Problem 19-1A
Production costs computed and recorded; reports prepared C2 P1 P2 P3 P4
Marcelino Co's March 31 inventory of raw materials is $80,000. Raw materials purchases in April are $500,000, and
Jsb 306 | Job 307 | Job 308 | |
Balances on March 31 | |||
Direct materials | $ 29.000 | $ 35.000 | |
Direct lata | 20.000 | 18.000 | |
Applied overhead | 10,10 | 9.000 | |
Costs during April | |||
Direct materials | 135,000 | 220.000 | $100,000 |
Direct lata | 85,000 | 150.000 | 105,000 |
Applied overhead | ? | ? | ? |
Status or April 30 | Finished (sold) | Finished (unsold) | In process |
Required
- Determine the total of each production cost incurred for April (direct labor, direct materials, and applied overhead) and the total cost assigned to each job (including the balances from March 31).
- Prepare
journal entries for the month of April to record the following.
a. Materials purchases (on credit).
b. Direct materials used in production.
c. Direct labor paid and assigned to Work in Process Inventor)7.
d. Indirect labor paid and assigned to Factor;7 Overhead.
e. Overhead costs applied to Work in Process Inventor)7.
f. Actual overhead costs incurred, including indirect materials. (Factory rent and utilities are paid in cash.)
g.
Transfer of Jobs 306 and 307 to Finished Goods Inventory.
h.
Cost of goods sold for Job 306.
i. Revenue from the sale of Job 306.
j. Assignment of any underapplied or overapplied overhead to the Cost of Goods Sold account. (The amount is not material.)
Want to see the full answer?
Check out a sample textbook solutionChapter 19 Solutions
FUND.ACCT.PRIN.
- Applying factory overhead Bergan Company estimates that total factory overhead costs will be 620,000 for the year. Direct labor hours are estimated to be 80,000. For Bergan Company, (A) determine the predetermined factory overhead rate using direct labor hours as the activity base, (B) determine the amount of factory overhead applied to Jobs 200 and 305 in May using the data on direct labor hours from BE 16-2, and (C) prepare the journal entry to apply factory overhead to both jobs in May according to the predetermined overhead rate.arrow_forwardA company estimates its manufacturing overhead will be $750,000 for the next year. What is the predetermined overhead rate given the following independent allocation bases? Budgeted direct labor hours: 60,000 Budgeted direct labor expense: $1,500,000 Estimated machine hours: 100,000arrow_forwardPlease solve this MCQs The following costs were incurred in May: Direct materials $ 43,100 Direct labor $ 24,800 Manufacturing overhead $ 18,100 Selling expenses $ 20,300 Administrative expense $ 28,700 Prime costs during the month totaled: $135,000 $86,000 $42,900 $67,900arrow_forward
- Finished Goods (FG) Inventory Factory Overhead April 30 57,000 Cost of goods sold Cost of goods manuf. May 31 57,000 Income statement (partial)arrow_forwardProblem 19-1A Production costs computed and recorded; reports prepared LO P1, P2, P3, P4 Skip to question [The following information applies to the questions displayed below.] Marcelino Co.'s March 31 inventory of raw materials is $88,000. Raw materials purchases in April are $540,000, and factory payroll cost in April is $382,000. Overhead costs incurred in April are: indirect materials, $56,000; indirect labor, $25,000; factory rent, $31,000; factory utilities, $23,000; and factory equipment depreciation, $52,000. The predetermined overhead rate is 50% of direct labor cost. Job 306 is sold for $630,000 cash in April. Costs of the three jobs worked on in April follow. Job 306 Job 307 Job 308 Balances on March 31 Direct materials $ 32,000 $ 37,000 Direct labor 25,000 16,000 Applied overhead 12,500 8,000 Costs during April Direct materials 138,000…arrow_forwardWork in Frocess May 1 Per general ledger P22,250 Per cost sheets #001 #002 #003 Direct materials P 6,000 P S,000 Direct labor 3,000 2,500 Factory Costs for May 6,000 2,600 Direct materials 3,000 2,000 Direct labor 1,000 1,500 Factory overhead is charged to production based on direct labor cost. Jobs #001 and #002 are completed during the month. Required: Determine the following: L Total manufacturing costs for the month. 2. Total cost of Job #001. 3. Total cost of Job #002 4. Work in Process - End 5. Total factory overhead applied for the month 6. Cos of goods manufactured for the month. V. Multiple C 1. Whicharrow_forward
- Total Manufacturing Overhead at the beginning of the year $105,840 Total direct labour costs estimated at the beginning of the year $186,000 Total direct labour hours estimated at the beginning of the year 3,600 DLH Actual manufacturing overhead costs for the year $99,760 Actual direct labour costs for the year $142,000 Actual direct labou hours for th eyear 2,950 DLH The company bases its manufacturing overhead allocation on direct labour hours. What was the predetermined manufacturing overhead allocation rate for 2012? 2. Halcyon Company just completed Job #22. See details below. Direct labor cost: $2,040 Direct materials cost: $90 Direct labor hours: 75 Predetermined manufacturing overhead allocation rate: $34.00 per direct labor hour Number of units of finished product: 200 units. What was cost per unit of finished product? 3. Use Picture 1 to answer the following: A. After these transactions have been recorded, the balance in the Work in…arrow_forwardroblem 19-1A Production costs computed and recorded; reports prepared LO P1, P2, P3, P4 Skip to question [The following information applies to the questions displayed below.] Marcelino Co.'s March 31 inventory of raw materials is $88,000. Raw materials purchases in April are $540,000, and factory payroll cost in April is $382,000. Overhead costs incurred in April are: indirect materials, $56,000; indirect labor, $25,000; factory rent, $31,000; factory utilities, $23,000; and factory equipment depreciation, $52,000. The predetermined overhead rate is 50% of direct labor cost. Job 306 is sold for $630,000 cash in April. Costs of the three jobs worked on in April follow. Job 306 Job 307 Job 308 Balances on March 31 Direct materials $ 32,000 $ 37,000 Direct labor 25,000 16,000 Applied overhead 12,500 8,000 Costs during April Direct materials 138,000…arrow_forwardApril 1April 30Direct materials $67,000 $62,000 Work-in-process 145,000 171,000 Finished goods 85,000 78,000 Production data for the month of April is: Direct labor$200,000 Actual overhead 132,000 Direct materials purchased 163,000 Transportation in 4,000 Purchase Returns and Allowances 2,000 Beckett uses one overhead control account and charges overhead to production at 70% of direct labor cost. The company does not formally recognize over- or underapplied overhead until year-end. What is Beckett's cost of goods transferred to finished goods inventory for April?arrow_forward
- Spree Party Lights overhead expenses are: Indirect material, pounds per unit 0.30 Indirect material, cost per pound $2 Indirect labor hours 1 Indirect labor rate per hour $16.50 Variable maintenance per unit $0.70 Variable utilities per unit $0.10 Supervisor salaries $11,000 Maintenance salaries $10,000 Insurance $3,000 Depreciation $1,400 Prepare a manufacturing overhead budget if the number of units to produce for January, February, and March are 2,400, 3,100, and 2,600, respectively. Spree Party Lights Manufacturing Overhead Budget For the Quarter Ending January - March January February March Units to Produce fill in the blank 1 fill in the blank 2 fill in the blank 3 Variable Costs Indirect Material $fill in the blank 5 $fill in the blank 6 $fill in the blank 7 Indirect Labor fill in the blank 9 fill in the blank 10 fill in the blank 11 Maintenance fill in the blank 13 fill in the blank 14 fill in the blank 15 Utilities…arrow_forwardSpree Party Lights overhead expenses are: Indirect material, pounds per unit 0.30 Indirect material, cost per pound $2 Indirect labor hours 1 Indirect labor rate per hour $16.50 Variable maintenance per unit $0.75 Variable utilities per unit $0.20 Supervisor salaries $11,000 Maintenance salaries $9,000 Insurance $3,000 Depreciation $1,600 Prepare a manufacturing overhead budget if the number of units to produce for January, February, and March are 2,400, 3,100, and 2,800, respectively. Spree Party LightsManufacturing Overhead BudgetFor the Quarter Ending January - March January February March Units to Produce fill in the blank 1 fill in the blank 2 fill in the blank 3 Variable Costs $- Select - $- Select - $- Select - - Select - - Select - - Select - - Select - - Select - - Select - - Select - - Select - - Select - Total Variable Manufacturing Costs $fill in the blank 20 $fill in the blank 21 $fill in the blank 22…arrow_forwardProblem 13-30 (Algo) Cost of goods manufactured, cost of goods sold, and income statement LO 4, 5, 7 I JUST NEED HELP WITH PART D!! PLEASE!! Morrison & Company incurred the following costs during August: Raw materials purchased $ 44,060 Direct labor ($12.4 per hour) 54,684 Manufacturing overhead (actual) 90,230 Selling expenses 31,790 Administrative expenses 14,380 Interest expense 6,231 Manufacturing overhead is applied on the basis of $20 per direct labor hour. Assume that overapplied or underapplied overhead is transferred to cost of goods sold only at the end of the year. During the month, 4,080 units of product were manufactured and 4,470 units of product were sold. On August 1 and August 31, Morrison & Company carried the following inventory balances: August 1 August 31 Raw materials $ 19,800 $ 17,700 Work in process 52,700 56,900 Finished goods 41,300 23,631 Required: Prepare a…arrow_forward
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubPrinciples of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage LearningPrinciples of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College