(c) Calculate the amount required for the first 10 weeks , mid 10 weeks and the last 10 weeks.
Q: 3.13. Given the following data, can an order for 40 more units for delivery in week 5 be accepted?…
A: Given data- On-hand inventory= 0 Week 1 2 3 4 5 6 7 8 Customer Orders 70 10 50 40 10 15 20 15…
Q: Waht is the implication of nutrition and hygiene programs as part of occupational health. Create a…
A:
Q: Write the complete model for each the following: (a) ARMA(p = 0, q = 2) × (P = 1, Q = 2)d=4
A: Given, ) ARMA(p = 0, q = 2) × (P = 1, Q = 2)d=4
Q: Week 1 2 3 4 5 6 Value 19 14 16 11 18 14 . Construct a time series plot. Time Series Value 20 F10 4…
A: 1) plot 1 horizontal b) Time period Actual Value(A) Moving avg. Forecast(F) Forecast error…
Q: Explain how the quality and timing of information received from the design consultants would…
A: A quantity conveyor can be referred to as a person who possesses expert knowledge on costs of…
Q: Assignment:
A: Product failures are a very common phenomenon in the marketing world. There have been many companies…
Q: Using the scheduled receipts, calculate the ATP. There are 45 units on hand.
A: Available to promise is an important concept of supply chain management, which projects the amount…
Q: the administration of the reward system, i.e. whether shirt or long term and whethervthe pay-outs…
A: A reward system is a subsystem of compensation management. Rewards and incentives are vital to…
Q: 1) Table below is for a product with 150 unit lot size. The current on-hand inventory is 110 units.…
A: given,
Q: You have developed the following simple productstructure of items needed for your gift bag for a…
A: Given Number of attendees forecasted = 200
Q: An electric hand drill would take 15, 40, 10, 20, 50, and 30 units in the next 6 weeks. The…
A: The MPs record for the production of drill log is as under: Drill Log 1 2 3 4 5 6 Forecast…
Q: Assume that Product Z is made of two units of A and three units of B. A is made of four units of C…
A:
Q: c) Project life cycle diagrams d) Selection method for project (Names and Formulas)
A: Inventory management is a systematic approach to sourcing, storing, and selling inventory both raw…
Q: Two months ago Harry was asked to prepare cash budget with a very short notice. He did an excellent…
A: Motivation refers to what states why individuals or animals start off, continue, or end or terminate…
Q: 1.The foreman determined the quantity of materials used in the project, as well as the amount of…
A: Two measures are given in the given question. 1. Quantity of used material 2. Quantity of waste…
Q: Describe the following types of bills of material:a. Product tree.b. Multilevel bill.c. Single-level…
A: A structure that consists of the list of all the parts and their quantities required to manufacture…
Q: 8. When will the manager need to place their Second order? write the week number example: 1
A: I have created the table based on the given information in the question,
Q: What is the significance of quality and suitable development and delivery schedules?
A: Quality is important for impressing your customers and maintaining their confidence so that they…
Q: You have been asked to forecast the sales of your lead product over the next 2 years. You have…
A: Sales forecasting is the process of anticipating future revenue by predicting how much goods or…
Q: company that produces golf carts has just received an order for 200 carts, which must be ready for…
A: Material Resource Planning (MRP) is a data framework that converts ace timetable necessities for the…
Q: What are focus groups and how could they contribute to requir
A: A focus group is a promoting research instrument in which a little gathering of individuals…
Q: It differs from what term? Give an example of a target that was met efficiently and effectively.
A: The primary goal of efficiency is to achieve the task at the lowest possible cost and with the least…
Q: Which are the types of Manufacturing Processes and Scheduling Approaches?
A: The manufacturing process is described as a process that converts the raw materials into final…
Q: The Cookie Monster sells oatmeal cookies for $1.30 per pound and peanut butter cookies for $1.60 per…
A: In the given question, the oatmeal cookies sell at $1.30 per pound and peanut butter cookies sell at…
Q: St. Clair's pre-school creates a budget based on 6 classrooms with an average class size of 15…
A: A small introduction about promotion Promotions are related to the full collection of actions that…
Q: Task 3.1 Task 4.1 Task 5.1 Resource 3 Resource 3 Resource 1 Task 1 Task 2 Task 3.2 Finished Resource…
A: Here, for each activity, we have activity duration in the form of Hours per unit, Resource related…
Q: what are the 4m's (manpower, machines, material, method) of manufacturing
A: The 4M's are very important for business opportunities. That is without 4M's business was not run…
Q: A company that produces golf carts has just received an order for 200 carts, which must be ready for…
A: An assembly time chart shows when production or procurement should be done as per the lead time for…
Q: The Sales&Operations (S&OP) process is designed to produce a plan that all departments within the…
A: It is very important to understand where sales and Operations Planning, is a monthly integrated…
Q: Sales last year for a department were $98,600. This year planned sales are forecast to decrease by…
A: Find the Given details below: Given details: Sales 98600 $/Year Decrease 1.5 %
Q: In the process of selection, the step that follows the short-listing is normally the?
A: The selection of the right team, who have the right set of qualities and traits to perform the tasks…
Q: Define the following terms:
A: FILL OR KILL ORDER It is an interesting concept which has emerged from order types like buy order or…
Q: What is the significant effect of poor construction of conclusion and recommendation?
A: Conclusions are the interpretation of the findings or results. The key points are discussed in the…
Q: Calculate the expected time and the variance - a - 47 weeks b - 167 weeks m - 67 weeks
A: Given: Optimistic time (a) = 47 weeks Pessimistic time (b) = 167 weeks Most likely time (m) = 67…
Q: Alan Industries is expanding its product line to include three new products: A, B, and C. These are…
A: Formulate a spreadsheet s shown below to get the answer. note: to make sure that each month demands…
Q: a) Develop the time-phased product structure. b) Produce the MRP for fulfilling the order.
A: The following steps have time phased structure and MRP for fulfilling the order
Q: An end item’s demand forecasts for the next 10 weeks are 30, 30, 30, 30, 20, 20, 30, 30, 30, and 30…
A: A Master Production Schedule can be referred to as a plan where the commodities can be scheduled as…
Q: a. Contrast the meanings of the terms job enlargement and job enrichment. b. What is the purpose of…
A: Delegation refers to the process of assigning the responsibility to the particular job profile along…
Q: How did the requirements prioritization activity go? What were the issues and challenges? How can…
A: Requirement prioritization is used to set requirements in a project so that engineers and…
Q: What it the importance of quality and appropriate schedules for development and delivery .
A: Quality is basic to fulfilling your clients and holding their dedication so they keep on purchasing…
Project Management
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
- A B с D E FL ד G H J K L M N P R S T U V 1 On Week 3 Forecast 4 2 a) Smell Fresh Customer Orders hand 1 2 20 20 5 3 5 PAB 20 50 30 3222 4 5 6 7 8 Problem 6: Georgia Clay and Gravel was updating the MPS record for one of its products, Smell Fresh Cat Litter. Partially-completed MPS time-phased record is given below. 20 30 30 30 30 30 Week 10 30 50 20 40 10 Item: Smell Fresh On hand 1 6 Available to Promise 7 MPS 50 50 50 50 Forecast 20 8 MPS lot size = 50 9 20 10 On Week hand 2 3 4 5 6 7 8 9 20 53 43 78 30 30 30 30 30 3220 2233 -250 30 10 30 50 6 8 45 12 13 14 PAB 15 11 b) Smell Fresh Forecast Customer Orders Available to Promise 16 MPS 17 MPS lot size=50 18 19 20 21 23 24 222 Orders Projected available balance Available-to-promise MPS MPS Lot Size = 50. 50 20 40 10 50 50 50 a) Complete the MPS time-phased record (the first table on the left). The following events occurred during week 1: • Actual demand during week 1 was 25 units. • Marketing forecasted that 40 units would be needed for…41. A manager is going to purchase new processing equipment and must decide on the number of spare parts to order with the new equipment. The spares cost $200 each, and any unused spares will have an expected salvage value of $50 each. The probability of usage can be described by this distribution: Number 0 1 2 3 Probability .10 .50 .25 .15 If a part fails and a spare is not available, two days will be needed to obtain a replacement and install it. The cost for idle equipment is $500 per day. What quantity of spares should be ordered? Page 553 a. Use the ratio method. b. Use the tabular method (see Table 12.3).1 2 3456780 9 10 A Unit Cost Benefit A B C Solution Multiple Choice B Activity 1 $15 Where are the output cells located? F10 Contribution per Unit 1 2 1 B10:C10 Activity 1 2 B2:C2, B5:C7, and F5:F7 с Activity 2 $20 231 None of the answer choices are correct. Activity 2 4 D Totals 10 16 6 SOE E >= >= F Needed 10 966 Total Cost $110
- Transcribed Image Text On hand: 35 Planning time fence: 10 Lot size: 200 Demand time fence: 2 Period 2 4 6. 7 9. 10 11 12 Forecast 30 40 40 50 40 40 30 40 40 50 40 40 Customer Orders 31 35 29 21 17 14 33 11 5 2 Projected Available Available to Promise MPS 200 200 3. a. Given the following master schedule, fill in the projected available and availableto promise rows: b. A customer wants an order of 100 in period 4. What can you tell him?c. The customer from part (b) cancels his request, but then says he wants 120 in period 5.What do you tell him now?d. Sales has requested that you add an MPS of 200 in period 9 to cover their needs for a sales promotion. What do you tell them and why?e. What action (if any) should be taken in period 11? Why is it okay to take theaction? I only need question D and E answeredWBS Element Planned Value(PV) Earned Value(EV) Actual Cost(AC) 2.01 Airframe 48000 48000 50000 2.02 Engines 22000 21000 23000 2.03 Avionics 80000 60000 45000 2.04 Communications 30000 30000 30000 2.05 Tech. Manuals 42000 42000 48000 2.06 Spares 40000 35000 42000 2.07 Training 80000 80000 86000 Project Total 342000 316000 324000 Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report (October 31, 20XX) Consider the project performance report presented in figure 14.1. What valid conclusion can you draw regarding the project schedule performance as of October 31, 20XX? Select one: a. The project is $26,000 behind schedule. b. The project is 18 days behind schedule. c. The project is $26,000 ahead of schedule. d. The project is $18,000 behind schedule.Transcribed Image Text On hand: 35 Planning time fence: 10 Lot size: 200 Demand time fence: 2 Period 2 4 6. 7 9. 10 11 12 Forecast 30 40 40 50 40 40 30 40 40 50 40 40 Customer Orders 31 35 29 21 17 14 33 11 5 2 Projected Available Available to Promise MPS 200 200 3. d. Sales has requested that you add an MPS of 200 in period 9 to cover their needs for a sales promotion. What do you tell them and why?e. What action (if any) should be taken in period 11? Why is it okay to take theaction? I only need question D and E answered
- 00:53:53 C k TB Problem Qu. 5-114 (Algo) Mccabe Corporation uses the weighted-average... for September. Mccabe Corporation uses the weighted-average method in its process costing. The following data pertain to its Assembly Department Mc Graw Hill control Work in process, September 1 Units started into production during September Units completed during September and transferred to the next department Work in process, September 30 Equivalent units of production Q A 2 Required: the weighted-average method. Compute the equivalent units of production for both materials and conversion costs for the Assembly Department for September using Z option W S # 3 X F3 Materials E H command D $ 4 DOD DOO F4 Conversion R C do 5 % F U * 8 N DII F8 Units 800 8,200 7,300 1,700 ( 9 F9 K M 0 Materials 55% F10 Percent Complete 75% L H P F11 > Help command Conversion 10% 25% + 11 Save & Exit 2 F12 option 2 Sub dele1. A company that produces golf carts has just received an order for 200 carts, which must be ready for delivery at the start of week 8. Information concerning the product structure, lead times and quantities on hand is shown in the following table. Parts list for golf cart Lead time Quantity on hand Golf cart Top Base 1 1 1 0 40 20 Top Supports(4) Cover 1 1 200 0 Base Motor Body Seats (2) 2 3 2 300 50 120 Body Frame Controls Wheel assemblies(4) 1 1 1 35 0 240 You are required to: a) Construct a product tree. b) Determine the low level codes for all the components. c) Develop a material requirements plan that will provide 200 golf carts by week 8 assuming lot for lot ordering.1. A company that produces golf carts has just received an order for 200 carts, which must be ready for delivery at the start of week 8. Information concerning the product structure, lead times and quantities on hand is shown in the following table. Parts list for golf cart Lead time Quantity on hand Golf cart Top Base 1 1 1 0 40 20 Top Supports(4) Cover 1 1 200 0 Base Motor Body Seats (2) 2 3 2 300 50 120 Body Frame Controls Wheel assemblies(4) 1 1 1 35 0 240 You are required to: a) Construct a product tree.
- ABD Sdn Bhd is a consultation company to produce electronic circuit devices. As one of the prominent consultation company this company required to provide excellent service to meet customer demand. Table Q5 shows the planning for the new product development project received recently by this company. Table Q5 Activity Actions Preceding Time (weeks) activities A Product Conception 4 В Material Selection 3 Process Conception Production System Design Prototype tests C А, В D 1 E C 5 F Procurement D G Tool and machine E,F acquisition H Product installation G and testing Construct a PERT network diagram for Table Q5. State the early start (ES), late start (LS), early finish (EF) and late finish (LF) in the diagram. b. Find the critical path in the network diagram11. A manager must decide which type of machine to buy, A, B, or C. Machine costs are as follows: Machine A B C Product forecasts and processing times on the machines are as follows: PROCCESSING TIME PER UNIT (minutes) Product 1 2 3 4 Cost $40,000 $30,000 $80,000 Annual Demand 16,000 12,000 6,000 30,000 A 3452 2 B 4 4 6 2 C 2 3 4 1 a. Assume that only purchasing costs are being considered. Which machine would have the low- est total cost, and how many of that machine would be needed? Machines operate 10 hours a day, 250 days a year. b. Consider this additional information: The machines differ in terms of hourly operating costs: The A machines have an hourly operating cost of $10 each, B machines have an hourly oper- ating cost of $11 each, and C machines have an hourly operating cost of $12 each. Which alternative would be selected, and how many machines, in order to minimize total cost while satisfying capacity processing requirements?3. Normal Loss - FIFO The Nasiraan Manufacturing operates two consecutive producing departments, A and B. Th following quantity data are on Dep't A's production in March: WIP, beg Placed in Process 5,000 units, 1/5 done 50,000 units WIP, end 3,000 units, 2/3 done TIC Transferred out 49,500 Compute for the equivalent units of production under each of the following independer assumptions using FIFO costing: [a] Loss occurs at the beginning of the process: [b] Loss occu during process; [c] Loss is occurs when goods are ½ done; [d] loss occurs at the end of proces 4. Abnormal Loss - Average The Loosan Manufacturing reported the quantity data from its operations for January: WIP, beg 7,500 units, 1/4 complete Placed in Process 75,000 units WIP, end 4,500 units, 2/5 complete Transferred out Compute for the equivalent units of production under each of the following independer assumptions using Average costing: [a] Loss occurs at the beginning of the process; [b] Lo occurs during process; [c]…