Sarah Chang is the owner of a small electronics company. In six months, a proposal is due for an electronic timing system for the next Olympic Games. For several years, Chang’s company has been developing a new microprocessor, a critical component in a timing system that would be superior to any product currently on the market. However, progress in research and development has been slow, and Chang is unsure whether her staff can produce the microprocessor in time. If they succeed in developing the microprocessor (probability p1), there is an excellent chance (probability p2) that Chang’s company will win the $1 million Olympic contract. If they do not, there is a small chance (probability p3) that she will still be able to win the same contract with an alternative but inferior timing system that has already been developed. If she continues the project, Chang must invest $200,000 in research and development. In addition, making a proposal (which she will decide whether to do after seeing whether the R&D is successful) requires developing a prototype timing system at an additional cost. This additional cost is $50,000 if R&D is successful (so that she can develop the new timing system), and it is $40,000 if R&D is unsuccessful (so that she needs to go with the older timing system).   Suppose now that this is a relatively big project for Chang. Therefore, she decides to use expected utility as her criterion, with an exponential utility function. Using some trial and error, see which risk tolerance changes her initial decision from “go ahead” to “abandon” when p1= 0.4, p2 = 0.8, and p3 = 0.1.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Sarah Chang is the owner of a small electronics

company. In six months, a proposal is due for an

electronic

timing system for the next Olympic

Games. For several years, Chang’s company has been

developing a new microprocessor, a critical component

in a timing system that would be superior

to any product currently on the market. However,

progress in research and development has been

slow, and Chang is unsure whether her staff can

produce the microprocessor

in time. If they succeed

in developing the microprocessor (probability

p1), there is an excellent chance (probability p2) that

Chang’s company will win the $1 million Olympic

contract. If they do not, there is a small chance

(probability p3) that she will still be able to win the

same contract with an alternative but inferior timing

system that has already been developed.

If she continues the project, Chang must invest

$200,000 in research and development. In addition,

making a proposal (which she will decide whether

to do after seeing whether the R&D is successful)

requires developing a prototype timing system at an

additional cost. This additional cost is $50,000 if R&D

is successful (so that she can develop the new timing

system), and it is $40,000 if R&D is unsuccessful (so

that she needs to go with the older timing system).

 

  1. Suppose now that this is a relatively big project for Chang. Therefore, she decides to use expected utility as her criterion, with an exponential utility function. Using some trial and error, see which risk tolerance changes her initial decision from “go ahead” to “abandon” when p1= 0.4, p2 = 0.8, and p3 = 0.1.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Production Plant
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.