Fundamentals of Corporate Finance
11th Edition
ISBN: 9780077861704
Author: Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Bradford D Jordan Professor
Publisher: McGraw-Hill Education
expand_more
expand_more
format_list_bulleted
Textbook Question
Chapter 11, Problem 10QP
Using Break-Even Analysis [LO3] Consider a project with the following data: accounting break-even quantity = 14,200 units; cash break-even quantity = 10,300 units; life = five years; fixed costs = $170,000; variable costs = $27 pier unit; required return = 12 percent. Ignoring the effect of taxes, find the financial break-even quantity.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The most likely outcomes for a particular project are estimated as follows:
Unit price:
Variable cost:
Fixed cost:
Expected sales:
50
24
30
$370,000
36,000 units per year
However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10%
higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.4 million, which will
be depreclated straight-line over the project life to a final value of zero. The firm's tax rate is 21% and the required rate of return is 14%.
(For all the requirements, a negative amount should be indicated by a minus sign. Enter your answer in dollars not in millions. Do
not round intermediate calculations. Round your answer to the nearest dollar amount.)
a. What is project NPV in the best-case scenario, that is, assuming all variables take on the best possible value?
b. What is project NPV in the worst-case scenario?
The most likely outcomes for a particular project are estimated as
follows:
Unit price:
Variable cost:
Fixed cost:
Expected sales:
$ 50
$ 30
$ 490,000
48,000 units per year
However, you recognize that some of these estimates are subject to
error. Suppose each variable turns out to be either 10% higher or 10%
lower than the initial estimate. The project will last for 10 years and
requires an initial investment of $2.3 million, which will be depreciated
straight-line over the project life to a final value of zero. The firm's tax
rate is 21%, and the required rate of return is 10%.
a. NPV
b. NPV
a. What is project's NPV in the best-case scenario, that is, assuming
all variables take on the best possible value?
b. What is project's NPV in the worst-case scenario?
Note: For all the requirements, a negative amount should be
indicated by a minus sign. Enter your answers in dollars, not in
millions. Do not round intermediate calculations. Round your
answers to the nearest dollar amount.
4
I want to be sure about my answers.
Chapter 11 Solutions
Fundamentals of Corporate Finance
Ch. 11.1 - Prob. 11.1ACQCh. 11.1 - What are some potential sources of value in a new...Ch. 11.2 - Prob. 11.2ACQCh. 11.2 - What are the drawbacks to the various types of...Ch. 11.3 - How are fixed costs similar to sunk costs?Ch. 11.3 - What is net income at the accounting break-even...Ch. 11.3 - Why might a financial manager be interested in the...Ch. 11.4 - If a project breaks even on an accounting basis,...Ch. 11.4 - If a project breaks even on a cash basis, what is...Ch. 11.4 - Prob. 11.4CCQ
Ch. 11.5 - What is operating leverage?Ch. 11.5 - How is operating leverage measured?Ch. 11.5 - Prob. 11.5CCQCh. 11.6 - What is capital rationing? What types are there?Ch. 11.6 - Prob. 11.6BCQCh. 11 - Prob. 11.1CTFCh. 11 - Marcos Entertainment expects to sell 84,000...Ch. 11 - Delta Tool has projected sales of 8,500 units at a...Ch. 11 - What is true for a project if that project is...Ch. 11 - A capital-intensive project is one that has a...Ch. 11 - Pavloki, Inc., has three proposed projects with...Ch. 11 - Forecasting Risk [LO1] What is forecasting risk?...Ch. 11 - Sensitivity Analysis and Scenario Analysis [LO1,...Ch. 11 - Prob. 3CRCTCh. 11 - Operating Leverage [LO4] At one time at least,...Ch. 11 - Operating Leverage [LO4] Airlines offer an example...Ch. 11 - Prob. 6CRCTCh. 11 - Prob. 7CRCTCh. 11 - Prob. 8CRCTCh. 11 - Prob. 9CRCTCh. 11 - Scenario Analysis [LO2] You are at work when a...Ch. 11 - Calculating Costs and Break-Even [LO3] Night...Ch. 11 - Prob. 2QPCh. 11 - Scenario Analysis [LO2] Sloan Transmissions, Inc.,...Ch. 11 - Sensitivity Analysis [LO1] For the company in the...Ch. 11 - Sensitivity Analysis and Break-Even [LO1, 3] We...Ch. 11 - Prob. 6QPCh. 11 - Prob. 7QPCh. 11 - Calculating Break-Even [LO3] In each of the...Ch. 11 - Calculating Break-Even [LO3] A project has the...Ch. 11 - Using Break-Even Analysis [LO3] Consider a project...Ch. 11 - Calculating Operating Leverage [LO4] At an output...Ch. 11 - Leverage [LO4] In the previous problem, suppose...Ch. 11 - Operating Cash Flow and Leverage [LO4] A proposed...Ch. 11 - Cash Flow and Leverage [LO4] At an output level of...Ch. 11 - Prob. 15QPCh. 11 - Prob. 16QPCh. 11 - Sensitivity Analysis [LO1] Consider a four-year...Ch. 11 - Operating Leverage [LO4] In the previous problem,...Ch. 11 - Project Analysis [LO1, 2, 3, 4] You are...Ch. 11 - Project Analysis [LO1, 2] McGilla Golf has decided...Ch. 11 - Prob. 21QPCh. 11 - Sensitivity Analysis [LO1] McGilla Golf would like...Ch. 11 - Break-Even Analysis [LO3] Hybrid cars are touted...Ch. 11 - Break-Even Analysis [LO3] In an effort to capture...Ch. 11 - Prob. 25QPCh. 11 - Operating Leverage and Taxes [LO4] Show that if we...Ch. 11 - Scenario Analysis [LO2] Consider a project to...Ch. 11 - Sensitivity Analysis [LO1] In Problem 27, suppose...Ch. 11 - Prob. 29QPCh. 11 - Prob. 30QP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.Similar questions
- İ would like to be sure about my answer.arrow_forwardASAP!! The most likely outcomes for a particular project are estimated as follows: Unit price: $50 Variable cost: $30 Fixed cost: $300,000 Expected sales: 30,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 12 percent higher or 12 percent lower than the initial estimate. The project will last for 5 years and requires an initial investment of $1 million, which will be depreciated straight-line over the project life to a final value of zero. The firm’s tax rate is 35 percent and the required rate of return is 12 percent. What is project NPV in the “best-case scenario,” that is, assuming all variables take on the best possible value? What about the worst-case scenario?arrow_forward10. An engineer is comparing three projects with the Incremental ROR method. There are revenue forecasts and cost cash flows. He uses Excel's IRR function to determine the ROR value for each project. Alternative A is 3.5% above MARR, Alternative B is 1.2% below MARR, and Alternative C = 2.4% above MARR. Which alternatives should be included in the incremental ROR analysis? A. He must include alternatives A and C in the Incremental analysis B. He must include alternatives A and B in the Incremental analysis C. He must include alternatives B and C in the Incremental analysis D. Only alternative A should be included in the incremental analysis Please solve max only answer option ASAP in 10 minutesarrow_forward
- The estimates for a project appear in the following table: Dear optimistic most likely pessimist Fixed cost($) 250,000 250,000 250,000 Annual profit ($) 20,000 15,000 8,000 Shelf life(years) 30 30 30 Residual value($) 0 00 to. Use the range of values to calculate the heavy average of benefits. b. Using the heavy average, calculate the Equivalent Average Present Value for this project. Use a MARR of 10%. Heavy average annual benefits =$ ; Average Present Value = $ 2 points. To receive credit results have to match submitted procedures. c. Send the calculations made to arrive at the answer through the Spreadsheet icon.arrow_forwardSolve this problemarrow_forwardnote : please you dont use excel.arrow_forward
- Give correct solutionarrow_forwardSuppose an opportunity arises to invest $10 million that will pay $5.5 million at the end of year 1 and $6.5 million at the end of year two. The cost of capital is 10%. Find NPV. Is the project a go? Show and explain Suppose the project’s cash flows are delayed a year, but not the outlay. How does that change your answer? Show and explain Suppose there is a cost overrun of 20%. The cash flows and their timing are the same as in part a. How does this change your answer? Show and explain. Suppose the second-year cash flow decreases to $5 million. The outlay and timing of the cash flows are the same as in part a. How does this change your answer? Show and explain. Evaluate the proposal. Would you undertake it?arrow_forwardDo not provide hand written solutionarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Essentials Of InvestmentsFinanceISBN:9781260013924Author:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.Publisher:Mcgraw-hill Education,
- Foundations Of FinanceFinanceISBN:9780134897264Author:KEOWN, Arthur J., Martin, John D., PETTY, J. WilliamPublisher:Pearson,Fundamentals of Financial Management (MindTap Cou...FinanceISBN:9781337395250Author:Eugene F. Brigham, Joel F. HoustonPublisher:Cengage LearningCorporate Finance (The Mcgraw-hill/Irwin Series i...FinanceISBN:9780077861759Author:Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Jeffrey Jaffe, Bradford D Jordan ProfessorPublisher:McGraw-Hill Education
Essentials Of Investments
Finance
ISBN:9781260013924
Author:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:Mcgraw-hill Education,
Foundations Of Finance
Finance
ISBN:9780134897264
Author:KEOWN, Arthur J., Martin, John D., PETTY, J. William
Publisher:Pearson,
Fundamentals of Financial Management (MindTap Cou...
Finance
ISBN:9781337395250
Author:Eugene F. Brigham, Joel F. Houston
Publisher:Cengage Learning
Corporate Finance (The Mcgraw-hill/Irwin Series i...
Finance
ISBN:9780077861759
Author:Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Jeffrey Jaffe, Bradford D Jordan Professor
Publisher:McGraw-Hill Education
What is Risk Management? | Risk Management process; Author: Educationleaves;https://www.youtube.com/watch?v=IP-E75FGFkU;License: Standard youtube license