A generating plant has a maximum capacity of 100 kW and costs Rs 2,000,000.The annual fixed charges are 12% consisting of 6% interest, 4% depreciation and 2% taxes. Find the fixed charges per kWh if the load factor is (i) 100% and (ii) 60%.

Electricity for Refrigeration, Heating, and Air Conditioning (MindTap Course List)
10th Edition
ISBN:9781337399128
Author:Russell E. Smith
Publisher:Russell E. Smith
Chapter7: Alternating Current, Power Distribution, And Voltage Systems
Section: Chapter Questions
Problem 8RQ
icon
Related questions
Question
A generating plant has a maximum capacity
of 100 kW and costs Rs 2,000,000.The
annual fixed charges are 12% consisting of
6% interest, 4% depreciation and 2% taxes.
Find the fixed charges per kWh if the load
factor is (i) 1o0% and (ii) 60%.
Transcribed Image Text:A generating plant has a maximum capacity of 100 kW and costs Rs 2,000,000.The annual fixed charges are 12% consisting of 6% interest, 4% depreciation and 2% taxes. Find the fixed charges per kWh if the load factor is (i) 1o0% and (ii) 60%.
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Maximum power transfer theorem
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, electrical-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Electricity for Refrigeration, Heating, and Air C…
Electricity for Refrigeration, Heating, and Air C…
Mechanical Engineering
ISBN:
9781337399128
Author:
Russell E. Smith
Publisher:
Cengage Learning
Power System Analysis and Design (MindTap Course …
Power System Analysis and Design (MindTap Course …
Electrical Engineering
ISBN:
9781305632134
Author:
J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher:
Cengage Learning