Person K is the vice-president of operations at Company J, which received a request for quote of supplying 400 units per week. Employee must be permitted to perform the task for 17 times. The actual times observed were given below:

Number Actual time (minutes)
1 2.05
2 1.92
3 2.01
4 1.89
5 1.77
6 1.8
7 1.86
8 1.83
9 1.93
10 1.96
11 1.95
12 2.05
13 1.79
14 1.82
15 1.85
16 1.85
17 1.99

Performance rating is 115%, fatigue allowance is given as 8%, personal allowance is 6%, and delay allowance is 2%. Workday hour is 7.5 hours and the operators would be paid $12.50 per hour for 8 hours.

To determine: Thecost per unit for the task in direct labor cost.

Blurred answer
Students have asked these similar questions
Question 2: start ever Activity A Activity B Activity A Activity B Activity C Activity D Activity E Activity F Activity G Activity H Activity Activity C 20% 40% 40% Calculate CTE of the following process: Activity D Activity E 2 days 1 day 1 day 2 days 2 days 1 day 1 day 4 days Cycle Time Activity G Activity H 2 hours 2 hours 1 hour 2 hours 2 hours 3 hours 2 hours 4 hours 20% Process Time end event L
Q: Discuss HRM in Construction process perspective. Subject: Human resources management in construction Program: construction engineering management
Question 1Rock View Restaurant is a new fast food restaurant chain. The Operations Manager has dividedits normal drive-through service process into the following tasks:Tasks          Description              Task Time(InSeconds)       PredecessorsA                   Take order                       25                                 NoneB                   Receive payment            20                                    AC                  Gather drinks                   35                                    AD                  Gather food                      32                                   AE                   Put food etc. in bag         25                                  C,DF                   Give food to customer     10                                  B,E Currently, Rock View Restaurant has a single window with one person who takes the order,gather the food, collects the money and gives the food to the customer. This takes an average of147 seconds per customer so only 25.5…
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.