Adequate information:

Debt-equity ratio D/E = 0.65

Debt D = 0.65

Equity E = 1

Capital required K = $1,850,000

Cost of equity ke = 11%

After-tax cost of debt kd = 4.3%

Growth rate g = 3%

Adjustment factor Af = 2%

To compute: To identify the circumstances under which the project should be taken or not.

Introduction: Breakeven cost refers to the equilibrium point where the company is at the no profit no loss stage.

Blurred answer
Students have asked these similar questions
WACC and NPV Pink, Inc., is considering a project that will result in initial aftertax cash savings of $1.82 million at the end of the first year, and these savings will grow at a rate of 3 percent per year indefinitely. The firm has a target debt-equity ratio of .85, a cost of equity of 12.2 percent, and an aftertax cost of debt of 5 percent. The cost-saving proposal is somewhat riskier than the usual projects the firm undertakes; management uses the subjective approach and applies an adjustment factor of +2 percent to the cost of capital for such risky projects.   What is the maximum initial cost the company would be willing to pay for the project?
Lible, Incorporated, is considering a project that will result in initial aftertax cash savings of $1.74 million at the end of the first year, and these savings will grow at a rate of 1 percent per year indefinitely. The firm has a target debt-equity ratio of .75, a cost of equity of 11.4 percent, and an aftertax cost of debt of 4.2 percent. The cost-saving proposal is somewhat riskier than the usual project the firm undertakes; management uses the subjective approach and applies an adjustment factor of +2 percent to the cost of capital for such risky projects. What is the maximum initial cost the company would be willing to pay for the project? (Do not round intermediate calculations and enter your answer in dollars, not millions, rounded to the nearest whole number, e.g., 1,234,567.)
Ariana, Incorporated, is considering a project that will result in initial aftertax cash savings of $5.7 million at the end of the first year, and these savings will grow at a rate of 3 percent per year, indefinitely. The firm has a target debt-equity ratio of .56, a cost of equity of 13.1 percent, and an aftertax cost of debt of 5 percent. The cost-saving proposal is somewhat riskier than the usual project the firm undertakes; management uses the subjective approach and applies an adjustment factor of +2 percent to the cost of capital for such risky projects. Calculate the required return for the project. Note: Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16. What is the maximum cost the company would be willing to pay for this project? Note: Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:9781337514835
Author:MOYER
Publisher:CENGAGE LEARNING - CONSIGNMENT
Text book image
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Text book image
Intermediate Financial Management (MindTap Course...
Finance
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Cengage Learning