a.

Explanation of Solution

Identification and selection of project:

  • By using inventory control systems, the needs and requirements of the project can be identified...

b.

Explanation of Solution

Identifying the project scope:

  • The project scope includes the hardware or software components, customer requirements, and inventory systems and so on...

c.

Explanation of Solution

Feasibility factors:

  • Economic feasibility:
    • It provides excellent customer service by proposing new inventory system.
    • It provides benefits such as profit and rapid increase in sales.
  • Operational feasibility:
    • For maintaining time, efficient operating systems should be used.
    • Implementation of best systems provides excellent service to customers...

d.

Explanation of Solution

Project scope statement:

Project scope statement for improving inventory control is given below:

Hosier Burgur                               Prepared by : Bob

Project scope statement                Date : 12-05-2019

General project information

Project Name         : Improving inventory control

Sponsor                  ...

Blurred answer
Students have asked these similar questions
Scenario: Tasneem Software Engineering Company won a new project for Mirbat Bank. According to the project plan, the final system will take at least nine months to complete. Thus, the team has decided to divide the system into a small number of minimum cycles. Each cycle will include a set of activities that will allow team members to finish and review the code.     QUESTIONS: 1.       What is the most appropriate process model for this scenario, and why?   2.       List two advantages and two disadvantages of the aforementioned process model.  3.       In your opinion, which of the process models is the worst to use in software development?      hellllllllllllp
You've been appointed project coordinator for a tourism workshop to be conducted on the island of Anguilla in the near future. There will be local, regional, and international participants in attendance. As part of your preparations, you have invited 25 participants and 12 speakers. There are also many additional tasks to be completed:   Invitation letters must include all pertinent information. Estimates for workshop financing must be calculated in total. All participants and equipment requirements will be recorded throughout the session for reporting reasons and to be compared to other potential seminars in the future. The workshop attendees will be documented, and the pre- and post-funding projections will be compared. It's also worth noting any additional costs spent during the session. As part of the workshop's welcome, all participants will be given a short presentation showcasing different elements of Anguilla's culture and island. It should be emphasized that data duplication…
solve the questions: Tony and his team identified some risks during the first month of the Recreation and Wellness Intranet Project. However, all they did was document the risks in a list. They never ranked the risks or developed any response strategies. Because the project has had several problems, such as key team members leaving the company, users being uncooperative, and team members not providing good status information. Tony has decided to be more proactive in managing risks. He also wants to address positive risks as well as negative risks. the quation is : 1- Plot the six risks on a probability/impact matrix.  2-  assign a numeric value for the probability and impact of each risk on meeting the main project objective.
Knowledge Booster
Background pattern image
Computer Science
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning