Question
Chapter 4, Problem 24PE
Program Plan Intro
Economic feasibility analysis of an
Monetary benefits of an information system = ($40,000 for year 1), ($50,000 for year 2), ($60,000 for year 3), ($70,000 for year 4), ($80,000 for year 5), ($90,000 for year 6).
One-time costs = $80,000
Recurring cost = $40,000 per year.
Discount rate = 11%
Time period = 6 years
Explanation of Solution
Overall Return on Investment (ROI):
Overall return on investment can be calculated as:
Explanation of Solution
Break-Even Analysis (BEA):
- Break even analysis is carried out by determining NPV of yearly cash flows.
- The yearly cash flows are calculated by subtracting present values of recurring costs from the present value of yearly benefits...
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Use one requirement gathering technique to help clarify your proposed PM project (described in your answer for question 1). Then explain how you have used the technique and the results you have found.
Answer:
Chosen Requirement Gathering Technique:
Chosen Requirement Gathering Technique Scope:
Procedure followed:
Results:
Project scope statement:
what is the problem statement and objectives for this situation
Discuss the techniques and methods used in requirement prioritization and their significance.
Chapter 4 Solutions
Essentials of Systems Analysis and Design (6th Edition)
Ch. 4 - Prob. 1MCh. 4 - Prob. 2MCh. 4 - Prob. 3MCh. 4 - Prob. 4MCh. 4 - Prob. 5MCh. 4 - Prob. 6MCh. 4 - Prob. 7MCh. 4 - Prob. 8MCh. 4 - Prob. 9MCh. 4 - Prob. 10M
Ch. 4 - Prob. 11MCh. 4 - Prob. 12MCh. 4 - Prob. 13MCh. 4 - Prob. 14MCh. 4 - Prob. 15MCh. 4 - Prob. 16MCh. 4 - Prob. 17MCh. 4 - Prob. 18MCh. 4 - Prob. 19MCh. 4 - Prob. 20MCh. 4 - Prob. 21MCh. 4 - Prob. 22MCh. 4 - Prob. 1RQCh. 4 - Describe several project evaluation criteria.Ch. 4 - Prob. 3RQCh. 4 - Prob. 4RQCh. 4 - Prob. 5RQCh. 4 - Prob. 6RQCh. 4 - What are the potential consequences of not...Ch. 4 - Prob. 8RQCh. 4 - Prob. 9RQCh. 4 - Prob. 10RQCh. 4 - Prob. 11RQCh. 4 - Prob. 12PECh. 4 - Prob. 13PECh. 4 - Prob. 14PECh. 4 - Prob. 15PECh. 4 - Prob. 16PECh. 4 - Prob. 17PECh. 4 - Prob. 18PECh. 4 - Prob. 19PECh. 4 - Prob. 20PECh. 4 - Prob. 21PECh. 4 - Assume monetary benefits of an information system...Ch. 4 - Prob. 23PECh. 4 - Prob. 24PECh. 4 - Prob. 25PECh. 4 - Prob. 26PECh. 4 - Prob. 27PECh. 4 - Prob. 28PECh. 4 - Prob. 29DQCh. 4 - Prob. 30DQCh. 4 - Prob. 31DQCh. 4 - Prob. 32DQCh. 4 - Prob. 33CPCh. 4 - Prob. 34CPCh. 4 - Prob. 35CPCh. 4 - Prob. 36CQCh. 4 - Prob. 37CQCh. 4 - Identify a preliminary set of tangible and...Ch. 4 - Prob. 39CQCh. 4 - If you were assigned to help Jim with this...Ch. 4 - Prob. 41CQCh. 4 - Prob. 42CQCh. 4 - In Question 4, you analyzed the risks associated...
Knowledge Booster
Similar questions
- If 10 requirements defects are removed during design phase, and the relative cost is 2.5,what is the cost to remove these defects?arrow_forwardGenerate a schedule of project in Gantt chart to observe the task timeline and progress.arrow_forwardi. At what stage of the SDLC do you intend to carry out Requirements validation of your projectarrow_forward
- SYSTEM ANALYSIS AND DESIGN ( COMPUTER SCIENCE) Instruction: As a system analyst, you are required to analyze and propose a system design for your client company to help in their daily business process. Choose ONE (1) of the following system and discuss the development process in detail. Online Tuition Center - Online Babysitter - Online Cleaning Service Online Event Management - Online Emergency Management - Online Personal Shopper Question 1 a) Identify the appropriate system development method and explain why it is suitable for the system. b) List all the possible functions applicable to the system. c) Create a Gantt chart for the system analysis and design proposal. You may use the outline provided as a guideline for your Gantt Chart Outline for Gantt chart System Investigation - Introduction - System Request Form - Project Proposal - Feasibility Studies - Fact Finding Techniques Used - List of End-user Requirement System Analysis - Proposed Actors & Use cases - Proposed Use case…arrow_forwardAs a project manager of a Software project, you have received given data about the different type of Issues identified in the project: - Issue 1 85 occurrences; Issue 2 - 125 occurrences; Issue 3 - 28 occurrences; Issue 4 - 395 occurrences; Issue 5 - 185 occurrences; Issue 6- 128 occurrences; Issue 7 – 85 occurrences; Issue 8 169 occurrences; Issue 9 - 148 occurrences; Issue 10 209 occurrences. - - Which diagram you will use to prioritize the Issues? Generate the diagram using any tool and paste it here.arrow_forwardAs a project manager of a Software project, you have received given data about the different type of Issues identified in the project: – Issue 1 – 85 occurrences; Issue 2 – 125 occurrences; Issue 3 – 28 occurrences; Issue 4 – 395 occurrences; Issue 5 – 185 occurrences; Issue 6 – 128 occurrences; Issue 7 – 85 occurrences; Issue 8 – 169 occurrences; Issue 9 – 148 occurrences; Issue 10 – 209 occurrences. Which diagram you will use to prioritize the Issues? Generate the diagram using any tool and paste it here.arrow_forward
- You have been made project coordinator for an upcoming tourism workshop to be held in the island of Anguilla. Local, regional and international participants will be in attendance. You have invited 25 participants and 12 presenters as part of your planning. In addition, there are several other tasks to be performed: i. Letters of invitation are to be sent with relevant information. ii. Overall estimates for workshop funding need to be calculated. iii. During the workshop, all attendees and equipment requests will be documented for reporting purposes and also to be used for future analysis when compared with other possible workshops. iv. Final reports will be written to document those persons who attended the workshop as well as to compare the pre- and post-funding estimates. v. Extra expenses incurred at the workshop are also to be noted. vi. A brief presentation highlighting various aspects of Anguilla’s culture and island is to be made to all participants at the beginning of the…arrow_forwardWrite "Cost Management" about age detection. -Calculate net present value, Return on Investment for 3 years. Also calculate payback time for your project-Estimate the cost of your project ( which method would you use, top-down, bottom-up, parametric etc.) create project cost estimate table. -Provide cost estimate by using function point estimate.arrow_forwardThe term "requirements prioritisation and negotiation" refers to a phase of the SDLC concerned with gathering and analyzing requirements.You'll have to elaborate on it.arrow_forward
- h) Based on the analysis finding, write a short report and recommend the options in terms of achieving higher solvability.arrow_forwardWhat challenges can arise during the requirement analysis phase, and how can they be effectively addressed to prevent scope creep?arrow_forwardThis chart presents an overview of a project's status in terms of tasks, and represents the plan vs actual progress of the tasks in colored horizontal bars across a timeline. Company Name Project Lead TASK Phase 1 Planning Task 1 Document requirements Task 2 Prepare task list Task 3 Assign tasks to members Task 4 Brain storm technology Task 5 Update start and end dats of tasks Phase 2 Design Task 1 Research header component Task 2 Research SQL methodology with PHP CPM chart Gantt chart FDD Diagram PERT chart ASSIGNED TO Jose Project Start: Display Week: PROGRESS 50% 60% 50% 25% 50% 50% Wed, 10/26/2022 1 START 10/26/22 END 10/29/22 10/29/22 10/31/22 10/31/22 11/4/22 11/4/22 11/9/22 10/30/22 11/1/22 10/31/22 11/4/22 11/2/22 11/7/22 Oct 24, 2022 Oct 31, 2022 Nov 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 MTW FSSMTWTFSSMTarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Information Systems (MindTap Course...Computer ScienceISBN:9781305971776Author:Ralph Stair, George ReynoldsPublisher:Cengage LearningInformation Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage Learning
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781305971776
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning