Practical Management Science
6th Edition
ISBN: 9781337406659
Author: WINSTON, Wayne L.
Publisher: Cengage,
expand_more
expand_more
format_list_bulleted
Question
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by stepSolved in 1 steps
Knowledge Booster
Similar questions
- Information provided is for end of day 6: 1. What is the actual cost so far? 2. What is the estimated time to completion? ( show formula and working) 3. What is the estimated cost to completion? ( show formula and working)arrow_forwardActivity Predecessors 1 Description Duration Start job 1 2 1 Relocate electric 6 3 1 4 3 5 4 6 4 7 5,6 Excavate Install pipe section #1 10 Backfill section #1 Install pipe section #2 Backfill section #2 8 6 Test pipe sections 9 7,8 10 2,8 Grade and sod Install manhole 5652837 12 11 10 Test relocated electric 32 12 9.11 Final inspection 1 Of the following images which is the correct Activity on Node (AON) rendering of this project? (Keep in mind that within each box the top number is the activity and the bottom number is the duration)arrow_forwardMake a diagram please. don't just put text I need help creating a Work breakdown structure showing a revamp of the MBA program • Project notebook. Sections to include, but not be limited to:1. Stakeholders Engagement/Management2. Team Members and their roles3. Vision/Mission/Strategy/Goals4. SOW, Project Milestones, WBS (Actions and Deliverables)5. Project Justification6. Key Issues, Risks and Opportunities7. Contingency Plans8. Change Leadership and Communication Plans9. Your assessment of the project’s success or potential successarrow_forward
- Question Two: A shop works a 400-minute day. The manager of the shop wants an output of 200 units per day for the assembly line that has the elemental tasks shown in the table. Do the following: а- What is the cycle time and what is the minimum number of workstations required b- Construct the precedence diagram. C- Assign tasks according to the most following tasks rule.. d- what is the efficiency of such line Immediate Task Task Predecessor Time a 0.5 b a 1.4 C a 1.2 a 0.7 b, c 0.5 f d 1.0 e 0.4 h 0.3 0.5 e, i 0.8 k h, j 0.9 k 0.3arrow_forwardQuestion 2: start ever Activity A Activity B Activity A Activity B Activity C Activity D Activity E Activity F Activity G Activity H Activity Activity C 20% 40% 40% Calculate CTE of the following process: Activity D Activity E 2 days 1 day 1 day 2 days 2 days 1 day 1 day 4 days Cycle Time Activity G Activity H 2 hours 2 hours 1 hour 2 hours 2 hours 3 hours 2 hours 4 hours 20% Process Time end event Larrow_forwardTask No. Task Name Task Duration(Days) Immediate Predecessor task 1 Preliminary system description 40 — 2 Develop specifications 100 1 3 Client approval 50 2 4 Develop input-output summary 60 2 5 Develop alarm list 40 4 6 Develop log formats 40 3, 5 7 Software definition 35 3 8 Hardware requirements 35 3 9 Finalize input-output summary 60 5, 6 10 Analysis performance calculations 70 9 11 Automatic turbine startup analysis 65 9 12 Boiler guides analysis 30 9 13 Fabricate and ship 200 10, 11, 12 14 Software preparation 80 7, 10, 11 15 Install and check 130 13, 14 16 Termination and wiring lists 30 9 17 Schematic wiring lists 60 16 18 Pulling terminals and cables 60 15, 17 19 Operational test 125 18 20 First firing 1 19 Therefore, Critical Path = 1-2-4-5-6-9-10-13-15-18-19-20 Note: tj is the original duration of task j; dj is the minimum duration of task j. Expediting Costs ($1,000) and Limits Task no.…arrow_forward
- Time estimates Expected Variance Activity Optimistic Most Likely Pessimistic Time (ET) (6²) A B C D Start a 31 44 48 22 m 40 50 60 31 B b 4574 49 56 72 34 D End 4) What is the estimated standard deviation of the expected time for the critical path? A. 2.83 days B. 5 days C. 8 days D. 20 days E. 25 daysarrow_forwardQuestionarrow_forward7arrow_forward
- Question Mr Mustafa, manager of project RTS of Syarikat Aurora Sdn Bhd. Is in the process of designing a problem that is clients can use in the job-finding process. Some of the activities include preparing progress report, site inspections, documents validation and appointments to see prospective employers, researching companies and industries, and so on. Some of the information on the activities appears in the following table: Activity A B C D E F G H I J K L a 8 6 3 10 6 9 6 14 10 6 4 1 Time (days) m 10 7 3 20 7 10 7 15 11 7 7 2 b 12 9 4 30 8 11 10 16 13 8 8 4 Answer all questions below: a) Construct a PERT network for this problem. b) Determine the expected times and variances for each activity / c) Determine ES,EE,LS,LF and slack time for each activity. ( d) Determine the critical path and project completion time. ( e) Determine the probability that the project will be finished in 70 days. f) Determine the probability that the project will be finished in 80 days. g) Determine the…arrow_forwardCase Study: Designing a Comprehensive Employee Orientation Program for XYZ Global Corporation Background:XYZ Global Corporation, a multinational conglomerate, is undergoing a significant expansion, with new hires joining from diverse cultural backgrounds and professional experiences. The Human Resources department has been tasked with designing a comprehensive employee orientation program to ensure a seamless onboarding experience for all employees. Question- Identify the key topics and information to be covered during the orientation.arrow_forwardQuestion 12 A project oriented process flow is more flexible than an assembly line orientation. Group of answer choices a. True b. Falsearrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.