Interpretation:
Calculation of value of safety stock:
Concept Introduction: Inventory management is the process of managing the company’s stock so that there are no stock-outs. It includes ordering, storing, managing the stock.Stock keeping unit is the service or product identification code, which is a machine-readable bar code. It helps the company to track the product.
a
Explanation of Solution
Safety stock is calculated by subtracting the demand value from the reorder point. Demand value is the multiple of daily demand of 25 units and the lead time is 4 days.
Hence, the safety stock is 20 units.
b
Interpretation:
Service level provided by reorder point.
Concept Introduction: Inventory management is the process of managing the company’s stock so that there are no stock-outs. It includes ordering, storing, managing the stock. Stock keeping unit is the service or product identification code, which is a machine-readable bar code. It helps the company to track the product.
b
Explanation of Solution
The service level for all the three stock keeping units.
Stock keeping unit 1:
It is calculated by adding two values. First value is the multiple of daily demand and lead-time and second value is the multiple of Z, standard deviation, and square root of lead time. However, the z value is unknown in the equation. Thus, the equation should be remodeled to find the value of Z.
From the normal distribution table, service value is 0.7881 or 78.81%.
Stock keeping unit 2:
It is calculated by adding two values. First value is the multiple of daily demand and lead-time and second value is the multiple of Z, standard deviation, and square root of lead time. However, the z value is unknown in the equation. Thus, the equation should be remodeled to find the value of
From the normal distribution table, service value is 0.9772 or 97.72%.
Stock keeping unit 3:
It is calculated by adding two values. First value is the multiple of daily demand and lead time and second value is the multiple of Z with the square root of value A. Value A is the sum attained by multiplying standard deviation during demand and the lead time and the value attained by multiplying standard deviation during demand and the lead time and the value attained by multiplying standard deviation during lead-time and square of demand. However, the z value is unknown in the equation. Thus, the equation should be remodeled to find the value of Z.
From the normal distribution, service value is 0.7704or77.04%.
Want to see more full solutions like this?
Chapter 10 Solutions
Practical Operations Management
- The chapter presented various approaches for the control of inventory investment. Discuss three additional approaches not included that might involve supply chain managers.arrow_forwardIn ABC inventory analysis, which of the following is FALSE for class A items? Select one: a. Class A items together make up a higher percentage of total inventory value ($) than either class B or class C items. b. Tighter control of class A items (than for class B or class C items) is appropriate. c. It is advisable to manage Class A items using an automated computer system. d. Class A items together make up smaller percentage of inventory items than class C items. e. Class A items individually may have any value ($): small, medium or high.arrow_forwardInventory can be: A) final products B) work-in-process C) raw materials D) A or B above E) A, B or C above T or F Logistics management is the primary process of supply chain management. T or F The Economic Production Quantity depends in part on the maximum inventory and setup costs.arrow_forward
- A drugstore uses fixed-order cycles for many of the items it stocks. The manager wants a servicelevel of .98. The order interval is 14 days, and lead time is 2 days. Average demand for one itemis 40 units per day, and the standard deviation of demand is 3 units per day. Given the on-handinventory at the reorder time for each order cycle shown in the following table, determine theorder quantities for cycles 1, 2, and 3.Cycle On Hand1 422 83 103arrow_forwardA company has estimated its economic order quantity for Part A at 3,000 units for the coming year. If ordering costs are P200 and carrying costs are P0.50 per unit per year, what is the estimated total annual usage?arrow_forwardA travel agency has a branch in Tsim Sha Tsui. The number of leaflets distributed to customers at the branch is normally distributed with a mean of 60 copies and a standard deviation of 15 copies each day. The branch operates 300 days per year. The cost of each leaflet is $4 and the carrying cost of each leaflet is 20% per year. The leaflets are supplied by a print shop with a fixed set up cost of $250 per order placement. The delivery leadtime is 6 days. Find the optimal order quantity of leaflet and the minimized total cost of ordering and carrying. Determine the time (in month) between two consecutive orders. Determine the required safety stock and reorder point to achieve a 97% service level. (Round up to the nearest integer where reasonable and appropriate.)arrow_forward
- The Atlantic Paper Company produces paper from wood pulp ordered from a lumber products firm. The paper company’s daily demand for wood pulp is a constant 8,000 pounds. Lead time is normally distributed, with an average of 7 days and a standard deviation of 1.6 days. Determine the reorder point if the paper company wants to limit the probability of a stockout and work stoppage to 2%.arrow_forwardPetromax Enterprises uses a continuous review policy to manage the inventory for one of its SKUs. The following information is available on the item. The firm operates 50 weeks in a year. Demand = 90,000 units/year Ordering Cost = $60/Order Holding Cost = $3/Unit/Order Lead Time = 10 weeks Standard Deviation of Weekly Demand = 200 units Suppose due to some recent changes to the target service level, they have determined the reorder point to be 20,000. If the inventory position of this SKU is currently 19,600, how many units should they order? (Round your answer to the nearest whole number, if it has decimals. Input 0 if they should not order now.)arrow_forwardABC Company is planning to stock its product which is classified as an inventory item. The company has developed the following information: Annual usage is 16,200 units, cost of the inventory per unit is P730; ordering cost is P220 per order; carrying cost is 28% of inventory value per year. Determine the optimum number of units per order.arrow_forward
- SF, owner of the kebab houses, uses 20 pounds of mince each day in preparing meatball. Order costs for mince are $10.00 per order, and carrying costs are 4 cents per pound per day. Lead time for each order is three days, and the mince itself costs $3.00 per pound. At what point should she reorder mince? Select one: 20 pounds remaining 60 pounds remaining 100 pounds remaining 80 pounds remaining 40 pounds remainingarrow_forwardThe amount of denim used daily by the Western Jeans Company in its manufacturing process to make jeans is normally distributed, with an average of 3,000 yards of denim and a standard deviation of 600 yards. The lead time required to receive an order of denim from the textile mill is a constant 6 days. Determine the safety stock and reorder point if the Western Jeans Company wants to limit the probability of a stockout and work stoppage to 5%.arrow_forwardWhat are the alternate inventory classifications names for cycle, buffer, in-transit, and speculative stock? Group of answer choices raw materials, anticipation, in-transit, and decoupling stock base, safety, pipeline, and speculative stock normal, extra, mobile, and speculative stock base, safety, pipeline, and psychic stockarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning