Activity-Based
The total factory overhead for Bardot Marine Company is budgeted for the year at $954,400, divided into four activities: fabrication, $456,000; assembly, $208,000; setup, $158,400; and inspection, $132,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The activity-base usage quantities for each product by each activity are as follows:
Fabrication | Assembly | Setup | Inspection | |||||
Speedboat | 6,000 | dlh | 19,500 | dlh | 43 | setups | 75 | inspections |
Bass boat | 18,000 | 6,500 | 317 | 525 | ||||
24,000 | dlh | 26,000 | dlh | 360 | setups | 600 | inspections |
Each product is budgeted for 3,500 units of production for the year.
a. Determine the activity rates for each activity.
Fabrication | $fill in the blank 1 per direct labor hour |
Assembly | $fill in the blank 2 per direct labor hour |
Setup | $fill in the blank 3 per setup |
Inspection | $fill in the blank 4 per inspection |
b. Determine the activity-based factory overhead per unit for each product. Round to the nearest whole dollar.
Speedboat | $fill in the blank 5 per unit |
Bass boat |
$fill in the blank 6 per unit
|
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Activity-Based Costing Zeus Industries manufactures two types of electrical power units, custom and standard, which involve four factory overhead activities—production setup, procurement, quality control, and materials management. An activity analysis of the overhead revealed the following estimated activity costs and activity bases for these activities: Activity Activity Cost Activity Base Production setup $ 79,750 Number of setups Procurement 144,000 Number of purchase orders (PO) Quality control 256,000 Number of inspections Materials management 126,000 Number of components Total $605,750 The activity-base usage quantities for each product are as follows: Setups Purchase Orders Inspections Components Unit Volume Custom 300 1,200 2,400 400 2,000 Standard 250 400 800 300 2,000 Total 550 1,600 3,200 700 4,000 a. Determine an activity rate for each activity. Activity Rates Production Setup Procurement Quality…arrow_forwardActivity rates and product costs using activity-based costing Lonsdale Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the fixtures. These activities and their associated budgeted activity costs and activity bases are as follows: Activity BudgetedActivity Cost Activity Base Casting $594,000 Machine hours Assembly 66,500 Direct labor hours Inspecting 41,400 Number of inspections Setup 49,200 Number of setups Materials handling 27,200 Number of loads Corporate records were obtained to estimate the amount of activity to be used by the two products. The estimated activity-base usage quantities and units produced follow: Activity Base Entry Dining Total Machine hours 5,680 12,320 18,000 Direct labor hours 2,100 1,400 3,500 Number of inspections 320 580 900 Number of setups 360 240 600 Number of loads 280 520 800 Units produced 2,200 3,800 6,000…arrow_forwardActivity-Based Costing: Factory Overhead Costs The total factory overhead for Bardot Marine Company is budgeted for the year at $646,800, divided into four activities: fabrication, $288,000; assembly, $114,000; setup, $132,300; and inspection, $112,500. Bardot Marine manufactures two types of boats: speedboats and bass boats. The activity-base usage quantities for each product by each activity are as follows: Assembly 14,250 dlh 4,750 19,000 dlh Each product is budgeted for 3,000 units of production for the year. Determine the activity rates for each activity. per direct labor hour per direct labor hour Speedboat Bass boat a. Fabrication Assembly Setup Inspection Fabrication Speedboat Bass boat A 4,500 dlh 13,500 18,000 dlh per setup per inspection Setup 32 setups 238 270 setups b. Determine the activity-based factory overhead per unit for each product. Round to the nearest whole dollar. per unit per unit Inspection 56 inspections 394 450 inspectionsarrow_forward
- Greenwood Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 231,000 11,000 MHs Machine setups Number of setups $ 180,000 300 setups Production design Number of products $ 94,000 2 products General factory Direct labor-hours $ 260,000 10,000 DLHs Activity Measure Product Y Product Z Machining 9,000 2,000 Number of setups 60 240 Number of products 1 1 Direct labor-hours 9,000 1,000 6. What is the activity rate for the General Factory activity cost pool? (Round your answer to 2 decimal places.)arrow_forwardGreenwood Company manufactures two products-15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Machining Machine setups Production design General factory Activity Measure Machining Number of setups Number of products Direct labor-hours Activity Measure Machine-hours Number of setups Number of products Direct labor-hours Estimated Overhead Cost $ 210,100 $ 45,100 $ 75,000 $ 241,000 Product Y Product Z 7,100 3,900 50 60 1 2,900 7,100 Expected Activity 11,000 MHS 110 setups 2 products 10,000 DLHs 10. Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Z? (Round your intermediate calculations to 2 decimal places.…arrow_forwardActivity-Based Costing: Factory Overhead Costs The total factory overhead for Bardot Marine Company is budgeted for the year at $1,153,500, divided into four activities: fabrication, $551,000; assembly, $240,000; setup, $195,750; and inspection, $166,750. Bardot Marine manufactures two types of boats: speedboats and bass boats. The activity-base usage quantities for each product by each activity are as follows: Fabrication Assembly Setup Inspection Speedboat 7,250 dlh 22,500 dlh 52 setups 91 inspections Bass boat 21,750 7,500 383 634 29,000 dlh 30,000 dlh 435 setups 725 inspections Each product is budgeted for 5,500 units of production for the year. a. Determine the activity rates for each activity. Fabrication $fill in the blank 1 per direct labor hour Assembly $fill in the blank 2 per direct labor hour Setup $fill in the blank 3 per setup Inspection $fill in the blank 4 per inspection b. Determine the activity-based factory overhead per unit…arrow_forward
- Greenwood Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 231,000 11,000 MHs Machine setups Number of setups $ 180,000 300 setups Production design Number of products $ 94,000 2 products General factory Direct labor-hours $ 260,000 10,000 DLHs Activity Measure Product Y Product Z Machining 9,000 2,000 Number of setups 60 240 Number of products 1 1 Direct labor-hours 9,000 1,000 11. Using the plantwide overhead rate, what percentage of the total overhead cost is allocated to Product Y and…arrow_forwardGreenwood Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 235,200 12,000 MHs Machine setups Number of setups $ 73,600 160 setups Production design Number of products $ 80,000 2 products General factory Direct labor-hours $ 295,200 12,000 DLHs Activity Measure Product Y Product Z Machining 7,600 4,400 Number of setups 40 120 Number of products 1 1 Direct labor-hours 7,600 4,400 11. Using the plantwide overhead rate, what percentage of the total overhead cost is allocated to Product Y and Product…arrow_forwardGreenwood Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 227,700 11,000 MHs Machine setups Number of setups $ 153,900 270 setups Production design Number of products $ 91,000 2 products General factory Direct labor-hours $ 257,000 10,000 DLHs Activity Measure Product Y Product Z Machining 8,700 2,300 Number of setups 60 210 Number of products 1 1 Direct labor-hours 8,700 1,300 7. Which of the four activities is a batch-level activity? multiple choice Machining activity General…arrow_forward
- Greenwood Company manufactures two products-13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity- based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Machining Machine setups Production design General factory OWS KTOP- Ows Activity Measure Machining Number of setups Number of products Direct labor-hours Total manufacturing overhead cost +1 (252) 484-2153 Oh nun Activity Measure Machine-hours. Number of setups Number of products Direct labor-hours FEB 22 Product Y Product Z 8,800 3,200 40 240 1 1 8,800 3,200 NT Submit Check my work A Oarrow_forwardPlease do not give image formatarrow_forwardGreenwood Company manufactures two products-13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity- based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Machining Machine setups Production design General factory TOP- OWS Activity Measure Machining Number of setups Number of products Direct labor-hours Machining cost Activity Measure Machine-hours Number of setups Number of products Direct labor-hours Product Y +1 (252) 484-2153 Oh nun % Product Y Product Z 8,800 3,200 40 240 1 1 8,800 3,200 12. Using the ABC system, what percentage of the Machining costs is assigned to Product Y and Product Z? (Round your in calculations to 2 decimal places. Round your answers to 2 decimal places.) Product Zarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education