Question
An electronic contractor is examining the amount of time his crews take to complete wiring jobs. Some crews take longer than others. For an upcoming job, a list of activities and their optimistic, most likely, and pessimistic completion times are given in the following table.
|
Days |
|
||
Activity |
a |
m |
b |
Immediate Predecessors |
A |
2 |
5 |
8 |
- |
B |
1 |
3 |
5 |
- |
C |
1 |
2 |
3 |
- |
D |
5 |
6 |
7 |
C |
E |
1 |
3 |
5 |
B, D |
F |
5 |
9 |
13 |
A, E |
G |
1 |
2 |
3 |
A, E |
H |
2 |
5 |
8 |
F |
I |
9 |
10 |
11 |
G |
J |
13 |
15 |
20 |
G |
K |
4 |
7 |
10 |
H, I |
Use excel to answer the following;
a) Develop a project network for this problem.
b) Determine the expected duration and variance for each activity.
c) Determine the EST, EFT, LST, LFT, and slack for each activity.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 5 steps with 8 images
Knowledge Booster
Similar questions
- c) Total cost of crashing the project by 2 days = $_________ (Enter your response as an integer.)arrow_forwardPower Builders Inc. is planning for an upcoming job with a large client. They have listed the specific activities and steps to be performed, and estimated the time to complete each activity. The activities involved in the job are listed below: Activity Description of Activity Preceding Activity Estimated Time Required (in weeks) A B C D E F G H I J K Planning Meeting Obtain Permit Inspect Damage Begin Repair Work Order Additional Materials Apply for Waiver Obtain Waiver Complete Electrical Work Build Interior Partitions Onsite Testing Meet With Client -- A B A D E C, F D H G, I J 5 2 5 4 2 4 2 5 5 2 2 REQUIRED: Prepare a Gantt Chart from the facts in this time budget.arrow_forwardConsider a project that has the following tasks (with the duration measured in days): Task ID Duration Dependency A 3 14 C,F a) Draw the PERT chart for the above table. Be sure to include sequencing and identification for all tasks and events along with their time estimates. b) What is the critical path. c) What is the total expected duration time represented by the critical path. earrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.