One of two alternatives will be selected to reduce flood damage in a rural community in central Arizona. The estimates associated with each alternative are available. Use B/C analysis at a discount rate of 9.00% per year over a 20-year study period to determine which alternative should be selected. For analysis purposes only, assume that the benefits of reduced flood damage are available in years 7.00, 10.00, and 18 of the study period. Initial Cost, $ Annual Maintenance, $/Year Reduced Flood Damage, $ (Round the final answer to four decimal places.) The AB/C ratio is [ The alternative that should be selected is the (Click to select) Retention Pond 820,000 92,000 200,000 Channel 1,900,000 30,000 650,000

Managerial Economics: Applications, Strategies and Tactics (MindTap Course List)
14th Edition
ISBN:9781305506381
Author:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Chapter17: Long-term Investment Analysis
Section: Chapter Questions
Problem 10E
icon
Related questions
Question
None
Problem 09.029 - Two alternative comparison
One of two alternatives will be selected to reduce flood damage in a rural community in central Arizona. The estimates associated with
each alternative are available. Use B/C analysis at a discount rate of 9.00% per year over a 20-year study period to determine which
alternative should be selected. For analysis purposes only, assume that the benefits of reduced flood damage are available in years
7.00, 10.00, and 18 of the study period.
Initial Cost, $
Annual Maintenance, $/Year
Reduced Flood Damage, $
(Round the final answer to four decimal places.)
The AB/C ratio is [
The alternative that should be selected is the (Click to select)
Retention Pond
820,000
92,000
200,000
Channel
1,900,000
30,000
650,000
Transcribed Image Text:Problem 09.029 - Two alternative comparison One of two alternatives will be selected to reduce flood damage in a rural community in central Arizona. The estimates associated with each alternative are available. Use B/C analysis at a discount rate of 9.00% per year over a 20-year study period to determine which alternative should be selected. For analysis purposes only, assume that the benefits of reduced flood damage are available in years 7.00, 10.00, and 18 of the study period. Initial Cost, $ Annual Maintenance, $/Year Reduced Flood Damage, $ (Round the final answer to four decimal places.) The AB/C ratio is [ The alternative that should be selected is the (Click to select) Retention Pond 820,000 92,000 200,000 Channel 1,900,000 30,000 650,000
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Knowledge Booster
Property Damage
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Managerial Economics: Applications, Strategies an…
Managerial Economics: Applications, Strategies an…
Economics
ISBN:
9781305506381
Author:
James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:
Cengage Learning