Product A is an end item and is made from two units of B and four of C. B is made of three units of D and two of E. C is made of t units of F and two of E. A has a lead time of one week. B, C, and E have lead times of two weeks, and D and F have lead times of three weeks. If 110 units of A are required in Week 10. develop the MRP planning schedule, specifying when items are to be ordered and receiv There are currently no units of inventory on hand. (Leave no cells blank-be certain to enter "0" wherever required.) Item A OH=0 LT=1 SS-0 Q=LAL Item B OH=0 LT=2 SS-0 Q=LAL Item C OH=0 LT=2 SS=0 Q=L4L Item D OH=0 LT=3 Period Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Net requirements 1 2 3 4 5 6 7 8 9 10

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
100%

Please assist with Homework Chapter 21 Problem 9. I keep getting the calculations mixed up. Thank you. Please provide step by step explantion so I can use it for notes

Product A is an end item and is made from two units of B and four of C. B is made of three units of D and two of E. C is made of two
units of F and two of E.
A has a lead time of one week. B, C, and E have lead times of two weeks, and D and F have lead times of three weeks.
If 110 units of A are required in Week 10. develop the MRP planning schedule, specifying when items are to be ordered and received.
There are currently no units of inventory on hand. (Leave no cells blank-be certain to enter "0" wherever required.)
Item A
OH=0
LT=1
SS-0
Q=LAL
Item B
OH=0
LT=2
SS-0
Q=LAL
Item C
OH=0
LT=2
SS=0
Q=LAL
Item D
OH=0
LT=3
Period
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
1 2 3 4 5 6 7 8 9 10
Transcribed Image Text:Product A is an end item and is made from two units of B and four of C. B is made of three units of D and two of E. C is made of two units of F and two of E. A has a lead time of one week. B, C, and E have lead times of two weeks, and D and F have lead times of three weeks. If 110 units of A are required in Week 10. develop the MRP planning schedule, specifying when items are to be ordered and received. There are currently no units of inventory on hand. (Leave no cells blank-be certain to enter "0" wherever required.) Item A OH=0 LT=1 SS-0 Q=LAL Item B OH=0 LT=2 SS-0 Q=LAL Item C OH=0 LT=2 SS=0 Q=LAL Item D OH=0 LT=3 Period Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Net requirements 1 2 3 4 5 6 7 8 9 10
SS=0
Q=LAL
Item E
OH = 0
LT=2
SS=0
Q=LAL
Item F
OH = 0
LT=3
SS=0
Q=L4L
Planned order receipts
Planned order releases
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Transcribed Image Text:SS=0 Q=LAL Item E OH = 0 LT=2 SS=0 Q=LAL Item F OH = 0 LT=3 SS=0 Q=L4L Planned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 5 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.