What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Normal Crash Activity Time (days) Time (days) A B C D E 6 8 4 5 8 5 6 3 3 5 Normal Cost Activity A B C D E $900 $300 $500 $900 $1,000 Total Cost with Crashing Immediate Predecessor(s) By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.) The total cost of crashing the project by 4 days is $. (Enter your response as a whole number.) $1,000 $400 $600 $1,200 $1,600 Each Activity Should be Reduced BY (days) 00000 || | | <0

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
icon
Related questions
Question
What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days?
Normal
Crash
Activity Time (days) Time (days)
A
BUDI
The total cost of crashing the project by 4 days is $
C
E
68458
5
6335
Activity
BCDE
Normal
Cost
By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below.
(Enter your responses as whole numbers.)
с
$900
$300
$500
$900
$1,000
Total Cost
with Crashing Immediate Predecessor(s)
$1,000
$400
$600
$1,200
$1,600
(Enter your response as a whole number.)
Each Activity Should be
Reduced BY
(days)
| | | < 0
Transcribed Image Text:What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Normal Crash Activity Time (days) Time (days) A BUDI The total cost of crashing the project by 4 days is $ C E 68458 5 6335 Activity BCDE Normal Cost By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.) с $900 $300 $500 $900 $1,000 Total Cost with Crashing Immediate Predecessor(s) $1,000 $400 $600 $1,200 $1,600 (Enter your response as a whole number.) Each Activity Should be Reduced BY (days) | | | < 0
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 6 steps with 8 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,