What is the definition of the latest completion time (LCT) of a project activity?
- a. LCT(Ai) = Max{LST(Aj) for which Aj is a successor of Ai}
- b. LCT(Ai) = Min{LST(Aj) for which Aj is a successor of Ai}
- c. LCT(Ai) = Max{LST(Aj) for which Aj is a predecessor of Ai}
- d. LCT(Ai) = Min{LST(Aj) for which Aj is a predecessor of Ai}
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Which of the following in the project
management process defines a set of
clear, discrete set of activities and
resources required to complete a
project?
O Project Initiation.
Project Execution.
O Project Monitoring and Control.
Project Planning.
Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon
receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the
activities.
Activity
A
B
с
D
E
F
Description
Plan needs
Order equipment
Install equipment
Set up training lab
Conduct training course
Test system
Immediate
Predecessor
A
B
A
D
C, E
Time (weeks)
Normal Crash
10
8
10
7
10
3
6
7
6
8
3
Cost ($1,000s)
Normal
30
120
100
40
50
60
Crash
70
150
160
50
75
2.To obtain reasonable assurance about the completion of the project within the timeline, the best method is which of the following?
Group of answer choices
To compare the estimated end date and estimated time for completion of the project
To obtain confirmation from the project manager about the project completion date
To obtain confirmation from the project manager about the project completion date
To extrapolate the end date on the basis of completed work and resource availability
15.From among the following activities, which is the best example of a project?
Group of answer choices
Writing a term paper
Completing a college degree
Producing automobiles
Processing insurance claims
Chapter 19 Solutions
Operations Management
Ch. 19 - A project has four activities that take 4, 3, 6,...Ch. 19 - Consider the simple dependency matrix shown in...Ch. 19 - Consider a project with two activities that are...Ch. 19 - Prob. 4CQCh. 19 - Prob. 5CQCh. 19 - Prob. 6CQCh. 19 - Prob. 7CQCh. 19 - Prob. 8CQCh. 19 - Prob. 9CQCh. 19 - Prob. 10CQ
Ch. 19 - Consider two projects that have the same...Ch. 19 - Prob. 12CQCh. 19 - Prob. 13CQCh. 19 - Prob. 14CQCh. 19 - The key objectives of a project are given by a....Ch. 19 - Which of the following descriptions best captures...Ch. 19 - Prob. 1PACh. 19 - Prob. 2PACh. 19 - Prob. 3PACh. 19 - Prob. 4PACh. 19 - A project activity has an earliest completion time...Ch. 19 - What is the definition of the latest completion...Ch. 19 - Which of the following statements is correct with...Ch. 19 - A project consists of three tasks: A, B, and C....Ch. 19 - Prob. 9PACh. 19 - Prob. 10PACh. 19 - You manage a project with 10 activities....Ch. 19 - Which of the following activities is not part of...Ch. 19 - You have been asked by the CEO of your company to...Ch. 19 - BUILDING A HOUSE IN THREE HOURS Habitat for...Ch. 19 - BUILDING A HOUSE IN THREE HOURS Habitat for...
Additional Business Textbook Solutions
Find more solutions based on key concepts
What is precedent, and how does it affect common law?
Business in Action (8th Edition)
2. In what circumstances might a market-pull approach or a technology-push approach to new-product design be th...
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
2. Identify four people who have contributed to the theory and techniques of operations management.
Operations Management: Sustainability and Supply Chain Management (12th Edition)
There is a huge demand in the United States and elsewhere for affordable women’s clothing. Low-cost clothing re...
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
Mary Williams, owner of Williams Products, is evaluating whether to introduce a new product line. After thinkin...
Operations Management: Processes and Supply Chains (11th Edition)
The flowchart for the process at the local car wash. Introduction: Flowchart: A flowchart is a visualrepresenta...
Principles Of Operations Management
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- When is it MOST important that integration is performed? A At key interface points 60 217 B During project executing C At the end of each project management process D During project planningarrow_forwardn accepted deadline for project approaches. However, the project manager realizes only 75% percent of the work has been completed. The project manager then issues a change request. What should the change request authorize? Can you explain this.arrow_forwardThe four types of project closures are: Group of answer choices a. finite, infinite, continuous, discrete b. crashed, finished, successful, unsuccessful c. none of these d. normal, premature, perpetual, failedarrow_forward
- The following precedence diagram reflects three time estimates for each activity. Determine: Use Table B1 and Table B2. 9-10-12 3 8 5-7-10 8-10-14 11-12-13 6 11 14-18-26 10.5-13-15.5 10 8-8-8 1 5-6-7 2 4 13-13-13 7 7-10-12 a. The expected completion time for each path and its variance. (Round intermediate calculations to 4 decimal places and final answers to 2 decimal places.) Path Mean Var. Std. Dev. 1-2-3-8-11 37.33 1-2-4-6-11 43.00 5.11 1-2-4-7-11 0.81 1-2-5-9-10-11 46.83 1.25 9-9-9 10-11-12 10-12-14arrow_forwardMueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 45-week completion date requested by the owner. The Mueller project manager prepared the following project network. Start A B F H 0 D E Finish Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows. Activity Optimistic Most Probable A 4 8 Pessimistic 12 B 6 7 8 C 6 12 18 D 3 5 7 E 6 9 18 F 5 8 17 G 10 15 20 H 5 6 13arrow_forwardThe expected number of days to completion for a different project is E(x) = 3.32 The variance of days to completion is var(x) = 1.22 The project cost involves A fixed cost (in thousands of dollars) of FC = $83.783 A variable cost for each day taken to complete the project ($000) VC = $9.774 16 The standard deviation of the project cost is $________. a 13.041 b 12.245 c 11.497 d 10.796arrow_forward
- Incorporating flotation costs into the analysis of a project will : a. increase the initial cash outflow of the project b. cause the project to be improperly evaluated c. increase the net present value of the project d. increase the project's rate of returnarrow_forward(12) Cost budgeting can be best described by which of the following? A The process of developing the future trends along with the assessment of proba bilities, uncertainties, and inflation that could occur during the project B. The process of assembling and predicting costs of a project over its life cycle C. The process of establishing budgets, standards, and a monitoring system by whi ch the investment cost of the project can be measured and managed D. The process of gathering, accumulating, analyzing, reporting, and managing the costs on an on-going basis (13) The process of monitoring the status of the project to update the project costs and managing changes to the cost baseline is called A Determine Budget B. Control Costs C. Estimate Costs D. Plan Cost Manag ement (14) Cost Variance (CV) is which of the following equations? A CV = EV - PV B. CV = EV - AC C. CV = EV / AC D. A and c (15) To assist in budget control, it is suggested that an estimate be created at the level of the…arrow_forwardMangement Project management is a discipline that involves planning, organizing, and overseeing the execution of a project from initiation to completion. It encompasses defining project goals, outlining tasks, allocating resources, and managing budgets and timelines. A successful project manager must possess strong leadership skills, effective communication, and the ability to mitigate risks and solve problems efficiently. Collaboration among team members is crucial, as is the flexibility to adapt to unexpected challenges that may arise during the project lifecycle. Continuous monitoring and evaluation ensure that the project stays on track, meeting objectives and delivering value to stakeholders. Question: How can project managers encourage effective collaboration and communication among team members to ensure the successful and timely completion of a project?arrow_forward
- Which of the following statements regarding PERT analysis is TRUE? Select one: O a Project variance is the sum of all activity variances. O b. Project standard deviation is the sum of all critical activity standard deviations. O c. Each activity has two estimates of its duration. O d. Only critical activities contribute to the project variancearrow_forwardWhich one of the following statements best defines an estimate? The value of useful work done at any given point in a project to give a measure of progress. An approximation of project time and cost targets, refined throughout the project life cycle. A situation that affects or influences the outcome of the project expressed in time or cost terms. A prediction of a future condition or event based on information or knowledge available now.arrow_forwardThe following represents a project that should be scheduled using CPM: ACTIVITY ABCDEFGH А с IMMEDIATE PREDECESSORS IAABUDR C,D D,E F,G TIMES (DAYS) b a 1 1 3 - NTTTTE 1 1 1 1 2 m 5 WaNNASNU 2 5 4 2 2 6 3 ∞∞NWO3770 9 10 12 8arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY