Chapter 10, Problem 2CS
Summary Introduction

Case summary:

Person K is the vice-president of operations at Company J, which received a request for quote of supplying 400 units per week. Employee must be permitted to perform the task for 17 times. The actual times observed were given below:

Number Actual time (minutes)
1 2.05
2 1.92
3 2.01
4 1.89
5 1.77
6 1.8
7 1.86
8 1.83
9 1.93
10 1.96
11 1.95
12 2.05
13 1.79
14 1.82
15 1.85
16 1.85
17 1.99

Performance rating is 115%, fatigue allowance is given as 8%, personal allowance is 6%, and delay allowance is 2%. Workday hour is 7.5 hours and the operators would be paid $12.50 per hour for 8 hours.

To determine: Whether the sample size is adequate.

Blurred answer
Students have asked these similar questions
Please use the following information to answer the following questions Alpha=0.05, Beta=D0.01, LTPD=0.3 , AQL=0.05 Question 8. What is the cut off point? 66
Question 1 This Test: 60 pts possible Submit Test Daily high temperatures in St. Louis for the last week were as follows: 92, 92, 94, 94, 95, 88, 95 (yesterday). a) The high temperature for today using a 3-day moving average = degrees (round your response to one decimal place). b) The high temperature for today using a 2-day moving average = degrees (round your response to one decimal place). c) The mean absolute deviation based on a 2-day moving average = degrees (round your response to one decimal place). %3D d) The mean squared error for the 2-day moving average = degrees (round your response to one decimal place). e) The mean absolute percent error (MAPE) for the 2-day moving average = % (round your response to one decimal place).
Question 1 Managing the Risk Management Function a) A manufacturer of computer disks took samples of 100 disks on 6 consecutive days.The number of disks with bad sectors was determined for each of these samples.The results are in the table that follows.Day Sample Size Bad    1      100      18    2      100       14    3      100       10   4       100       17   5       100       16  6         100         12Construct the p control chart table and determine whetherA) at least one point is outside of the control limitsB) a increasing trend is detectedC) a decreasing trend is detectedD) the process is in-control.
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.