Practical Management Science
6th Edition
ISBN: 9781337406659
Author: WINSTON, Wayne L.
Publisher: Cengage,
expand_more
expand_more
format_list_bulleted
Question
Hoff & Catherine Building company has plans to build a City Centre for the Government. The stages of the project are depicted in the table below:
Activity |
Immediate Predecessor |
Duration (weeks) |
Remarks |
A |
- |
2 |
|
B |
A |
7 |
|
C |
B |
5 |
|
D |
C |
6 |
|
E |
C |
4 |
|
F |
E |
10 |
|
G |
D |
7 |
|
H |
E, G |
12 |
|
I |
C |
7 |
|
J |
F, I |
9 |
|
K |
J |
4 |
|
L |
J |
5 |
|
M |
H |
5 |
|
N |
K,L |
10 |
|
Calculate the earliest start, earliest finish, latest start, latest finish and slack time for each activity.
Calculate the critical path
How long does it take to complete the project assuming no delays?
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by stepSolved in 3 steps with 4 images
Knowledge Booster
Similar questions
- A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented below: Activity Break down both machines Clean machine 1 Clean machine 2 Re-set machine 1 Re-set machine 2 Re-calibrate both machines. Final test Designation A B с Using CPM, which activities have slack in this project? D E F G Immediate Predecessor None A A B с D and E F Time in Days 3 3 3 4 2 1 1arrow_forwardConsider the project information in the table below: Immediate Activities Duration (days) Predecessors 8. 6. C 8. 11 A 6. A F 6. H. 4 F, G, H D, E, I Draw and analyze a project network diagram to answer the following questions: What is the most that Activity E can be delayed in starting, without delaying the project? OA. 22 В. 21 OC. 19 O D. 20 O E. 18 5. A Barrow_forwardBuild a PERT Network Diagram for a 3-month project with 6 activities (A to F) and 5 nodesarrow_forward
- Solve the following problem using PERT or CPM.arrow_forwardRequired: Develop a schedule for hiring new employees. What is thetotal cost of this schedule?arrow_forward1. Draw network diagram neatly using this chart provided: Activity Predecessor Normal time Normal cost Crash time Crash cost Max Crash Time Slope A 5 $200 4 $350 B A 8 $220 8 $220 C B 6 $250 4 $650 D A 9 $500 5 $600 E A,C 10 $150 9 $500 F E 10 $500 9 $650 G D,F 8 $400 6 $900arrow_forward
- A project consisting of the following activities: Activities predece.Activities day TE M K J H G E C B G KJ G I,F D D E,C B,A| B,A A 1 3 4 6. 5 2 3 9 6 2 4 3 5 1- Draw the network diagram of the project 2- Calculate (Es) and (Lc) the project events 3- Select the critical path 4 - What is the minimum time required to complete the project?arrow_forwardThe product development group at “Griffin” Company has already worked on new computer software products that has potential to know a large market share. Via an outside source, London Management has learned that a competitor is working to bring a similar product to market. As a result, London's top management increased its pressure on the product development group. Group leaders have turned to CPM / PERT as an aid to scheduling remaining activities before new products can be brought to market. The estimated time of activity in a day is as follows Question: Create an initial network Find the cost and the duration Determine the path and critical activitiesarrow_forwardJamison Day Consul tants has been entrusted with thetask of evaluating a business plan that has been divided into foursections- marketing, finance, operations, and human resources.Chris, Steve, Juana, and Rebecca form the evaluation team. Each of them has expertise in a certain field and tends to finish thatsection faster. The estimated times taken by each team memberfor each section have been outlined in the following table. Furtherinformation states that each of these individuals is paid $60/hour.a) Assign each member to a different section such that JamisonConsultants's overall cost is minimized.b) What is the total cost of these assignments?arrow_forward
- A renovation of the gift shop at Orlando Amway Center has six activities (in hours). For the following estimates of a, m, and b, calculate the expected time and the standard deviationfor each activity:arrow_forwardPlease don't provide handwriting solutionarrow_forwardKelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are given in the following table: Time (days) Activity a 3 5 3 4 1 2 7 TH 3 10 10 ABCD E F G H I K 61 525DE5 13 m Activity A 3 7 11 15 9 This exercise contains only part a. a) Based on the activity time estimates, the expected times and variance for each of the activities are: (Round your responses to two decimal places.) b 9 5 3 8 5 13 49127 13 Immediate Predecessor(s) Expected Time C B, D A, E A, E F G C H, I Variancearrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.