M               | 4                 |
| D        | 3        | A                        | D               | 2                 |
| E        | 1        | B                        | D               | 2                 |
| F        | 2        | C,D,E                    | M(C,E)          | 4                 |

### Explanation:

- **Activity**: This column lists the various tasks or activities in the project.
  
- **Duration**: The time each activity is expected to take. For example, Activity A has a duration of 2 units of time.

- **Predecessor (dependency)**: This shows which activities need to be completed before the current activity can begin. A dash ("-") indicates no predecessors.

- **Dependency Type**: 
  - "D" indicates a Direct dependency, where one activity depends on the completion of another.
  - "M" indicates a Multiple dependency, where the activity may depend on more complex conditions or multiple predecessor activities.
  - "M(C,E)" for Activity F signifies a dependency on the completion of Activities C and E.

- **Number of Workers**: Indicates how many workers are assigned to each activity. For example, Activity C involves 4 workers.

This table is used for project planning and scheduling, helping to allocate resources efficiently and identify dependencies between tasks.
Transcribed Image Text:This table outlines the details of various activities within a project. Each activity is characterized by its duration, predecessors, dependency type, and the number of workers involved. Here's a detailed explanation: | Activity | Duration | Predecessor (dependency) | Dependency Type | Number of Workers | |----------|----------|--------------------------|-----------------|-------------------| | A | 2 | - | D | 2 | | B | 4 | - | D | 2 | | C | 10 | - | M | 4 | | D | 3 | A | D | 2 | | E | 1 | B | D | 2 | | F | 2 | C,D,E | M(C,E) | 4 | ### Explanation: - **Activity**: This column lists the various tasks or activities in the project. - **Duration**: The time each activity is expected to take. For example, Activity A has a duration of 2 units of time. - **Predecessor (dependency)**: This shows which activities need to be completed before the current activity can begin. A dash ("-") indicates no predecessors. - **Dependency Type**: - "D" indicates a Direct dependency, where one activity depends on the completion of another. - "M" indicates a Multiple dependency, where the activity may depend on more complex conditions or multiple predecessor activities. - "M(C,E)" for Activity F signifies a dependency on the completion of Activities C and E. - **Number of Workers**: Indicates how many workers are assigned to each activity. For example, Activity C involves 4 workers. This table is used for project planning and scheduling, helping to allocate resources efficiently and identify dependencies between tasks.
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Knowledge Booster
Software cost estimation
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Database System Concepts
Database System Concepts
Computer Science
ISBN:
9780078022159
Author:
Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Publisher:
McGraw-Hill Education
Starting Out with Python (4th Edition)
Starting Out with Python (4th Edition)
Computer Science
ISBN:
9780134444321
Author:
Tony Gaddis
Publisher:
PEARSON
Digital Fundamentals (11th Edition)
Digital Fundamentals (11th Edition)
Computer Science
ISBN:
9780132737968
Author:
Thomas L. Floyd
Publisher:
PEARSON
C How to Program (8th Edition)
C How to Program (8th Edition)
Computer Science
ISBN:
9780133976892
Author:
Paul J. Deitel, Harvey Deitel
Publisher:
PEARSON
Database Systems: Design, Implementation, & Manag…
Database Systems: Design, Implementation, & Manag…
Computer Science
ISBN:
9781337627900
Author:
Carlos Coronel, Steven Morris
Publisher:
Cengage Learning
Programmable Logic Controllers
Programmable Logic Controllers
Computer Science
ISBN:
9780073373843
Author:
Frank D. Petruzella
Publisher:
McGraw-Hill Education