The information for project X is shown below. What is your recommendation if the imposed penalty is $3500 for each week the project is late and dead line is week 24? Activity Preceding Normal Time K K L N J,M 8 weeks 6 weeks 1 week 5 weeks 4 weeks 6 weeks Crashing Costs 1st Week K L N M J Q Crash activity M by one week. O Crash activity N by one week. The project does not need to be crashed because it ends before the deadline. Do not crash the project because the penalty cost is higher than the minimum crashing cost. O Crash activity L by one week. $4100 3250 450 3000 500 4000 2nd Week 450 3500 4000

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Please don't provide handwritten solution ..... 

The information for project X is shown below. What is your recommendation if the imposed penalty is $3500 for each week the project is
late and dead line is week 24?
Activity
K
L
N
M
J
Preceding
Normal Time
8 weeks
6 weeks
1 week
5 weeks
4 weeks
6 weeks
Crashing Costs
1st Week
$4100
3250
450
3000
500
4000
2nd
Week
K
K
L
N
J,M
Crash activity M by one week.
Crash activity N by one week.
The project does not need to be crashed because it ends before the deadline.
Do not crash the project because the penalty cost is higher than the minimum crashing cost.
Crash activity L by one week.
450
3500
4000
Transcribed Image Text:The information for project X is shown below. What is your recommendation if the imposed penalty is $3500 for each week the project is late and dead line is week 24? Activity K L N M J Preceding Normal Time 8 weeks 6 weeks 1 week 5 weeks 4 weeks 6 weeks Crashing Costs 1st Week $4100 3250 450 3000 500 4000 2nd Week K K L N J,M Crash activity M by one week. Crash activity N by one week. The project does not need to be crashed because it ends before the deadline. Do not crash the project because the penalty cost is higher than the minimum crashing cost. Crash activity L by one week. 450 3500 4000
Expert Solution
steps

Step by step

Solved in 4 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.